West Virginia Dam Hydro Bid: Comments Invited on Clean Power Push
Published Date: 1/23/2025
Notice
Summary
Current Hydro Project 19, LLC wants to build a new hydroelectric power project at the New Cumberland Locks and Dam on the Ohio River in West Virginia. The government is now accepting public comments, protests, and requests to join the decision process for the next 60 days. This project could bring clean energy but also affects local land and water, so your voice matters—and the clock is ticking!
Analyzed Economic Effects
4 provisions identified: 3 benefits, 0 costs, 1 mixed.
New 19.99 MW Hydropower Project Proposed
A new New Cumberland Hydroelectric Project is proposed at the New Cumberland Locks and Dam in Hancock County, West Virginia. The proposal would occupy 2 acres of U.S. Army Corps of Engineers land and include two Kaplan turbine-generators with a combined capacity of 19.99 megawatts plus associated transmission lines and a powerhouse.
60-Day Window to Intervene or Protest
You can file a protest or a motion to intervene in the New Cumberland Hydroelectric Project proceeding within 60 days of January 23, 2025. Filings must follow FERC rules and clearly identify the project name and docket number (P-15045-002).
Competing Applications Allowed on Deadline
Any qualified applicant wanting to file a competing development application must submit it on or before the intervention deadline (60 days from January 23, 2025), or submit a timely notice of intent and then file the competing application no later than 120 days after the intervention deadline. Applications for preliminary permits will not be accepted in response to this notice.
Environmental Review and Comment Schedule
FERC accepted the application for filing but stated it is not yet ready for environmental analysis. The procedural schedule lists: Issue Scoping Document 1 in April 2025, comments on Scoping Document 1 due in May 2025, requests for additional information (if needed) in June 2025, and Issue Scoping Document 2 (if necessary) in June 2025.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-17101, Georgia Power Company; Notice of Application for Temporary Variance Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Georgia Power Company asked for a temporary change to rules at their Flint River Hydroelectric Project in Georgia. This could affect water quality rules and needs approval from state agencies. People have until September 17, 2026, to share their thoughts or get involved before any decisions are made.
2026-17103, Seefeld Corporation: Notice of Application for Surrender of Exemption Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Seefeld Corporation wants to give up its special exemption for the Smith Creek Hydroelectric Project in Washington. This change could affect local water quality rules and needs approval from the Washington Department of Ecology. People have until September 17, 2026, to share their thoughts or get involved before the decision moves forward.
2026-16925, Commission Information Collection Activities (FERC-725U); Comment Request; Extension
In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is soliciting public comment on the currently approved information collection FERC-725U (1902-0274), Mandatory Reliability Standards for the Bulk Power System; CIP Reliability Standards. There are no proposed changes to the reporting requirements. The comment period ended on July 27, 2026, with no comments received.
2026-16739, Venture Global CP2 LNG, LLC, Venture Global CP Express, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed CP2 LNG Expansion Project, and Notice of Public Scoping Sessions
2026-16616, Regulatory Agenda
We are publishing our regulatory agenda (the Agenda) in accordance with Public Law 96-354, "The Regulatory Flexibility Act," and Executive Order 12866, "Regulatory Planning and Review." FERC's complete Agenda, available on OMB's website at https://www.reginfo.gov, is a compilation of all rulemaking activities on which we have recently completed action or have proposed or are considering action. Our last Agenda was provided in May 2025 and in this current agenda, we have listed 42 rulemaking activities. We also note that the Agency has one inactive rulemaking that is not listed in this Agenda. This issuance of our Agenda contains ten (10) Pre-Rules, eleven (11) Notice of Proposed Rules, eight (8) Final Rules, and thirteen (13) Completed activities. Four (4) rulemakings are Section 3(f)(1) Significant; two (2) are Other Significant; one (1) is a routine rulemaking activity; two (2) are administrative, and thirty-two (32) are Substantive, Nonsignificant rulemaking activities.
2026-16637, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from several natural gas pipeline companies about rate changes and rule updates. These changes could affect pipeline rates starting as soon as July 9, 2026, and some compliance updates kick in January 1, 2027. If you want to speak up or get involved, you need to comment by late August 2026.
Previous / Next Documents
Previous: 2025-01579, Pike Island Hydropower Corporation; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests
Pike Island Hydropower Corporation wants to build a new hydroelectric project on the Ohio River in Belmont County, Ohio, using 2 acres of federal land. The government is now accepting public comments, protests, and requests to join the discussion for the next 60 days. This project could bring clean energy but also affects local land and water use, so your voice matters—and soon!
Next: 2025-01581, Idaho Power Company; Notice of Availability of Environmental Assessment
Idaho Power wants to keep running the American Falls Hydroelectric Project in Idaho, and the government checked to make sure it won’t harm the environment. They found it’s safe to continue with some protective rules. People have 30 days to share their thoughts before the new license is approved, so this affects local communities and energy users soon.