After the Secretary approves the plans and notifies the bridge owner, the owner must take bids as the Secretary directs and send all bids, including the owner’s, to the Secretary. The owner must name a recommended bid and give a written guarantee that the total project cost, including the owner’s work, will not exceed the stated amount. The Secretary may reject all bids or let the work go forward by contract, partly by contract and partly by the owner, or entirely by the owner. Once cost shares are fixed under sections 516 and 517, the owner must start within a reasonable time. If only part of the project is funded, bids may be taken for that part, and the owner may need to give a new guarantee after each phase.

Full Legal Text

Title 33, §515

Navigation and Navigable Waters — Source: USLM XML via OLRC

After approval of such general plans and specifications by the Secretary, and after notification of such approval, the bridge owner shall, in such manner and within such times as the Secretary may prescribe, take bids for the alteration of such bridge in accordance with such general plans and specifications. All bids, including any bid for all or part of the project submitted by the bridge owner, shall be submitted to the Secretary, together with a recommendation by the bridge owner as to the most competent bid or bids, and at the same time the bridge owner shall submit to the Secretary a written guaranty that the total cost of the project, including the cost of such work as is to be performed by the bridge owner and not included in the work to be performed by contract, shall not exceed the sum stated in said guaranty. The Secretary may direct the bridge owner to reject all bids and to take new bids, or may authorize the bridge owner to proceed with the project, by contract, or partly by contract and partly by the bridge owner, or wholly by the bridge owner. Upon such authorization and fixing of the proportionate shares of the cost as provided in section 516 of this title, the bridge owner shall, within a reasonable time to be prescribed by the Secretary, proceed with the work of alteration; and the cost thereof shall be borne by the United States and by the bridge owner, as provided in section 516 and 517 of this title: Provided, That where funds have been appropriated for part only of a project, the bridge owner may take bids for part only of the work. In the event the bridge owner proceeds with the alteration through the taking of successive partial bids, the bridge owner shall, if required by the Secretary, submit a revised guaranty of cost after bids are accepted for successive parts of the work.

Legislative History

Notes & Related Subsidiaries

Editorial Notes

Amendments

1958—Pub. L. 85–640 struck out provisions which required bridge owner to take bids within 90 days after notification of approval of general plans and specifications, and inserted provisions permitting the taking of partial bids where funds have been appropriated for part of a project, and requiring the bridge owner, if requested, to submit a revised guaranty of cost.