20 chapters · 1,347 sections in this title.
ORS 543.010 Definitions for ORS 543.010 to 543.610
1.2K chars
As used in ORS 543.010 to 543.610: (1) Actual original cost includes the sum paid to the state at the time the application was made for a preliminary permit; the sum paid or secured to be paid to the state by the applicant for license at the time such application was made; such…
ORS 543.012 Applicability of chapter to reauthorization of existing hydroelectric project
0.6K chars
(1) Except for the provisions of ORS 543.300, 543.310, 543.430, 543.440, 543.610, 543.650 to 543.685, 543.710, 543.720, 543.730 and 543.990, nothing in this chapter shall apply to the reauthorization of an existing project. (2) All references in ORS 543.300, 543.310, 543.430, 543…
ORS 543.013 Applicability of chapter and ORS chapter 543A to ocean renewable energy facility
0.6K chars
The provisions of this chapter and ORS chapter 543A do not apply to an ocean renewable energy facility as defined in ORS 274.870 if: (1) The facility is located within Oregons territorial sea, as defined in ORS 196.405; or (2) The facility is in an estuary, unless any part of th…
ORS 543.015 Policy
0.7K chars
The Legislative Assembly declares that it is the policy of the State of Oregon: (1) To protect the natural resources of this state from possible adverse impacts caused by the use of the waters of this state for the development of hydroelectric power. (2) To permit siting of hydro…
ORS 543.017 Minimum standards for development of hydroelectric power; public interest considerations; rules
4.7K chars
(1) In order to carry out the policy set forth in ORS 543.015, the following minimum standards shall apply to any action of the Water Resources Commission relating to the development of hydroelectric power in Oregon: (a) The anadromous salmon and steelhead resources of Oregon sha…
ORS 543.050 Powers of Water Resources Commission as to permits, licenses, investigations, reports, forms and examination of records
2.2K chars
The Water Resources Commission may: (1) Issue preliminary permits, as provided in ORS 543.210 to 543.250, to any person qualified to become a licensee. (2) Issue licenses, as provided in ORS 543.260, to citizens of the United States, associations of citizens, or private corporati…
ORS 543.055 Hearings and witnesses
1.5K chars
(1) The Water Resources Commission may hold hearings and take testimony orally, by deposition or in such other form as the commission considers satisfactory, either within or without this state. The Water Resources Commission may require, by subpoena, the attendance of witnesses …
ORS 543.060 Investigations; access to project, maps, books and other project data
0.4K chars
The Water Resources Commission, the Water Resources Director or any employee of the Water Resources Department, at all reasonable times, shall have free access to any project, addition or betterment during or after construction or acquisition, and to all maps, plans, profiles, es…
ORS 543.075 Definitions for ORS 543.075 to 543.092
1.6K chars
As used in ORS 543.075 to 543.092: (1) 1998 dollar means a dollar amount that when adjusted for inflation or deflation equals the value of a dollar in 1998. (2) Holder means a person authorized to operate a hydroelectric project under the authority of either a time-limited wa…
ORS 543.078 Annual fee for hydroelectric project
2.2K chars
(1) On or before January 1 of each year, each holder shall pay to the State of Oregon an annual fee for each hydroelectric project that is subject to this section. The annual fee required by this section shall be based on the theoretical horsepower specified in the water right fo…
ORS 543.080 Project specific fees; summary of project specific expenditures
5.6K chars
(1) In addition to the annual fee set forth in ORS 543.078, a holder may be required to pay project specific fees. (2) Project specific fees are fees that compensate a state agency for the agencys reasonable and necessary oversight of a holders implementation of the protection,…
ORS 543.082 Invoice for fees; overdue fee; interest on delinquent fees
1.8K chars
(1) At least 45 days before the fees required under ORS 543.078 or 543.080 become due, the Water Resources Department shall issue invoices to the holder for each fee. (2) If any holder fails to pay the fees required under ORS 543.078 or 543.080 within 15 days after the date speci…
ORS 543.085 Periodic review of annual fee
1.8K chars
(1) At least once every eight years the Water Resources Director shall appoint a review panel to review the amount of the annual fee established under ORS 543.078. The review panel shall consist of at least one representative from the following and others at the directors discre…
