Erie Hydropower Application Ready for FERC Green Light
Published Date: 8/7/2026
Notice
Summary
No summary available.
Analyzed Economic Effects
5 provisions identified: 4 benefits, 0 costs, 1 mixed.
Minimum downstream flow requirement continues
If you use the Black River downstream of the Beebee Island dam, the project will continue releasing a minimum flow of 1,000 cubic feet per second (cfs) or the inflow, whichever is less, and a year-round minimum flow of 14 cfs into the bypassed reach. These flows are part of the applicant’s proposed operations under the new license.
Seasonal 37 cfs fish/ice chute release set
The project will continue a provision to release 37 cubic feet per second (cfs) from the ice chute from April 1 through November 30. This schedule affects river flows and habitat during those dates each year.
Water level minimums kept near dam crest
The applicant proposes to maintain impoundment water levels no lower than 0.5 foot below the crest of the dam or flashboards, if present. This setpoint governs how low the reservoir behind the dam can be drawn.
Replacement of wooden flashboards with inflatable gates
The applicant proposes to replace existing 3-foot-high wooden flashboards with 3-foot-high inflatable rubber crest gates at the project. This change alters how the dam crest is operated and controlled.
Boating access and veiling flows to be continued
The applicant will continue to operate and maintain a hand-carry boat access site and directional signage, and provide one-half inch veiling flows over the dam center section from May 1 to October 31. These measures affect recreational boaters and river access during those dates.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-16065, Gulf South Pipeline Company, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Gulf South Pipeline Company wants to build a new 16-mile pipeline in Texas to help deliver natural gas to a power plant switching from coal to gas. This $46.8 million project will boost energy supply for Southwestern Electric Power Company and needs approval soon. If you want to speak up or protest, you’ve got a deadline to meet!
2026-15883, Tres Palacios Gas Storage LLC; Notice of Application and Establishing Intervention Deadline
Tres Palacios Gas Storage LLC wants to expand its Texas gas storage by adding three new giant caverns, new pipelines, and powerful compressors. This upgrade will boost their storage capacity by over 50% and speed up gas injection by 650 million cubic feet daily. If you’re interested, you’ve got until a set deadline to speak up or join the process—this could impact local energy storage and market rates.
2026-15780, Texas Gas Transmission, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Dearborn County Lateral Project
2026-15639, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got a bunch of new electric rate filings from big energy players like Duke Energy, Idaho Power, and several grid operators. These filings include updates to tariffs and agreements that could affect how electricity rates and services work, with some changes kicking in as soon as July 22, 2026. If you’re involved in energy or just curious, keep an eye out for public comments due by mid-August and possible impacts on future electricity costs.
2026-15694, Vinton Dome Storage Hub, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Vinton Dome Storage Hub Project
2026-15693, Guardian Pipeline, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Guardian 3 Expansion Project
Guardian Pipeline wants to expand its gas pipeline in parts of Illinois and Wisconsin, which could affect local communities and the environment. The government is asking people to share their thoughts on possible environmental impacts by August 28, 2026, to help decide if the project should move forward. This expansion could mean new construction and changes in how gas moves through the area, with important decisions coming soon.
Previous / Next Documents
Previous: 2026-16169, Erie Boulevard Hydropower, L.P.; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions
Next: 2026-16171, Pacific Gas & Electric Company; Notice of Application for Minimum Flow Variance Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Pacific Gas & Electric wants to temporarily change how much water flows into Bear River near their Drum Spaulding Hydroelectric Project in California. This affects local communities, wildlife, and federal lands managed by several agencies. People have until September 3, 2026, to share their thoughts or get involved before any changes happen—no money changes are mentioned yet.