Duke Energy's Lake Keowee Water Grab Under Enviro Scrutiny
Published Date: 7/29/2025
Notice
Summary
Duke Energy Carolinas wants to let Pickens Regional Joint Water System build a water intake facility on Lake Keowee to pull up to 16.5 million gallons of water daily. The government is preparing an environmental check to make sure this project is safe for the area, with a report expected by mid-December 2025. Local communities, landowners, and nature lovers should keep an eye out and share their thoughts during the public comment period.
Analyzed Economic Effects
3 provisions identified: 2 benefits, 0 costs, 1 mixed.
Proposed Lake Keowee water intake
Pickens Regional Joint Water System has requested an easement to build a raw water intake on Lake Keowee on a 0.37 acre site. The proposal would allow a gross maximum instantaneous withdrawal rate of 16.5 million gallons per day (MGD) and a gross maximum average annual withdrawal rate of 12 MGD, and would include screened intake pipes, shoreline stabilization, and a floating dock.
Environmental assessment and 30-day comment
The Federal Energy Regulatory Commission staff intends to prepare an environmental assessment (EA) under NEPA and plans to issue the EA by December 15, 2025. When issued, the EA will be made available for a 30-day public comment period so members of the public can submit comments for staff to consider.
Help available to participate
The Commission's Office of Public Participation (OPP) can help landowners, community organizations, Tribal members, and others access information and navigate filings such as interventions, comments, or requests for rehearing. OPP contact information is provided (phone: (202) 502-6595) for people seeking assistance with participation.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-22879, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies like ATCO, Emera, and Google Energy. These filings include requests for approvals, complaints, and updates on company statuses. If you’re involved or interested, note the comment deadlines in November—they could affect how energy businesses operate and possibly impact prices or services.
2026-22878, ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is investigating whether ConocoPhillips’ electricity rates are fair or not. If found unfair, refunds could be required starting from November 10, 2026. Anyone interested has 21 days to join the case and share their views.
2026-22877, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from natural gas companies about rate changes and reports. These updates could affect customers and businesses by changing pipeline rates or how penalties are handled, with some changes starting as soon as October 2026. If you want to speak up or get involved, you need to comment by specific deadlines in November or January.
2026-22803, Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Northern Illinois Hydropower, LLC asked for more time to start and finish building their Brandon Road Hydroelectric Project in Illinois. The project sits on federal land near Rockdale and needs approval from the Federal Energy Regulatory Commission (FERC). People have until December 4, 2026, to share their thoughts or objections, so this extension could affect the project’s timeline and future energy plans.
2026-22791, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates from Texas Eastern Transmission and Enable Gas Transmission. These filings propose changes to contracts and rates starting November 1 or 5, 2026, which could affect customers and companies using these pipelines. If you want to speak up or get involved, you need to act by November 16, 2026.
2026-22721, Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Expansion Project
Transcontinental Gas Pipe Line Company wants to build new pipeline facilities in Pennsylvania to move more natural gas from the Marcellus Shale area. The government is preparing an environmental review to make sure the project is safe and will finish it by March 26, 2027. If all goes well, final approvals should happen by June 24, 2027, affecting local communities and energy customers with potential new energy options.
Previous / Next Documents
Previous: 2025-14302, Tennessee Gas Pipeline Company, L.L.C.; Southern Natural Gas Company, L.L.C.; Elba Express Company, L.L.C.; Notice of Petitions for Waiver and Establishing Intervention Deadline
Tennessee Gas Pipeline, Southern Natural Gas, and Elba Express are asking for special permission to speed up two big pipeline projects in Mississippi, Alabama, Georgia, and nearby areas. These projects will add hundreds of miles of new pipelines, compressor stations, and meter stations to boost natural gas flow. If you want to speak up or get involved, you need to act before the deadline—this could impact local energy and jobs soon!
Next: 2025-14305, Agency Information Collection Extension
The Department of Energy is extending a paperwork form for three more years, so folks who fill it out can keep doing so without interruption. This means no new costs or big changes, just more time to keep things running smoothly. If you’re involved with DOE info requests, this extension keeps everything on track through the next few years.