ORS 543.088 Payment of costs or fee for reauthorization or relicensing of project
3.3K chars
(1) Notwithstanding ORS 543A.405 and 543A.410, during each year of the interim period established in subsection (2) of this section, any licensee or water right certificant seeking reauthorization of a state water right to operate a federally licensed hydroelectric project shall …
ORS 543.090 Payment of expenses of Hydroelectric Application Review Team for project operating under federal license and state power claim or uncertificated claim
1.1K chars
(1) Any project operating under a hydroelectric license issued by the Federal Energy Regulatory Commission and concurrently operating under the authority of a power claim or uncertificated claim shall pay all expenses related to the review and decision of a Hydroelectric Applicat…
ORS 543.092 Amendment of hydroelectric water right or claim; rules; unilateral amendment of power claim or uncertificated claim to assess project specific fees
0.8K chars
(1) Upon the request of the holder and the approval of the Water Resources Department, a hydroelectric water right or claim may be amended. (2) The Water Resources Department shall develop rules governing the process by which a hydroelectric water right or claim may be amended. A…
ORS 543.095 Challenges to certain statutes related to hydroelectric projects
1.5K chars
(1) As used in this section, person has the meaning given that term in ORS 174.100. (2) No person shall be estopped or precluded from challenging the constitutionality or validity of any provision of chapter 449, Oregon Laws 1997, or the provisions of chapter 873, Oregon Laws 1…
ORS 543.110 Appropriation and use of water for power is governed by this chapter
0.5K chars
After February 26, 1931, no right to appropriate or to use the waters of the lakes, rivers, streams or other bodies of water within this state, including water over which this state has concurrent jurisdiction, in connection with the development of any water power project for the…
ORS 543.120 Water power projects to be in conformity with this chapter
0.3K chars
After February 26, 1931, no water power project involving the use of the waters of lakes, rivers, streams or other bodies of water within this state, including waters over which this state has concurrent jurisdiction, for the generation of electricity, shall be begun or construct…
ORS 543.140 Projects or developments constructed by federal government excepted from law
0.1K chars
The provisions of ORS 543.010 to 543.610 shall not apply to any water power project or development constructed by the United States.
ORS 543.150 Municipal corporations and utility districts; applicability of laws; powers of commission respecting districts
0.7K chars
The provisions of ORS 543.010, 543.050, 543.210, 543.220, 543.250, 543.260 and 543.290 to 543.610 shall not apply to cities, towns or other municipal corporations of this state, including utility districts organized under section 12, Article XI, Oregon Constitution, and legislati…
ORS 543.160 Hydroelectric facility on North Santiam River prohibited; exception
0.8K chars
(1) No person shall construct or maintain, and no officer or agency of the state shall issue any permit for the construction or maintenance of any hydroelectric facility or structure on the North Santiam River between river mile 27 and Big Cliff Dam. (2) Nothing in subsection (1)…
ORS 543.165 Hydroelectric facility on part of Deschutes River prohibited
0.6K chars
No person, state agency, local government, district or municipal corporation shall construct, and no officer or agency of the state shall issue any permit for the construction of any hydroelectric facility or structure on the Deschutes River between river mile 172 below Lava Isla…
ORS 543.170 Hydroelectric facility on Isqúulktpe Creek prohibited
0.5K chars
No person, state agency, local government, district or municipal corporation shall construct or maintain, and no officer or agency of the state shall issue any permit for the construction or maintenance of any hydroelectric facility or structure on Isqúulktpe Creek. [1985 c.560 §…
ORS 543.175 Hydroelectric facility on Deschutes River within City of Bend prohibited; exception
1.7K chars
(1) Except as provided in subsection (2) of this section, no person, state agency, local government, district or municipal corporation shall construct or maintain, and no officer or agency of the state shall issue any permit for the construction or maintenance of any hydroelectri…
ORS 543.210 Preliminary permits; application; contents; fee
1.5K chars
