ORS 87.035 Perfecting lien; filing claim of lien; contents of claim
1.5K chars
(1) Every person claiming a lien created under ORS 87.010 (1) or (2) shall perfect the lien not later than 75 days after the person has ceased to provide labor, rent equipment or furnish materials or 75 days after completion of construction, whichever is earlier. Every other pers…
ORS 87.036 Subcontractor’s perfection of claim of lien; notice; fee; rules
1.3K chars
(1) A subcontractor or a person that provides labor, materials or equipment for a project to renovate, remodel, repair or otherwise alter an existing owner-occupied residence may not perfect a claim of lien against the owner’s property under ORS 87.035 if the subcontractor or the…
ORS 87.037 Prohibition against claim of lien
0.4K chars
An original contractor may not claim a lien arising from the improvement of real property if a written contract for the work is required by ORS 701.305 and the contractor does not have a written contract. [2007 c.648 §5] Note: 87.037 was added to and made a part of 87.001 to 87.0…
ORS 87.039 Notice of filing claim of lien; effect of failure to give notice
1.0K chars
(1) A person filing a claim of lien pursuant to ORS 87.035 shall mail to the owner and to the mortgagee a notice in writing that the claim has been filed. A copy of the claim of lien shall be attached to the notice. The notice shall be mailed not later than 20 days after the date…