FERC Opens Comments on Columbia Gas Pipeline Upgrade Project
Published Date: 1/8/2026
Notice
Summary
Columbia Gas wants to upgrade its NKY Gate facilities in parts of Kentucky and Ohio, and the government is asking the public to share their thoughts on how this might affect the environment. If you live nearby or care about nature, now’s the time to speak up before February 4, 2026. This project could change local gas operations and might involve some construction costs, so your input helps shape the final decision!
Analyzed Economic Effects
5 provisions identified: 2 benefits, 2 costs, 1 mixed.
Landowners May Be Asked for Easements
If you own land near the proposed project in Mason, Nicholas, Bracken, Pendleton, or Campbell Counties, Kentucky, or Hamilton County, Ohio, Columbia Gas may contact you to negotiate an easement to construct, operate, and maintain new pipeline facilities. You are not required to agree, but if FERC approves the project the company could initiate condemnation (eminent domain) proceedings and any compensation would be determined by a judge under state law.
Construction Will Disturb and Permanently Use Land
Building and abandoning the proposed facilities would disturb about 565.68 acres of land and Columbia would permanently maintain about 125.67 acres for operation of the new facilities; the rest would be restored and allowed to revert to former uses. Some portions of new lines would parallel existing rights-of-way (57% of Line AM36 and 100% of Line EM-7).
Old Pipelines Abandoned; New Pipelines Built
Columbia proposes to abandon about 48.54 miles of existing pipeline and construct and operate two new mains and three connecting pipelines totaling about 30.16 miles, plus four new meter/regulator stations, six pig launcher/receiver facilities, and five mainline valves. The work includes specific new segments such as a 24.62-mile 36-inch Line AM36 and a 5.02-mile 30-inch Line EM-7.
FERC Will Study Specific Environmental Issues
FERC staff will evaluate how the project could affect geology and soils, water and wetlands, wildlife and vegetation, threatened species, cultural resources, socioeconomics, land use (including nearby residences and recreation), air quality, noise, and reliability and safety. Staff has already identified issues to study such as residential construction impacts, traffic, socioeconomics, public safety, and pipeline route alternatives.
Public Comment Window and How to Comment
You can submit written comments about the project's environmental effects by 5:00 p.m. Eastern Time on February 4, 2026. FERC accepts comments via the eComment feature, eFiling (docket CP26-19-000), or by mail to the Commission (instructions in the notice).
Your PRIA Score
Personalized for You
How does this regulation affect your finances?
Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-10313 — Commission Information Collection Activity (Ferc-549); Comment Request; Extension
FERC is extending its current paperwork rules for natural gas transactions for another three years with no changes. This affects companies involved in certain gas deals, but there’s no new cost or extra work. If you want to share your thoughts, you’ve got until June 22, 2026, to speak up!
2026-10314 — Western Area Power Administration; Notice of Filing
The Western Area Power Administration fixed a small mistake in its power rate records that started April 1, 2026. This update mainly affects customers and companies using their power rates, with a chance to comment or protest by June 4, 2026. No big money changes are announced, but folks should act fast if they want to speak up!
2026-10223 — Southwest Gas Storage Company; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Southwest Gas Storage Company wants to close and plug five old, leaky wells and related pipes in Oklahoma to keep their gas storage running smoothly. This cleanup helps stop salty water from causing problems and keeps things safe and efficient. If you want to speak up or get involved, you’ve got until a set deadline to file your protest or join the discussion.
2026-10091 — Commission Information Collection Activities (FERC-919); Comment Request; Extension
FERC is extending its current info collection rules for another three years without any changes. This affects public utilities that sell electricity at market-based rates, making sure their prices stay fair. If you want to share your thoughts, you’ve got until July 20, 2026, to comment—no extra costs or new paperwork coming your way!
2026-10095 — Commission Information Collection Activities (FERC-725S); Comment Request; Extension
FERC is asking for public comments to extend the approval of a key info collection about emergency power rules—no changes, just a renewal. This affects electric companies that help keep the lights on during emergencies. Comments are due by July 20, 2026, and there’s no new cost or paperwork increase involved.
2026-09998 — Revisions to Oil Pipeline Regulations Pursuant to the Energy Policy Act of 1992; Notice of Annual Change in the Producer Price Index for Finished Goods
Starting July 1, 2026, oil pipelines will update their maximum rates using a new number based on the Producer Price Index for Finished Goods, adjusted down by 0.55%. This change means pipeline rates can go up by about 1.4% for the next year. Pipeline companies and customers should get ready for this small but important price update that keeps things fair and predictable.
Previous / Next Documents
Previous: 2026-00143 — Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates from companies like Bridgeline, Gulf South, and Rover Pipeline. These filings could change how much customers pay starting early January 2026. If you want to speak up or get involved, you need to act by mid to late January 2026.
Next: 2026-00145 — Notice of Intent To Grant a Joint Ownership Agreement With an Exclusive Patent License
The Air Force plans to share ownership and give an exclusive patent license to the University of Michigan for a cool new laser tech that makes laser pulses way clearer and stronger. If anyone has concerns, they have 15 days to speak up after this notice. This deal could speed up laser tech improvements and might bring in some money through licensing.