FERC Revises Power Grid Rules to Battle Extreme Cold Snaps
Published Date: 1/26/2026
Notice
Summary
The Federal Energy Regulatory Commission (FERC) is updating its rules about how power companies prepare for extreme cold weather to keep the electricity grid safe and reliable. They want your thoughts on these changes by February 25, 2026. This affects power companies and could mean some new paperwork but helps prevent blackouts during cold snaps.
Analyzed Economic Effects
4 provisions identified: 2 benefits, 2 costs, 0 mixed.
Stronger cold‑weather grid protections
FERC approved Reliability Standard EOP-012-3 to strengthen generator cold-weather preparedness and Generator Cold Weather Constraint declarations so more generation is available during extreme cold. The standard takes effect October 1, 2025, and is intended to help prevent blackouts during extreme cold weather events.
New paperwork burden for generator owners
The rule adds paperwork for generator owners: 1,314 U.S. generator owners each must submit one annual response taking 4 hours each, for a total of 5,256 hours and an estimated cost of $333,861.12 (using $63.52/hour). The collection increases the FERC-725S responses by +1,314 and hours by +5,256.
New constraint review and extension process
The standard adds new processes: NERC will receive, review, evaluate, and confirm the validity of each Generator Cold Weather Constraint and will accept corrective action extension requests beyond the maximum timeframe; the standard also adds Requirement R9 and Attachment 1 and requires more frequent reviews of constraint declarations. These are new compliance steps for generator owners.
No added burden for generator operators
The Commission states the revisions should not present any additional burden to generator operators compared to the previously approved EOP-012-2. The estimated additional burden applies to generator owners, not generator operators.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-17257, Bangor-Pacific Hydro Associates; Notice of Reasonable Period of Time for Water Quality Certification Application
2026-17101, Georgia Power Company; Notice of Application for Temporary Variance Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Georgia Power Company asked for a temporary change to rules at their Flint River Hydroelectric Project in Georgia. This could affect water quality rules and needs approval from state agencies. People have until September 17, 2026, to share their thoughts or get involved before any decisions are made.
2026-17103, Seefeld Corporation: Notice of Application for Surrender of Exemption Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Seefeld Corporation wants to give up its special exemption for the Smith Creek Hydroelectric Project in Washington. This change could affect local water quality rules and needs approval from the Washington Department of Ecology. People have until September 17, 2026, to share their thoughts or get involved before the decision moves forward.
2026-16925, Commission Information Collection Activities (FERC-725U); Comment Request; Extension
In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is soliciting public comment on the currently approved information collection FERC-725U (1902-0274), Mandatory Reliability Standards for the Bulk Power System; CIP Reliability Standards. There are no proposed changes to the reporting requirements. The comment period ended on July 27, 2026, with no comments received.
2026-16739, Venture Global CP2 LNG, LLC, Venture Global CP Express, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed CP2 LNG Expansion Project, and Notice of Public Scoping Sessions
2026-16616, Regulatory Agenda
We are publishing our regulatory agenda (the Agenda) in accordance with Public Law 96-354, "The Regulatory Flexibility Act," and Executive Order 12866, "Regulatory Planning and Review." FERC's complete Agenda, available on OMB's website at https://www.reginfo.gov, is a compilation of all rulemaking activities on which we have recently completed action or have proposed or are considering action. Our last Agenda was provided in May 2025 and in this current agenda, we have listed 42 rulemaking activities. We also note that the Agency has one inactive rulemaking that is not listed in this Agenda. This issuance of our Agenda contains ten (10) Pre-Rules, eleven (11) Notice of Proposed Rules, eight (8) Final Rules, and thirteen (13) Completed activities. Four (4) rulemakings are Section 3(f)(1) Significant; two (2) are Other Significant; one (1) is a routine rulemaking activity; two (2) are administrative, and thirty-two (32) are Substantive, Nonsignificant rulemaking activities.
Previous / Next Documents
Previous: 2026-01343, Arms Sales Notification
The U.S. Department of Defense is updating Congress about a big arms sale to Japan involving advanced Global Hawk drones and support gear. The deal, worth about $1.2 billion, includes new tech upgrades and extra equipment added over time. This keeps the sale fresh and ensures Japan gets the latest gear on schedule.
Next: 2026-01346, Charter Township of Van Buren, Michigan, STS Hydropower, LLC; Notice of Application for Non-Project Use Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
The Charter Township of Van Buren and STS Hydropower want to build two new docks on the Huron River in Michigan near the French Landing Hydroelectric Project. This change affects local water use and could impact the community and environment. People have until February 20, 2026, to share their thoughts or get involved before any decisions are made.