R.479-05-479-05-040 Value engineering study requirements.
1.2K chars
The executive director may determine whether a value engineering study is required based on project risk factors summarized below. The agency will be notified if a value engineering study is required during the design process and must complete the study prior to authorization to …
R.479-05-479-05-051 Project phases.
2.6K chars
Projects authorized by the board are divided into the following phases:(1) Design phase – Documents that must be received prior to phase approval include:(a) Signed funding status form confirming that the funding partners are fully committed;(b) Page from the adopted six-year tra…
R.479-05-479-05-052 Project modification and scope change.
0.7K chars
The executive director may approve scope changes except the following which require the board's approval:(1) A change in the project limits with a request for an increase in funding beyond the executive director's administrative authority in WAC 479-01-060;(2) Adding or decreasin…