Title 16 › CHAPTER 12C — FORT PECK PROJECT › § 833e
Set rates for selling any Fort Peck electricity that is more than what the dam needs so those prices reflect that the power comes from water created by building the dam for the purposes listed in section 833. Rates must cover the cost to produce and send the electricity, including paying back the capital investment over a reasonable period of years. The Secretary of Energy will decide how to split costs. If a facility is used for power and other things, the Secretary may charge the power side a fair share of those joint costs.
Full Legal Text
Conservation, Source: USLM XML via OLRC
Legislative History
Reference
Citation
16 U.S.C. § 833e
Title 16, Conservation
Last Updated
Aug 21, 2026
Release point: 119-102