ORS 543.210 Preliminary permits; application; contents; fee
1.5K chars
(1) Any person who proposes to operate a hydroelectric project in Oregon shall apply for a state preliminary permit. Any person who applies to the Federal Energy Regulatory Commission for a preliminary permit to operate a hydroelectric project shall, at the same time, apply for a…
ORS 543.220 Notice of filing of application; waiting period
1.5K chars
(1) If an application is made for a preliminary permit, after said application has been referred to hearing, the Water Resources Commission shall give written notice of the filing of the application to: (a) Any municipality or other person or corporation that, in the judgment of …
ORS 543.225 Hearing on application; notice; policy
2.9K chars
(1) The Water Resources Commission shall conduct a public hearing on any application or amended application for a preliminary permit or for a license for a major project of more than 100 theoretical horsepower and an application for preliminary permit or license for a minor proje…
ORS 543.230 Hearings on application; rules; protest
1.8K chars
(1) The Water Resources Commission shall, by order or rule, provide for the time and manner of hearings upon applications. However, upon request by any person made within 30 days after the Water Resources Director issues an order pertaining to cumulative impacts under ORS 543.255…
ORS 543.250 Permit; duration; transfer; cancellation; priority; terms and conditions; denial
1.0K chars
A preliminary permit may be issued for a period not exceeding a total of three years. It shall not be transferable except upon written approval of the Water Resources Commission, and may be canceled by order of the commission at any time upon proof to the commissions satisfactio…
ORS 543.255 Determination of cumulative impacts of proposed hydroelectric power projects; consolidated review; applicability
2.6K chars
(1) Whenever the Water Resources Department receives an application to appropriate water for a new hydroelectric project under ORS 537.140 to 537.320 or for a hydroelectric permit or license under ORS 543.010 to 543.610, the department shall determine whether the impacts of the p…
ORS 543.260 Licenses; duration; terms and conditions; termination; denial of application; preference of municipality or utility district
1.7K chars
(1) A license may be issued by the Water Resources Commission to any qualified person for a period not exceeding 50 years. If the project is subject to regulation by the Federal Energy Regulatory Commission, the term shall be concurrent with and expire upon expiration of the fede…
ORS 543.265 Testing of fish protection measures as condition for hydroelectric project permit or license; scope and cost
0.9K chars
The Water Resources Department shall impose as a condition to any water right permit to appropriate water for hydroelectric purposes granted under ORS 537.211 or any license granted under ORS 543.260 that the person operating the hydroelectric project shall, during the operationa…
ORS 543.270 Preference in granting permit or license; municipal use
0.6K chars
In issuing preliminary permits, and in issuing licenses where no preliminary permit is held by an applicant for a license, preference shall be given to the application which appears to the Water Resources Commission to be best adapted to conserve and utilize the water power invol…
ORS 543.280 Fee payments by licensee
3.2K chars
(1) Any person who applies to the Federal Energy Regulatory Commission for a preliminary permit to operate a hydroelectric project shall, at the same time, apply for a state preliminary permit. An applicant for a state preliminary permit for a new hydroelectric project shall subm…
ORS 543.290 Filing of maps, plans, estimates and other materials; incorporation as part of license; alteration; further statements and data
0.9K chars
The applicant for a license shall submit to and file with the Water Resources Commission: (1) All maps, plans, specifications and cost estimates as may be required by the commission for a full understanding of the proposed project. The maps, plans and specifications, when approve…
ORS 543.300 Conditions governing license; fees; waiver of conditions
3.6K chars
Any license issued under ORS 543.010 to 543.610 shall take into consideration, and shall be on, the following conditions: (1) That the proposed project shall be such as, in the judgment of the Water Resources Commission, is well adapted to the development and utilization of the w…
ORS 543.310 Disposition of moneys collected
0.2K chars
Except as provided in ORS 536.015, all moneys collected under the provisions of ORS 543.010 to 543.610 shall forthwith be paid to the State Treasurer and become a part of the General Fund. [Amended by 1985 c.674 §10; 1991 c.869 §10]
ORS 543.320 Effect of amendment or repeal of law
0.4K chars
The right to alter, amend or repeal ORS 543.010 to 543.610, or any part thereof, hereby is expressly reserved; but no such alteration, amendment or repeal shall affect any license theretofore issued under the provisions of ORS 543.010 to 543.610, or the rights of any licensee the…
ORS 543.410 Construction of project; time for commencement and completion; supply of service; extension of time; nonperformance; termination of license
1.4K chars
(1) The licensee shall commence the construction of the project works within the time fixed in the license, which shall not be more than two years from the date thereof, shall thereafter in good faith and with due diligence prosecute such construction, and shall, within the time …
ORS 543.420 Noncompletion of construction within prescribed time; judicial proceedings; sale of property; disposition of proceeds; rights of purchaser
0.9K chars
If construction of a project under license has been begun but has not been completed within the time prescribed in the license or in any lawful extension thereof, then the Attorney General, upon request of the Water Resources Commission, shall institute proceedings in the circuit…
