Pipeline Review Timeline Slips Two Months
Published Date: 6/24/2026
Notice
Summary
The Rockies Express Pipeline project is taking a bit longer to review because they made some changes that affect new landowners. The environmental report will now come out on October 2, 2026, pushing the final decision deadline to December 31, 2026. This means more time for everyone to weigh in and make sure the project stays safe and sound.
Analyzed Economic Effects
2 provisions identified: 1 benefits, 0 costs, 1 mixed.
Environmental review delayed; comment window
The Federal Energy Regulatory Commission staff moved the environmental assessment (EA) issuance to October 2, 2026 and set a 30-day public comment period when it is issued. The revised schedule also sets the 90-day Federal authorization decision deadline as December 31, 2026, giving the public more time to review and comment before agencies reach final decisions.
Project changes affect new landowners
On May 15, 2026, Rockies Express Pipeline filed changes that add and modify facilities and explicitly affect new landowners; staff issued a Notice of Amendment Establishing Intervention Deadline on May 22, 2026. The Commission staff said it needs more time to incorporate those changes into the EA.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-20744, Combined Notice of Filings #2
The Federal Energy Regulatory Commission got a new filing from Iroquois Gas Transmission about changing their natural gas rates starting November 1, 2026. This affects customers and companies using their pipeline, who might see new negotiated prices. If you want to speak up or get involved, you have until October 19, 2026, to file your comments or protests.
2026-20658, Shoshone Irrigation District; Notice of Existing Licensee's Failure To File a Timely Notice of Intent To File a New License Application, and Soliciting Notices of Intent To File a License Application and Pre-Application Documents
The Shoshone Irrigation District missed the deadline to say if they want to renew their license for the Garland Canal hydro project in Wyoming, which ends in 2031. Because of this, they’re treated as if they don’t plan to relicense, opening the door for others to step in and apply. If you’re interested, now’s the time to file your intent and get your paperwork ready!
2026-20659, Eastern Shore Natural Gas Company; Notice of Application and Establishing Intervention Deadline
Eastern Shore Natural Gas is planning a big upgrade to its pipelines in Pennsylvania, Delaware, and Maryland, including building new loops and replacing old pipes. This $75 million project will boost gas delivery for local utilities and customers, with new facilities and some old parts being removed. If you want to have a say, you need to act before the intervention deadline set by the Federal Energy Regulatory Commission.
2026-20642, Combined Notice of Filings
The Federal Energy Regulatory Commission got a new filing from Colorado Interstate Gas Company about changing a gas pipeline agreement that starts November 16, 2026. People who want to speak up or join the discussion must do so by October 14, 2026. This could affect gas rates and contracts, so keep an eye on the deadline if you’re involved!
2026-20580, Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Ventura to Farmington A-Line Abandonment and Capacity Replacement Project and Northern Lights 2027 Expansion Project
Northern Natural Gas Company plans to retire old pipeline sections in Iowa and Minnesota and build new ones to keep gas flowing smoothly and add extra capacity. This project will affect local communities and the environment but aims to do so responsibly, with a decision expected after public comments by November 2, 2026. The upgrades will help deliver more natural gas reliably, supporting energy needs without major environmental harm.
2026-20582, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from several natural gas pipeline companies about rate changes and agreements that could affect how much customers pay starting this fall. If you want to speak up or get involved, you need to comment by mid-October or late October depending on the case. These updates impact pipeline rates and contracts, so keep an eye on deadlines to have your say!
Previous / Next Documents
Previous: 2026-12622, Demonstrating Substantial Evidence of Effectiveness for Human Drug and Biological Products; Revised Draft Guidance for Industry; Availability
The FDA just released a new draft guide to help drug makers prove their medicines really work, using smarter and faster science. This update affects companies developing human drugs and biological products, aiming to save time and money by allowing strong evidence from just one good clinical study plus extra proof. Comments on this draft are open until September 22, 2026, so industry folks have a chance to weigh in before it becomes final.
Next: 2026-12624, Bluff Spur Pumped Storage, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications
Bluff Spur Pumped Storage, LLC wants to study building a big energy storage project in Wise County, Virginia, that could generate lots of clean power. The government is now accepting comments and competing ideas until August 17, 2026, so locals and energy fans have a chance to weigh in. This project could bring new jobs and cleaner energy, but no construction can start yet without permission.