FERC Announces New Gas Pipeline Rate Filings
Published Date: 4/30/2025
Notice
Summary
The Federal Energy Regulatory Commission got new filings from natural gas pipeline companies about their rates and refunds. These filings could affect customers and communities by changing pipeline charges, with deadlines to comment by early to mid-May 2025. If you want to speak up or learn more, now’s the time to jump in and make your voice heard!
Analyzed Economic Effects
2 provisions identified: 1 benefits, 0 costs, 1 mixed.
Natural Gas Pipeline Rate Filings Notice
The Federal Energy Regulatory Commission received natural gas pipeline rate and refund filings (dockets PR19-9-001, PR20-52-002, PR25-35-001) filed on April 23, 2025. These filings could change pipeline charges and thus affect customers and communities. Public comments or protests must be filed by 5:00 p.m. Eastern on the specified dates: May 7, 2025 (for PR25-35-001) and May 14, 2025 (for PR19-9-001 and PR20-52-002).
Help Available to Participate in FERC Proceedings
The Commission's Office of Public Participation (OPP) offers help to members of the public — including landowners, community organizations, and Tribal members — to access information and navigate filing processes. For assistance with interventions, comments, or rehearing requests, OPP can be contacted at (202) 502-6595 or at OPP@ferc.gov.
Your PRIA Score
Personalized for You
How does this regulation affect your finances?
Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-11880 — Rio Grande LNG Train 6, LLC; Notice of Application and Establishing Intervention Deadline
Rio Grande LNG Train 6, LLC wants to expand its Texas LNG terminal by adding a new liquefaction train and marine jetty, boosting production by over 6 million tonnes per year and allowing more LNG ships to dock. This means more energy and business for the area, but folks have a deadline to speak up or get involved. The project is moving fast, so keep an eye on the clock and your calendars!
2026-11881 — Venture Global CP2 LNG, LLC, Venture Global CP Express, LLC; Notice of Application and Establishing Intervention Deadline
Venture Global CP2 LNG and CP Express want to expand their LNG export terminal in Louisiana and the pipeline from Texas to Louisiana. This big project will boost LNG export capacity by 11.7 million tonnes per year and add pipeline capacity for 1,900 million cubic feet daily, costing about $826 million. If you’re interested, you’ve got until the intervention deadline to speak up or get involved!
2026-11846 — Combined Notice of Filings
The Federal Energy Regulatory Commission is reviewing new and updated natural gas pipeline rate filings that could change how much customers pay starting as soon as July 1, 2026. Pipeline companies like DCP Guadalupe and Transcontinental Gas are asking for rate changes or corrections, and the public has until late June or early August to share their thoughts. These updates affect energy companies and customers who rely on natural gas, with some changes already effective or coming soon.
2026-11879 — Northern Natural Gas Company; Notice of Application and Establishing Intervention Deadline
Northern Natural Gas Company wants to build new pipelines and a compressor station in New Mexico and Texas to boost gas delivery to a power plant and improve their system’s reliability. The project will cost about $105 million, and they’re asking to include these costs in their regular rates. If you’re interested, you need to act before the deadline to get involved in the decision.
2026-11878 — California Department of Water Resources; Notice of Availability and Adoption of Final Environmental Assessment
The California Department of Water Resources has shared its final environmental assessment, which looks at how a new water project might affect the environment. This update mainly impacts local communities and water users by ensuring the project is safe and eco-friendly. The assessment is now official, so the project can move forward without delays or extra costs.
2026-11782 — Combined Notice of Filings
The Federal Energy Regulatory Commission got several new filings about natural gas pipeline rates and refunds from companies like NextEra Energy and ETC Tiger Pipeline. These filings could change how much customers pay starting as soon as June or July 2026. If you want to speak up or get involved, you need to act before the deadlines in mid to late June.
Previous / Next Documents
Previous: 2025-07452 — Agency Information Collection Activities; Extension; Distribution of Continued Dumping and Subsidy Offset to Affected Domestic Producers (CBP Form 7401)
The U.S. Customs and Border Protection is asking to keep collecting info on how money from anti-dumping and subsidy penalties gets shared with American businesses hurt by unfair trade. This helps make sure the right companies get paid on time. If you’re a U.S. producer affected by these trade rules, this update keeps the process running smoothly without delays.
Next: 2025-07455 — Combined Notice of Filings #1
The Federal Energy Regulatory Commission got new filings from energy companies like Enbridge and AEP about their power projects and rates. These filings include updates on generator status, rate changes, and contract cancellations that could affect energy prices and services starting as soon as late April through July 2025. If you want to comment or learn more, deadlines are coming up fast in mid-May!