(1) Any person who proposes to operate a hydroelectric project in Oregon shall apply for a state preliminary permit. Any person who applies to the Federal Energy Regulatory Commission for a preliminary permit to operate a hydroelectric project shall, at the same time, apply for a…
ORS 543.220 Notice of filing of application; waiting period
1.5K chars
(1) If an application is made for a preliminary permit, after said application has been referred to hearing, the Water Resources Commission shall give written notice of the filing of the application to: (a) Any municipality or other person or corporation that, in the judgment of …
ORS 543.225 Hearing on application; notice; policy
2.9K chars
(1) The Water Resources Commission shall conduct a public hearing on any application or amended application for a preliminary permit or for a license for a major project of more than 100 theoretical horsepower and an application for preliminary permit or license for a minor proje…
ORS 543.230 Hearings on application; rules; protest
1.8K chars
(1) The Water Resources Commission shall, by order or rule, provide for the time and manner of hearings upon applications. However, upon request by any person made within 30 days after the Water Resources Director issues an order pertaining to cumulative impacts under ORS 543.255…
ORS 543.250 Permit; duration; transfer; cancellation; priority; terms and conditions; denial
1.0K chars
A preliminary permit may be issued for a period not exceeding a total of three years. It shall not be transferable except upon written approval of the Water Resources Commission, and may be canceled by order of the commission at any time upon proof to the commissions satisfactio…
ORS 543.255 Determination of cumulative impacts of proposed hydroelectric power projects; consolidated review; applicability
2.6K chars
(1) Whenever the Water Resources Department receives an application to appropriate water for a new hydroelectric project under ORS 537.140 to 537.320 or for a hydroelectric permit or license under ORS 543.010 to 543.610, the department shall determine whether the impacts of the p…
ORS 543.260 Licenses; duration; terms and conditions; termination; denial of application; preference of municipality or utility district
1.7K chars
(1) A license may be issued by the Water Resources Commission to any qualified person for a period not exceeding 50 years. If the project is subject to regulation by the Federal Energy Regulatory Commission, the term shall be concurrent with and expire upon expiration of the fede…
ORS 543.265 Testing of fish protection measures as condition for hydroelectric project permit or license; scope and cost
0.9K chars
The Water Resources Department shall impose as a condition to any water right permit to appropriate water for hydroelectric purposes granted under ORS 537.211 or any license granted under ORS 543.260 that the person operating the hydroelectric project shall, during the operationa…
ORS 543.270 Preference in granting permit or license; municipal use
0.6K chars
In issuing preliminary permits, and in issuing licenses where no preliminary permit is held by an applicant for a license, preference shall be given to the application which appears to the Water Resources Commission to be best adapted to conserve and utilize the water power invol…
ORS 543.280 Fee payments by licensee
3.2K chars
(1) Any person who applies to the Federal Energy Regulatory Commission for a preliminary permit to operate a hydroelectric project shall, at the same time, apply for a state preliminary permit. An applicant for a state preliminary permit for a new hydroelectric project shall subm…
ORS 543.290 Filing of maps, plans, estimates and other materials; incorporation as part of license; alteration; further statements and data
0.9K chars
The applicant for a license shall submit to and file with the Water Resources Commission: (1) All maps, plans, specifications and cost estimates as may be required by the commission for a full understanding of the proposed project. The maps, plans and specifications, when approve…
ORS 543.300 Conditions governing license; fees; waiver of conditions
3.6K chars
Any license issued under ORS 543.010 to 543.610 shall take into consideration, and shall be on, the following conditions: (1) That the proposed project shall be such as, in the judgment of the Water Resources Commission, is well adapted to the development and utilization of the w…
ORS 543.310 Disposition of moneys collected
0.2K chars
Except as provided in ORS 536.015, all moneys collected under the provisions of ORS 543.010 to 543.610 shall forthwith be paid to the State Treasurer and become a part of the General Fund. [Amended by 1985 c.674 §10; 1991 c.869 §10]
ORS 543.320 Effect of amendment or repeal of law
0.4K chars