ORS 543.430 Proceedings after completion of project for violation of license terms; authority of court; sale of project
1.5K chars
The Attorney General shall, upon request of the Water Resources Commission, institute proceedings in the circuit court for the county in which any project, or the major part of a project is situated, after the project has been completed, for the purpose of revoking for violation …
ORS 543.440 Transfer of license, rights or property; effect
1.1K chars
No voluntary transfer of any license or any rights under a license or of any property acquired, constructed or operated pursuant to license issued under ORS 543.010 to 543.610 shall be made without written approval of the Water Resources Commission. Any successor or assignee of a…
ORS 543.525 ORS 543.530 to 543.550 not applicable to regulated utilities
0.4K chars
The provisions of ORS 543.530 to 543.550 shall not apply to any licensee which is a utility as defined in ORS 757.005 and regulated by the Public Utility Commission of Oregon. [1965 c.333 §1] Note: 543.525 was enacted into law by the Legislative Assembly but was not added to or m…
ORS 543.530 Issuance by licensee of stocks, bonds or other interest without authorization of Water Resources Commission prohibited
1.9K chars
(1) No licensee shall issue any share of corporate stock, or any bond, or other evidence of interest in or indebtedness of the licensee, or assume any obligation or liability as lessor, lessee, guarantor, indorser, surety or otherwise, in respect of the corporate shares, bonds or…
ORS 543.540 Consideration for bonds, stocks and other securities; restrictions; corporate shares; sale price of securities; discount from face value
1.3K chars
No bonds, notes or other obligations or securities or corporate stock shall be issued in connection with the financing, construction or acquisition of any project or part of a project, under a license issued pursuant to ORS 543.010 to 543.610, except for cash or property. If issu…
ORS 543.550 Liens prohibited; exceptions; what may be included by mortgage, trust deed, or sale; determination of investment in case of sale of part
1.3K chars
No lien for labor, services, materials, machinery or equipment shall exist or be acquired or enforced upon any property acquired, constructed or made a part of any project under license issued pursuant to ORS 543.010 to 543.610. No property shall be put into or made part of any s…
ORS 543.560 Bond of licensee or letter of credit securing claims of suppliers; enforcement of obligation; action for sums due State Accident Insurance Fund Corporation
1.5K chars
Before entering upon the work of construction or acquisition of any project, the licensee shall execute to the state a bond, with good and sufficient sureties or an irrevocable letter of credit issued by an insured institution, as defined in ORS 706.008, in either case, to be app…
ORS 543.610 Acquisition of project by state or municipality
1.2K chars
(1) Upon not less than two years notice in writing the state, or any municipality thereof, shall have the right at any time to take over and thereafter to maintain and operate any project constructed under a license pursuant to ORS 543.010 to 543.610, upon payment of just compen…
ORS 543.650 Policy
1.2K chars
The Legislative Assembly finds that a significant potential exists for the development of the hydroelectric generation capabilities of water systems serving domestic water supply districts, irrigation districts, drainage districts, water improvement districts and water control di…
ORS 543.655 Definitions for ORS 543.650 to 543.685
0.9K chars
As used in ORS 543.650 to 543.685, unless the context requires otherwise: (1) District means any one of the following: (a) A domestic water supply district organized under ORS chapter 264. (b) An irrigation district organized under ORS chapter 545. (c) A drainage district organ…
ORS 543.660 Authority of district to enlarge or modify water system and power generating facilities; joint district ventures; prohibitions; sale of energy; regulations
2.4K chars
(1) A district, alone or jointly with other districts, electric cooperatives, as defined in ORS 261.010, peoples utility districts, a cooperative as defined in ORS 62.015, municipal corporations authorized to engage in generating and distributing electricity or public utilities,…
ORS 543.662 Authority of district to develop joint project with private person; restrictions
0.5K chars
A district may contract with a private person to enlarge or modify the districts water system for the purpose of generating hydroelectric power. The district shall retain sufficient benefit and interest in, and control of a joint project as necessary for the project to be consid…
ORS 543.664 Rules relating to joint projects of districts and private persons
0.4K chars
The Water Resources Commission shall establish rules necessary to carry out the provisions of ORS 543.662. The rules shall include the amount of control over and interest in a joint project a district must retain in order to receive the benefit of the municipal preference and pro…
ORS 543.665 Authority to issue revenue bonds to acquire hydroelectric facilities
1.8K chars
(1) In addition to any other authority under its principal Act to issue bonds, a district, when authorized at any properly called election, shall have the power to sell and dispose of revenue bonds to construct or acquire hydroelectric facilities in conformance with ORS 543.650 t…
ORS 543.670 Manner of issuance of revenue bonds
0.2K chars
All revenue bonds issued under ORS 543.665 shall be issued as prescribed in ORS chapter 287A, but the requirements of ORS 287A.150 do not apply. [1981 c.420 §5; 1983 c.557 §12; 2007 c.783 §216]
ORS 543.675 Power of eminent domain not to be exercised to acquire hydroelectric facilities
0.3K chars
Notwithstanding any powers of eminent domain and condemnation given to a district under its principal Act, a district shall not exercise any power of condemnation or eminent domain to condemn, appropriate or acquire real property for the purpose of constructing, acquiring, operat…
