Title 30, Mineral Lands and MiningRelease 119-110

§1260 Permit Approval or Denial

Title 30 › CHAPTER 25 — SURFACE MINING CONTROL AND RECLAMATION › SUBCHAPTER V — CONTROL OF THE ENVIRONMENTAL IMPACTS OF SURFACE COAL MINING › § 1260

Last updated Sep 23, 2026|Official source

Summary

The permit agency must approve, change, or deny a mining permit after it gets a complete application and plan and follows the state or federal program rules, including public notice and any hearing. The applicant must prove the application meets all rules. If a permit is granted, the agency must tell local government officials within 10 days and say where the land is. To approve a permit, the agency must write findings showing the application is complete and accurate, the reclamation plan will work, likely effects on water have been assessed and won’t cause material damage outside the permit area, the site is not in an area banned or under study for mining (with a limited exception for operators who made big legal or financial commitments before January 1, 1977, where the Secretary may arrange coal lease or title exchanges), operations west of the 100th meridian must not stop farming on irrigated valley floors or harm water that feeds them, and if the mineral rights are separate from the surface rights the applicant must have the surface owner’s consent or a legal right to mine. The applicant must include a list of any notices of violations in the past three years and how they were resolved. The agency won’t issue a permit until current violations are fixed, and it can deny a permit after a hearing if the applicant has a pattern of willful violations causing serious, lasting environmental harm. If the land is prime farmland, the agency—after consulting the Secretary of Agriculture and following Interior rules—may only approve a permit if the operator can restore the land, within a reasonable time, to equal or better crop yields and meet the law’s soil-rebuilding standards; this does not apply to permits issued before August 3, 1977. After October 24, 1992, the rule blocking permits for violations does not apply to violations caused by unexpected events at operations on lands eligible for remining when the applicant already holds the remining permit.

Full Legal Text

Title 30, §1260

Mineral Lands and Mining, Source: USLM XML via OLRC

(a)Basis for decision; notification of applicant and local government officials; burden of proof (b) Requirements for approval
Upon the basis of a complete mining application and reclamation plan or a revision or renewal thereof, as required by this chapter and pursuant to an approved State program or Federal program under the provisions of this chapter, including public notification and an opportunity for a public hearing as required by section 1263 of this title, the regulatory authority shall grant, require modification of, or deny the application for a permit in a reasonable time set by the regulatory authority and notify the applicant in writing. The applicant for a permit, or revision of a permit, shall have the burden of establishing that his application is in compliance with all the requirements of the applicable State or Federal program. Within ten days after the granting of a permit, the regulatory authority shall notify the local governmental officials in the local political subdivision in which the area of land to be affected is located that a permit has been issued and shall describe the location of the land.
(c)Schedule of violations
The applicant shall file with his permit application a schedule listing any and all notices of violations of this chapter and any law, rule, or regulation of the United States, or of any department or agency in the United States pertaining to air or water environmental protection incurred by the applicant in connection with any surface coal mining operation during the three-year period prior to the date of application. The schedule shall also indicate the final resolution of any such notice of violation. Where the schedule or other information available to the regulatory authority indicates that any surface coal mining operation owned or controlled by the applicant is currently in violation of this chapter or such other laws referred to this subsection, the permit shall not be issued until the applicant submits proof that such violation has been corrected or is in the process of being corrected to the satisfaction of the regulatory authority, department, or agency which has jurisdiction over such violation and no permit shall be issued to an applicant after a finding by the regulatory authority, after opportunity for hearing, that the applicant, or the operator specified in the application, controls or has controlled mining operations with a demonstrated pattern of willful violations of this chapter of such nature and duration with such resulting irreparable damage to the environment as to indicate an intent not to comply with the provisions of this chapter.
(d)Prime farmland mining permit
(1)In addition to finding the application in compliance with subsection (b) of this section, if the area proposed to be mined contains prime farmland pursuant to section 1257(b)(16) of this title, the regulatory authority shall, after consultation with the Secretary of Agriculture, and pursuant to regulations issued hereunder by the Secretary of Interior with the concurrence of the Secretary of Agriculture, grant a permit to mine on prime farmland if the regulatory authority finds in writing that the operator has the technological capability to restore such mined area, within a reasonable time, to equivalent or higher levels of yield as non-mined prime farmland in the surrounding area under equivalent levels of management and can meet the soil reconstruction standards in section 1265(b)(7) of this title. Except for compliance with subsection (b), the requirements of this paragraph (1) shall apply to all permits issued after August 3, 1977.
(2)Nothing in this subsection shall apply to any permit issued prior to August 3, 1977, or to any revisions or renewals thereof, or to any existing surface mining operations for which a permit was issued prior to August 3, 1977.
(e)Modification of prohibition
After October 24, 1992, the prohibition of subsection (c) shall not apply to a permit application due to any violation resulting from an unanticipated event or condition at a surface coal mining operation on lands eligible for remining under a permit held by the person making such application. As used in this subsection, the term “violation” has the same meaning as such term has under subsection (c).

Legislative History

Notes & Related Subsidiaries

Editorial Notes

Amendments

2006—Subsec. (e). Pub. L. 109–432 struck out at end “The authority of this subsection and section 1265(b)(20)(B) of this title shall terminate on September 30, 2004.” 1992—Subsec. (e). Pub. L. 102–486 added subsec. (e).

Reference

Citations & Metadata

Citation

30 U.S.C. § 1260

Title 30, Mineral Lands and Mining

Last Updated

Sep 23, 2026

Release point: 119-110