Summary
Public Service Company of Colorado wants to make some changes to their Georgetown Hydroelectric Project license, but these changes won’t affect how much power it produces. People living near South Clear Creek and anyone interested can share their thoughts or ask to join the discussion by August 7, 2025. No big money moves are mentioned, but it’s a chance to have your say on this Colorado energy project!
Analyzed Economic Effects
2 provisions identified: 2 benefits, 0 costs, 0 mixed.
Temporary 200 cfs Stream Bypass
The licensee proposes a temporary stream bypass pipeline that could divert up to 200 cubic feet per second (cfs) from South Clear Creek around the Forebay Reservoir and Dam, discharging downstream. The bypass is intended to address dam safety and water quality, support water management until the dam can be decommissioned, and required minimum flows would continue but be delivered by a different method.
Public Comment Deadline August 7, 2025
Anyone may submit comments, protests, or motions to intervene on the Georgetown Hydroelectric Project application by August 7, 2025. FERC encourages electronic filing (including eComment for brief comments up to 6,000 characters) and notes the project docket number is P-2187-046; motions to intervene are required if you want to become a party to the proceeding.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-20744, Combined Notice of Filings #2
The Federal Energy Regulatory Commission got a new filing from Iroquois Gas Transmission about changing their natural gas rates starting November 1, 2026. This affects customers and companies using their pipeline, who might see new negotiated prices. If you want to speak up or get involved, you have until October 19, 2026, to file your comments or protests.
2026-20658, Shoshone Irrigation District; Notice of Existing Licensee's Failure To File a Timely Notice of Intent To File a New License Application, and Soliciting Notices of Intent To File a License Application and Pre-Application Documents
The Shoshone Irrigation District missed the deadline to say if they want to renew their license for the Garland Canal hydro project in Wyoming, which ends in 2031. Because of this, they’re treated as if they don’t plan to relicense, opening the door for others to step in and apply. If you’re interested, now’s the time to file your intent and get your paperwork ready!
2026-20659, Eastern Shore Natural Gas Company; Notice of Application and Establishing Intervention Deadline
Eastern Shore Natural Gas is planning a big upgrade to its pipelines in Pennsylvania, Delaware, and Maryland, including building new loops and replacing old pipes. This $75 million project will boost gas delivery for local utilities and customers, with new facilities and some old parts being removed. If you want to have a say, you need to act before the intervention deadline set by the Federal Energy Regulatory Commission.
2026-20642, Combined Notice of Filings
The Federal Energy Regulatory Commission got a new filing from Colorado Interstate Gas Company about changing a gas pipeline agreement that starts November 16, 2026. People who want to speak up or join the discussion must do so by October 14, 2026. This could affect gas rates and contracts, so keep an eye on the deadline if you’re involved!
2026-20580, Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Ventura to Farmington A-Line Abandonment and Capacity Replacement Project and Northern Lights 2027 Expansion Project
Northern Natural Gas Company plans to retire old pipeline sections in Iowa and Minnesota and build new ones to keep gas flowing smoothly and add extra capacity. This project will affect local communities and the environment but aims to do so responsibly, with a decision expected after public comments by November 2, 2026. The upgrades will help deliver more natural gas reliably, supporting energy needs without major environmental harm.
2026-20582, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from several natural gas pipeline companies about rate changes and agreements that could affect how much customers pay starting this fall. If you want to speak up or get involved, you need to comment by mid-October or late October depending on the case. These updates impact pipeline rates and contracts, so keep an eye on deadlines to have your say!
Previous / Next Documents
Previous: 2025-13024, Agency Information Collection Activities; Submission to the Office of Management and Budget (OMB) for Review and Approval; Comment Request; Groundfish Trawl Catcher Processor Economic Data Report (EDR)
The Department of Commerce wants your thoughts on a new form that groundfish trawl catcher processors need to fill out about their economic info. This helps make sure the paperwork isn’t too much and keeps things fair. You’ve got 60 days to share your feedback before the form gets the official OK—no money changes yet, just making sure the process works smoothly!
Next: 2025-13026, Spencer Mountain Hydropower, LLC; Notice of Authorization for Continued Project Operation
Spencer Mountain Hydropower, LLC gets the green light to keep running their hydroelectric project from July 1, 2025, through June 30, 2026, while waiting for a new license. This means no interruptions in power or operations, and the license will automatically renew if a new one isn’t ready by next summer. It’s a smooth ride for the company and the community relying on clean energy!