PSC-112-112.04 Interconnection projects
1.1K chars
PSC 112.04 Interconnection projects. No electric utility may begin construction, install or place in operation an initial interconnection with the transmission system of another electric utility, with which it has no existing transmission interconnections, without the commission[…
PSC-112-112.05 Construction of electric utility facilities
5.9K chars
PSC 112.05 Construction of electric utility facilities. (1) No electric utility may begin construction, install or place in operation any of the following facilities whose estimated gross cost exceeds the applicable amount specified in sub. (3), without prior commission approval …
PSC-112-112.06 Applications for commission authorization
4.5K chars
PSC 112.06 Applications for commission authorization. (1) PRIOR TO FILING AN APPLICATION. Before filing an application for commission authorization under s. 196.49, Stats., the applicant shall do all of the following: (a) Notify the department and the commission of its intent to …