FERC Sets Timeline for Texas Gas Lateral Project Review

Published Date: 8/4/2026

Notice

Summary

No summary available.

Analyzed Economic Effects

2 provisions identified: 1 benefits, 1 costs, 0 mixed.

Landowners face property and farming impacts

Texas Gas would build an approximately 11.8-mile, 20-inch interstate natural gas pipeline through Indiana, Kentucky, and Ohio to deliver up to 265,000 dekatherms per day. Private landowners along the route may see impacts to farming operations, maple syrup and honey production, woodlands, groundwater and drinking-water springs, stocked ponds and outflow structures, farmland privacy, and property values, and commenters raised concerns about increased trespassing and the possible use of eminent domain.

Environmental review timeline set by FERC

FERC staff intends to issue an Environmental Assessment (EA) on January 15, 2027. The EA will be available for a 30-day public comment period, and the 90-day Federal Authorization Decision deadline for agencies is April 15, 2027.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
Effective Date
8/4/2026
1/15/2027

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register