R.463-61-463-61-070 Corridors and transmission facilities considerations.
1.4K chars
(1) EFSEC shall consider and may recommend certification of electrical transmission facilities in corridors designated for this purpose by affected cities, towns, or counties where:(a) Jurisdictions have identified electrical transmission facility corridors as part of their land …
R.463-61-463-61-080 Negotiations between preapplicants, cities, towns and counties.
0.9K chars
(1) As required by RCW 80.50.330(2) if no corridor has been designated by a local government, the preapplicant and affected cities, towns, and/or counties shall negotiate to designate a corridor for the electrical transmission facility.(2) If after 60 days of negotiations between…
R.463-61-463-61-090 Preapplication costs.
1.1K chars
(1) A preapplicant shall deposit with the state treasurer $10,000 to be applied to the cost of the preapplication process as a condition for proceeding by EFSEC.(2) EFSEC shall manage the preapplication costs using the structure outlined in RCW 80.50.071 as follows:(a) The preapp…