Current Hydro Project 19, LLC wants to build a new hydroelectric power project at the New Cumberland Locks and Dam on the Ohio River in West Virginia. The government is now accepting public comments, protests, and requests to join the decision process for the next 60 days. This project could bring clean energy but also affects local land and water, so your voice matters—and the clock is ticking!
Analyzed Economic Effects
4 provisions identified: 3 benefits, 0 costs, 1 mixed.
New 19.99 MW Hydropower Project Proposed
A new New Cumberland Hydroelectric Project is proposed at the New Cumberland Locks and Dam in Hancock County, West Virginia. The proposal would occupy 2 acres of U.S. Army Corps of Engineers land and include two Kaplan turbine-generators with a combined capacity of 19.99 megawatts plus associated transmission lines and a powerhouse.
60-Day Window to Intervene or Protest
You can file a protest or a motion to intervene in the New Cumberland Hydroelectric Project proceeding within 60 days of January 23, 2025. Filings must follow FERC rules and clearly identify the project name and docket number (P-15045-002).
Competing Applications Allowed on Deadline
Any qualified applicant wanting to file a competing development application must submit it on or before the intervention deadline (60 days from January 23, 2025), or submit a timely notice of intent and then file the competing application no later than 120 days after the intervention deadline. Applications for preliminary permits will not be accepted in response to this notice.
Environmental Review and Comment Schedule
FERC accepted the application for filing but stated it is not yet ready for environmental analysis. The procedural schedule lists: Issue Scoping Document 1 in April 2025, comments on Scoping Document 1 due in May 2025, requests for additional information (if needed) in June 2025, and Issue Scoping Document 2 (if necessary) in June 2025.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-20421, PJM Interconnection, L.L.C.; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is checking if PJM Interconnection’s new rules for buying backup power are fair and legal. This affects energy companies and customers in the PJM region, with possible changes to how costs are shared. If refunds are needed, they start from October 6, 2026, and anyone interested has 21 days to speak up.
2026-20453, Southern Star Central Gas Pipeline, Inc.; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Evergy McNew Power Plant Delivery Project
Southern Star Central Gas Pipeline wants to build new gas facilities to deliver power to the Evergy McNew Power Plant in Kansas. The government is asking the public to share their thoughts on how this might affect the environment before making a final decision. If you care about local air, water, or land, now’s the time to speak up by November 2, 2026!
2026-20450, Transcontinental Gas Pipe Line Company, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Leidy Access Expansion Project
Transcontinental Gas Pipe Line Company wants to expand its gas pipeline in Luzerne, Pennsylvania, and the government is asking the public to share their thoughts on how this might affect the environment. People have until November 2, 2026, to send in comments about possible impacts and better ways to do the project. This feedback will help decide if the project moves forward and how it’s done safely and responsibly.
2026-20420, Combined Notice of Filings
The Federal Energy Regulatory Commission got several filings from natural gas pipeline companies about rate changes and refunds. These updates affect customers and companies using pipelines, with new rates starting as soon as October 1, 2026. If you want to comment, deadlines are mostly mid-October, so act fast to have your say on possible price changes.
2026-20418, BIF III Holtwood LLC; Notice of Application for Non-Project Use of Project Land and Waters Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
BIF III Holtwood LLC wants to build docks on land and water near the Wallenpaupack Hydroelectric Project in Pennsylvania. The government is reviewing this request and asking the public to share their thoughts by October 30, 2026. This could change how the land and water are used but won’t affect electricity prices or timing.
2026-20416, Commission Information Collection Activities (FERC-603); Comment Request; Extension
FERC is renewing its info collection form called FERC-603, which helps protect important energy infrastructure details. No changes are planned, but folks who submit this info should know the deadline to comment is November 5, 2026. This keeps the process smooth without adding extra costs or paperwork.
Previous / Next Documents
Previous: 2025-01579, Pike Island Hydropower Corporation; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests
Pike Island Hydropower Corporation wants to build a new hydroelectric project on the Ohio River in Belmont County, Ohio, using 2 acres of federal land. The government is now accepting public comments, protests, and requests to join the discussion for the next 60 days. This project could bring clean energy but also affects local land and water use, so your voice matters—and soon!
Next: 2025-01581, Idaho Power Company; Notice of Availability of Environmental Assessment
Idaho Power wants to keep running the American Falls Hydroelectric Project in Idaho, and the government checked to make sure it won’t harm the environment. They found it’s safe to continue with some protective rules. People have 30 days to share their thoughts before the new license is approved, so this affects local communities and energy users soon.