20,156 sections across 1,502 Wisconsin regulatory chapters.
Trans-401-401.10 Erosion control plan
0.0K chars
Trans 401.10 Erosion control plan.
R.401.105 Corrective action
7.3K chars
Trans 401.105 Corrective action. (1) (a) An inspector who believes that changes or corrections are needed to best management practices may, by written order delivered to the prime contractor, temporarily suspend work until the project engineer is notified and decides all question…
R.401.106 Post-construction performance
17.2K chars
Trans 401.106 Post-construction performance standard. (1) DEFINITIONS. In this section: (a) XAverage annual rainfallY means the rainfall determined by the following year and location for the location nearest the project site: Madison, 1981 (Mar. 12-Dec. 2); Green Bay, 1969 (Mar. …