SEPTA Gets Extra Time to Fix Passenger Train Safety Issues
Published Date: 11/5/2025
Notice
Summary
SEPTA gets extra time to finish two important safety fixes for its Silverliner IV trains—until November 14 and December 5, 2025. They also have three new safety rules to follow to keep passengers safe. All other safety rules still stand, so SEPTA’s on the clock but moving forward with safer rides!
Analyzed Economic Effects
6 provisions identified: 3 benefits, 0 costs, 3 mixed.
Inspection Deadline Extended to Nov 14
SEPTA was given more time to finish the emergency mechanical inspections required by Condition No. 8. SEPTA must complete and certify all actions under Condition No. 8 no later than November 14, 2025.
Thermal-Circuit Install Deadline Set for Dec 5
SEPTA must install thermal protection circuits at all critical locations on every Silverliner IV EMU and certify completion no later than December 5, 2025. FRA denied SEPTA's requested extension to December 15 and set the December 5, 2025 deadline.
Train-Crew Safety Review Requirement
Starting on November 2, 2025, SEPTA must give every train crew a comprehensive safety review at the start of their first shift. The review must cover the safety failures that led to the Order, the Order's requirements, and procedures for identifying and reporting equipment defects; SEPTA must keep records of each review, including content and attendance, and make them available to FRA on request.
Mechanical-Employee Safety Review Requirement
Starting on November 2, 2025, SEPTA must give every mechanical employee a comprehensive safety review at the start of their first shift. The review must include the mechanical issues that led to the Order, the Order's requirements, inspection/test procedures developed under the Order, and significant root-cause findings; SEPTA must retain records of each review and provide them to FRA on request.
Weekly Inspection Review and Plan Updates
Until all Silverliner IV EMUs are properly inspected, repaired, and equipped with the required thermal protection circuits, SEPTA must review inspection findings at least weekly, update its Condition No. 1 plan and related notices/processes/procedures, and communicate any updates to employees via additional comprehensive safety reviews as needed.
Other Order Conditions and FRA Authority Continue
All other findings, conditions, and requirements of Emergency Order No. 34 remain in effect and unmodified by this notice. FRA retains its authority to remove Silverliner IV EMUs from service under the Order.
Your PRIA Score
Personalized for You
How does this regulation affect your finances?
Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-13296 — Petition for Approval of Test Program
Union Pacific Railroad wants to test a new locomotive control system that could make train operations safer by letting operators control trains right where the work happens. To do this, they’re asking the government to temporarily pause some safety rules during the test. If approved, the public can share their thoughts by August 31, 2026, and this test could change how trains run without extra costs for now.
2026-12849 — Notice of Petition for Waiver of Compliance
The Virginia Museum of Transportation asked for a special pass to skip removing a fragile brick inside their steam locomotive during yearly inspections. They say taking the brick out usually breaks it, but they can still check it well enough with less damage. People have until August 24, 2026, to share their thoughts, and this could save time and money while keeping the train safe.
2026-11515 — Notice of Petition for Waiver of Compliance
The Terminal Railroad Association of St. Louis (TRRA) wants to renew a special permission to skip some brake tests on their transfer trains because their blast furnace is firing back up in 2026. This means trains will start running again, and they need the waiver to keep things moving smoothly without extra brake checks. The public can share their thoughts by August 10, 2026, before the decision is made.
2026-11516 — Notice of Petition for Extension of Waiver of Compliance
St. Mary's Railway West wants to keep its special safety break that lets train workers report close calls without fear of punishment. This helps everyone stay safer by encouraging honest sharing of near-misses. The public can share their thoughts on this by August 10, 2026, but no money changes are involved.
2026-11509 — Notice of Petition for Extension of Waiver of Compliance
NJ Transit wants to keep a special break from some railroad safety rules for its River Line train that runs between Camden and Trenton, NJ. This extension helps them run and maintain their trains more smoothly without extra hassle. If you have thoughts, make sure to share them by August 10, 2026!
2026-11276 — Long Island Rail Road's Request To Amend Its Positive Train Control System
The Long Island Rail Road wants to make some changes to its safety system that helps prevent train crashes, called Positive Train Control (PTC). They asked the government for approval on May 21, 2026, and now the public can share their thoughts until June 25, 2026. These updates aim to keep trains safer without causing delays or extra costs for riders.
Previous / Next Documents
Previous: 2025-19781 — New Postal Products
The Postal Service wants to add or change some special deals for competitive mail services, and the Postal Regulatory Commission is letting everyone know and asking for comments by November 7, 2025. This affects businesses and customers who use these special mail options, but no price changes are announced yet. It’s a chance to weigh in on new or updated mail products that could shake things up soon!
Next: 2025-19786 — Product Change-Priority Mail Express, Priority Mail, and USPS Ground Advantage Negotiated Service Agreements; Priority Mail and USPS Ground Advantage Negotiated Service Agreements; Priority Mail Negotiated Service Agreements
The Postal Service is updating its shipping deals for Priority Mail Express, Priority Mail, and USPS Ground Advantage by adding new negotiated service agreements. These changes affect businesses and customers who use these services, aiming to improve shipping options and pricing. The updates were filed in late October 2025 and could mean better deals and smoother shipping soon.