2025-16559Notice

Utah Hydro Project Goes to Tribe: Pipelines and Houses Removed

Published Date: 8/28/2025

Notice

Summary

Moon Lake Electric Association wants to give up its license for a hydroelectric project in Utah and remove some parts while handing over others to the Ute Indian Tribe. The government will check how this change might affect the environment and plans to share their findings by October 20, 2025. This affects local communities, Tribal lands, and could change how electricity is managed nearby.

Analyzed Economic Effects

4 provisions identified: 2 benefits, 0 costs, 2 mixed.

License Surrender and Infrastructure Removal

Moon Lake Electric filed on December 31, 2024 to surrender the license for the Uintah Hydroelectric Project (No. 190) near Neola, Duchesne County, Utah. The licensee proposes to remove specific project features — including the scour protection weir on the Uinta River, an elevated pipeline to the main canal, the Pole Creek diversion structure, the substation, and two operator houses — while other features would be transferred to the Ute Indian Tribe.

Transfer of Retained Features to Ute Indian Tribe

The licensee proposes that retained project features — including the main canal heading structure and main canal, the Big Springs diversion structure and access road, the project forebay, the powerhouse, and a garage — will be transferred to the Ute Indian Tribe. The transfer would place control of those listed features with the Tribe.

Transmission Line Will Be Retained

Under the proposal, the transmission line that provides electricity to legacy cabins and the nearby Ute Fish Hatchery will be retained. That means the licensee proposes to leave that specific electricity line in place rather than remove it during surrender.

Environmental Assessment and Public Comment Window

The Federal Energy Regulatory Commission staff intends to prepare an environmental assessment (EA) under the National Environmental Policy Act and plans to issue the EA by October 20, 2025. The EA will be posted for a 30-day public comment period, and all comments filed on the EA will be reviewed and considered in the Commission's final decision.

Your PRIA Score

Score Hidden

Personalized for You

How does this regulation affect your finances?

Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.

Free to start

Key Dates

Published Date
Effective Date
8/28/2025
10/20/2025

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML
Back to Federal Register

Take It Personal

Get Your Personalized Policy View

Start a Free Government Policy Watch to see how policy affects your household, then upgrade to PRIA Full Coverage for year-round monitoring.

Already have an account? Sign in