Gas Giant Adds Chillers in Georgia to Power Up New Plant

Published Date: 9/8/2026

Notice

Summary

Transcontinental Gas Pipe Line Company wants to add two new air chillers at a station in Georgia to boost gas delivery for a new power plant. This $20.1 million project will help move 75,000 dekatherms of gas daily without increasing the station’s power. If you want to speak up or get involved, there’s a deadline to do so soon!

Analyzed Economic Effects

3 provisions identified: 1 benefits, 1 costs, 1 mixed.

Two New Chillers Add Pipeline Capacity

Transcontinental Gas Pipe Line Company filed to install two air-cooled inlet air chillers at Station 116 in Carroll County, Georgia to support new power generation demand. Transco says the $20.1 million project will allow it to provide Digital Realty Trust, L.P. with 75,000 dekatherms per day of incremental firm transportation from Coweta County to Bartow County and asserts the station's certificated horsepower will not increase.

Deadline to File Protests and Comments

You can file a protest, a motion to intervene, or a comment about this pipeline project for free. The deadline to file is 5:00 p.m. Eastern Time on November 2, 2026, and you may file online via FERC's eFiling or by mailing a paper copy to the Commission.

Automatic Authorization If No Protest

If no protest is filed by 5:00 p.m. Eastern Time on November 2, 2026, or if a filed protest is withdrawn within 30 days after the deadline, the project will be automatically authorized effective the day after the protest deadline. That automatic authorization rule means the Commission will consider the activity approved unless a timely unresolved protest leads it to do otherwise.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
9/8/2026

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register