ORS 758.480 Assumption of obligations arising out of Trojan Nuclear Plant
3.2K chars
(1) As used in this section: (a) “Agreement” means the agreement dated October 5, 1970, and titled “Agreement for Construction, Ownership and Operation of the Trojan Nuclear Plant,” as amended. (b) “Allocated territory” has the meaning given that term in ORS 758.400. (c) “Person”…
ORS 758.505 Definitions for ORS 758.505 to 758.555
2.2K chars
As used in ORS 758.505 to 758.555: (1) “Avoided cost” means the incremental cost to an electric utility of electric energy or energy and capacity that the utility would generate itself or purchase from another source but for the purchase from a qualifying facility. (2) “Cogenerat…
ORS 758.515 Legislative findings
0.9K chars
The Legislative Assembly finds and declares that: (1) The State of Oregon has abundant renewable resources. (2) It is the goal of Oregon to: (a) Promote the development of a diverse array of permanently sustainable energy resources using the public and private sectors to the high…
ORS 758.525 Avoided cost schedules; filing; requirement to purchase energy from qualifying facilities
1.5K chars
(1) At least once every two years each electric utility shall prepare, publish and file with the Public Utility Commission a schedule of avoided costs equaling the utility’s forecasted incremental cost of electric resources over at least the next 20 years. Prices contained in the…