The right to alter, amend or repeal ORS 543.010 to 543.610, or any part thereof, hereby is expressly reserved; but no such alteration, amendment or repeal shall affect any license theretofore issued under the provisions of ORS 543.010 to 543.610, or the rights of any licensee the…
ORS 543.410 Construction of project; time for commencement and completion; supply of service; extension of time; nonperformance; termination of license
1.4K chars
(1) The licensee shall commence the construction of the project works within the time fixed in the license, which shall not be more than two years from the date thereof, shall thereafter in good faith and with due diligence prosecute such construction, and shall, within the time …
ORS 543.420 Noncompletion of construction within prescribed time; judicial proceedings; sale of property; disposition of proceeds; rights of purchaser
0.9K chars
If construction of a project under license has been begun but has not been completed within the time prescribed in the license or in any lawful extension thereof, then the Attorney General, upon request of the Water Resources Commission, shall institute proceedings in the circuit…
ORS 543.430 Proceedings after completion of project for violation of license terms; authority of court; sale of project
1.5K chars
The Attorney General shall, upon request of the Water Resources Commission, institute proceedings in the circuit court for the county in which any project, or the major part of a project is situated, after the project has been completed, for the purpose of revoking for violation …
ORS 543.440 Transfer of license, rights or property; effect
1.1K chars
No voluntary transfer of any license or any rights under a license or of any property acquired, constructed or operated pursuant to license issued under ORS 543.010 to 543.610 shall be made without written approval of the Water Resources Commission. Any successor or assignee of a…
ORS 543.525 ORS 543.530 to 543.550 not applicable to regulated utilities
0.4K chars
The provisions of ORS 543.530 to 543.550 shall not apply to any licensee which is a utility as defined in ORS 757.005 and regulated by the Public Utility Commission of Oregon. [1965 c.333 §1] Note: 543.525 was enacted into law by the Legislative Assembly but was not added to or m…
ORS 543.530 Issuance by licensee of stocks, bonds or other interest without authorization of Water Resources Commission prohibited
1.9K chars
(1) No licensee shall issue any share of corporate stock, or any bond, or other evidence of interest in or indebtedness of the licensee, or assume any obligation or liability as lessor, lessee, guarantor, indorser, surety or otherwise, in respect of the corporate shares, bonds or…
ORS 543.540 Consideration for bonds, stocks and other securities; restrictions; corporate shares; sale price of securities; discount from face value
1.3K chars
No bonds, notes or other obligations or securities or corporate stock shall be issued in connection with the financing, construction or acquisition of any project or part of a project, under a license issued pursuant to ORS 543.010 to 543.610, except for cash or property. If issu…
ORS 543.550 Liens prohibited; exceptions; what may be included by mortgage, trust deed, or sale; determination of investment in case of sale of part
1.3K chars
No lien for labor, services, materials, machinery or equipment shall exist or be acquired or enforced upon any property acquired, constructed or made a part of any project under license issued pursuant to ORS 543.010 to 543.610. No property shall be put into or made part of any s…
ORS 543.560 Bond of licensee or letter of credit securing claims of suppliers; enforcement of obligation; action for sums due State Accident Insurance Fund Corporation
1.5K chars
Before entering upon the work of construction or acquisition of any project, the licensee shall execute to the state a bond, with good and sufficient sureties or an irrevocable letter of credit issued by an insured institution, as defined in ORS 706.008, in either case, to be app…
ORS 543.610 Acquisition of project by state or municipality
1.2K chars
(1) Upon not less than two years notice in writing the state, or any municipality thereof, shall have the right at any time to take over and thereafter to maintain and operate any project constructed under a license pursuant to ORS 543.010 to 543.610, upon payment of just compen…
ORS 543.650 Policy
1.2K chars
The Legislative Assembly finds that a significant potential exists for the development of the hydroelectric generation capabilities of water systems serving domestic water supply districts, irrigation districts, drainage districts, water improvement districts and water control di…