Title 16 › CHAPTER 12B — BONNEVILLE PROJECT › § 832f
Rates for selling extra electricity from the Bonneville project must be set because the power comes from water created when the dam was built. The prices must let Bonneville recover the costs to produce and send that power, including paying off the capital investment over a reasonable time. The Secretary of Energy will decide how to split up the costs and may assign a fair share of shared facility costs to power.
Full Legal Text
Conservation, Source: USLM XML via OLRC
Legislative History
Reference
Citation
16 U.S.C. § 832f
Title 16, Conservation
Last Updated
Aug 21, 2026
Release point: 119-102