ORS 543.680 Compliance with water appropriation laws required
0.2K chars
A district shall comply with all applicable provisions of ORS chapter 537 before enlarging or modifying the districts water system for the purpose of generating hydroelectric energy. [1981 c.420 §7; 1985 c.561 §7]
ORS 543.685 District board to require weatherization; Weatherization Fund; purpose
0.8K chars
(1) If the board of directors of a district has not adopted an ordinance, resolution or administrative rule requiring the weatherization of the buildings of the district, the district shall deposit 10 percent of any revenues derived from the sale of excess electric energy under O…
ORS 543.705 Definitions for ORS 543.710 to 543.730
0.1K chars
As used in ORS 543.710 to 543.730, claimant means any person claiming the right to the use of water for power development. [1957 c.333 §1]
ORS 543.710 Annual fee based on horsepower; exemptions; disbursement
0.5K chars
Every claimant other than a licensee under ORS 543.010 to 543.610 shall on or before January 1 of each year pay to the state in advance an annual fee based upon the theoretical water horsepower claimed under each separate claim to water and calculated using the formula under ORS …
ORS 543.720 Payment of annual fee; accompanying statement; penalty for nonpayment of fees or nonfiling; lien; foreclosure; effect of filing excessive claim; computation of horsepower
2.6K chars
(1) The fees provided for in ORS 543.710 shall be paid to the Water Resources Commission in advance, and shall be accompanied by a written statement showing the extent of the claim. The statement shall set forth the name and address of the claimant; the name of the stream from wh…
ORS 543.730 Failure to file statement or pay fees as evidence of abandonment of claim; cancellation of claim, permit and water right certificate
1.0K chars
(1) Failure of any claimant for a period of five successive years ending after August 20, 1957, to file the written statement showing the extent of the claim as required by ORS 543.720, or failure of any claimant for a period of five successive years ending after August 20, 1957,…
ORS 543.760 Definition of water right
0.6K chars
As used in ORS 543.765, water right means a water use established by an adjudication under ORS chapter 539 as evidenced by a court decree or a certificated ground water or surface water right that is issued for some use other than for hydroelectric power and that serves as the …
ORS 543.765 Certificate to use water for hydroelectric purposes within artificial delivery system; expedited application process; certificate conditions; annual payments; fees
12.5K chars
(1) Notwithstanding ORS 537.145 and ORS chapter 543: (a) The holder of a water right may apply to the Water Resources Department for a certificate to use water for hydroelectric purposes within an artificial delivery system under the applicants existing water right. (b) A munici…
ORS 543.990 Penalties
1.1K chars
(1) Violation of ORS 543.530 (3) is a Class A misdemeanor. (2) Violation of any of the provisions of ORS 543.010 to 543.610, or any of the conditions made a part of any license issued under ORS 543.010 to 543.610, or any subpoena of the Water Resources Commission or of an adminis…
ORS 543A.005 Definitions
1.1K chars
As used in ORS 543A.005 to 543A.410. (1) Commission means the Water Resources Commission. (2) Department means the Water Resources Department. (3) Director means the Water Resources Director. (4) Federally licensed project means an existing project licensed under ORS 543.…
ORS 543A.010 Findings
1.0K chars
The Legislative Assembly finds that many hydroelectric projects within the state hold water rights for hydroelectric purposes for a limited time period, and that those water rights will expire. State law does not currently prescribe a means for reauthorizing the use of water for …
ORS 543A.015 Purpose
0.6K chars
It is the purpose of this chapter and ORS 468.065, 468B.040, 468B.045, 468B.046, 536.015, 536.050, 543.012 and 543.710 to establish a process for developing a coordinated state position to be reflected in governmental proceedings related to the reauthorization of existing hydroel…
ORS 543A.020 Policy
1.1K chars
The Legislative Assembly declares that it is the policy of the State of Oregon: (1) To reauthorize the use of water by existing projects provided that such projects meet the standards established in ORS 543A.025, are consistent with other applicable state laws and will not impair…
ORS 543A.025 Minimum standards for decision on reauthorization of water right; rules
5.7K chars
(1) Following the process set forth in ORS 543A.005 to 543A.410, the Water Resources Director shall issue a water right for continued operation of an existing hydroelectric project upon a finding that the proposed use will not impair or be detrimental to the public interest, cons…
ORS 543A.030 Notice of intent
1.4K chars
(1) Not later than three years before the expiration of a water right for a state project, the Water Resources Department shall notify the project owner of the expiration of the water right and request that the owner advise the department whether the owner intends to seek reautho…
ORS 543A.035 Reauthorization application and public comment
2.3K chars
(1) Within 60 days after submitting a notice of intent under ORS 543A.030, the applicant shall submit to the Water Resources Department an application to reauthorize the water right for the state project on a form prescribed by the department. (2) The reauthorization application …
ORS 543A.040 Process determination
3.0K chars
(1) Within 60 days after the close of the period allowed for public comment under ORS 543A.035, the Hydroelectric Application Review Team shall determine whether the reauthorization application for the water right contains sufficient information to determine whether reauthorizati…
ORS 543A.045 Public scoping meeting
1.3K chars