Molitor, LLC wants to study building a small hydroelectric power project on Deep Creek in Idaho. They’ve got a preliminary permit application accepted, which means they get first dibs to apply for a full license later. If you care about local land or power, you can comment or compete by August 4, 2025—no money changes hands yet, but this could lead to new clean energy soon!
Analyzed Economic Effects
3 provisions identified: 2 benefits, 0 costs, 1 mixed.
Applicant Gets Priority to Apply
FERC accepted a preliminary permit application for the Molitor Hydroelectric Project on Deep Creek in Twin Falls County, Idaho. The sole purpose of a preliminary permit is to give the permit holder priority to file a full license application during the permit term.
Deadline to Comment or Compete: Aug 4, 2025
If you want to comment, intervene, or file a competing application for the Molitor Hydroelectric Project, you must file by 5:00 p.m. Eastern Time on August 4, 2025. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36 and can be filed electronically using FERC's eFiling system.
No Land Access Without Owner Consent
The notice says a preliminary permit does not authorize the permit holder to perform land‑disturbing activities or enter lands or waters owned by others without the owners' express permission. Landowners on or near Deep Creek in Twin Falls County, Idaho keep control over whether the applicant can enter or disturb their property.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-16925, Commission Information Collection Activities (FERC-725U); Comment Request; Extension
In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is soliciting public comment on the currently approved information collection FERC-725U (1902-0274), Mandatory Reliability Standards for the Bulk Power System; CIP Reliability Standards. There are no proposed changes to the reporting requirements. The comment period ended on July 27, 2026, with no comments received.
2026-16739, Venture Global CP2 LNG, LLC, Venture Global CP Express, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed CP2 LNG Expansion Project, and Notice of Public Scoping Sessions
2026-16633, Columbia Gulf Transmission, LLC; Notice of Availability of the Environmental Assessment for the Proposed Maysville Project
2026-16616, Regulatory Agenda
We are publishing our regulatory agenda (the Agenda) in accordance with Public Law 96-354, "The Regulatory Flexibility Act," and Executive Order 12866, "Regulatory Planning and Review." FERC's complete Agenda, available on OMB's website at https://www.reginfo.gov, is a compilation of all rulemaking activities on which we have recently completed action or have proposed or are considering action. Our last Agenda was provided in May 2025 and in this current agenda, we have listed 42 rulemaking activities. We also note that the Agency has one inactive rulemaking that is not listed in this Agenda. This issuance of our Agenda contains ten (10) Pre-Rules, eleven (11) Notice of Proposed Rules, eight (8) Final Rules, and thirteen (13) Completed activities. Four (4) rulemakings are Section 3(f)(1) Significant; two (2) are Other Significant; one (1) is a routine rulemaking activity; two (2) are administrative, and thirty-two (32) are Substantive, Nonsignificant rulemaking activities.
2026-16637, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from several natural gas pipeline companies about rate changes and rule updates. These changes could affect pipeline rates starting as soon as July 9, 2026, and some compliance updates kick in January 1, 2027. If you want to speak up or get involved, you need to comment by late August 2026.
2026-16525, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from natural gas pipeline companies about their rates and refunds. These filings could change how much customers pay starting as soon as September 1, 2026. If you want to speak up or get involved, you need to act by mid to late August.
Previous / Next Documents
Previous: 2025-10483, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates from Black Hills Wyoming Gas and Columbia Gas Transmission. These filings could change how much customers pay starting early June 2025. If you want to speak up or get involved, you need to act by mid to late June.
Next: 2025-10486, Information Collection Being Submitted for Review and Approval to Office of Management and Budget
The FCC is asking everyone, especially small businesses with fewer than 25 employees, to help them cut down on paperwork. They want your thoughts on how to make forms easier and less time-consuming. This review helps keep things fair and legal, making sure no one gets penalized for missing forms without proper approval.