Goleta Water District wants to build a small hydropower project in Goleta, California, that uses water pipes to generate clean energy without changing how water is delivered. The project could produce enough electricity to power about 20 homes each year and is currently under review. People have until a set deadline to share their thoughts or get involved before final approval.
Analyzed Economic Effects
2 provisions identified: 2 benefits, 0 costs, 0 mixed.
56 kW Conduit Project Qualifies; No License
FERC staff preliminarily determined that the proposed Ellwood Hydroelectric Energy Recovery Project in Goleta, California (56 kW installed capacity; about 214 megawatt-hours estimated annual generation) meets the statutory criteria for a qualifying conduit hydropower facility and therefore is not required to be licensed or exempted from licensing under section 30 of the Federal Power Act.
Public Comment and Intervention Deadline
Anyone may file comments, contest the qualification, or file motions to intervene in this FERC proceeding; the deadline for filing comments, comments contesting qualification, and motions to intervene is June 9, 2025. Commenters can use FERC's eFiling system or submit brief comments up to 6,000 characters via the eComment system and may contact the Commission's Office of Public Participation for help.
Your PRIA Score
Personalized for You
How does this regulation affect your finances?
Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-10313 — Commission Information Collection Activity (Ferc-549); Comment Request; Extension
FERC is extending its current paperwork rules for natural gas transactions for another three years with no changes. This affects companies involved in certain gas deals, but there’s no new cost or extra work. If you want to share your thoughts, you’ve got until June 22, 2026, to speak up!
2026-10314 — Western Area Power Administration; Notice of Filing
The Western Area Power Administration fixed a small mistake in its power rate records that started April 1, 2026. This update mainly affects customers and companies using their power rates, with a chance to comment or protest by June 4, 2026. No big money changes are announced, but folks should act fast if they want to speak up!
2026-10223 — Southwest Gas Storage Company; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Southwest Gas Storage Company wants to close and plug five old, leaky wells and related pipes in Oklahoma to keep their gas storage running smoothly. This cleanup helps stop salty water from causing problems and keeps things safe and efficient. If you want to speak up or get involved, you’ve got until a set deadline to file your protest or join the discussion.
2026-10091 — Commission Information Collection Activities (FERC-919); Comment Request; Extension
FERC is extending its current info collection rules for another three years without any changes. This affects public utilities that sell electricity at market-based rates, making sure their prices stay fair. If you want to share your thoughts, you’ve got until July 20, 2026, to comment—no extra costs or new paperwork coming your way!
2026-10095 — Commission Information Collection Activities (FERC-725S); Comment Request; Extension
FERC is asking for public comments to extend the approval of a key info collection about emergency power rules—no changes, just a renewal. This affects electric companies that help keep the lights on during emergencies. Comments are due by July 20, 2026, and there’s no new cost or paperwork increase involved.
2026-09998 — Revisions to Oil Pipeline Regulations Pursuant to the Energy Policy Act of 1992; Notice of Annual Change in the Producer Price Index for Finished Goods
Starting July 1, 2026, oil pipelines will update their maximum rates using a new number based on the Producer Price Index for Finished Goods, adjusted down by 0.55%. This change means pipeline rates can go up by about 1.4% for the next year. Pipeline companies and customers should get ready for this small but important price update that keeps things fair and predictable.
Previous / Next Documents
Previous: 2025-08628 — US SFR Owner, LLC; Kemmerer Power Station, Unit 1; Exemption
TerraPower, through its subsidiary US SFR Owner, got the green light to start some early building work at the Kemmerer Power Station before the official construction permit is in hand. This means they can do things like pile driving and foundation work on parts that aren’t critical for safety, speeding up the project without extra costs or delays. It’s a smart move to keep the energy island project on track while following the rules.
Next: 2025-08633 — Combined Notice of Filings #2
Lots of energy companies just told the Federal Energy Regulatory Commission about changes in their electric rates and project statuses. This affects solar and wind power projects across the country, with updates that could impact how much you pay for electricity. If you want to have a say, you’ve got until May 21, 2025, to comment!