Title 33 › CHAPTER 11 — BRIDGES OVER NAVIGABLE WATERS › SUBCHAPTER II — ALTERATION OF BRIDGES › § 515
After the Secretary approves the plans, the bridge owner must take bids when and how the Secretary orders. All bids, even a bid from the owner, must go to the Secretary with the owner's pick for the best bid and a written guarantee that the total cost, including the work the owner will do, will not exceed the stated amount. The Secretary can reject bids and re-bid, or let the work be done by contract, partly by contract and partly by the owner, or entirely by the owner. If money is only available for part of the project, bids may be taken for that part. If the work is done in successive parts, the owner must give a new cost guarantee when the Secretary asks.