Arkansas Gas Pipeline Plan Up for Protests
Published Date: 9/17/2026
Notice
Summary
Enable Gas Transmission, LLC wants to build a new 13-mile natural gas pipeline and a delivery station in Arkansas to help power a new plant. This $59 million project will boost gas delivery by 150 million cubic feet per day, benefiting Hatchbo, LLC’s power facility. People have until a set deadline to speak up or protest before the plan moves forward.
Analyzed Economic Effects
2 provisions identified: 1 benefits, 0 costs, 1 mixed.
New 13‑Mile Gas Pipeline in Arkansas
If you live in Pope County or Johnson County, Arkansas, Enable Gas Transmission plans to build a new 13-mile, 16-inch interstate natural gas lateral and a delivery meter station. The project is estimated to cost $58.95 million, would have a capacity of 218 MMcf/day, and would allow 150 MMcf/day of incremental firm service to Hatchbo, LLC's proposed power facility.
How and When to Object or Intervene
You can file a protest, motion to intervene, or comment about this project at no cost. The deadline for protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on November 13, 2026; if no valid protest is filed or a protest is withdrawn within 30 days after the allowed time for filing, the proposed activity is deemed authorized the day after the protest filing period.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-18988, Black Canyon Hydro, LLC; Notice of Intent To Prepare a Supplemental Environmental Impact Statement for the Seminoe Pumped Storage Project, Schedule for Environmental Review, and Request For Comments
2026-18990, Great Lakes Hydro America, LLC; Notice of Reasonable Period of Time for Water Quality Certification Application
2026-18995, Tennessee Gas Pipeline Company L.L.C.; Notice of Schedule for the Preparation of an Environmental Assessment for the South Texas Enhancement Project
2026-18991, Vinton Dome Storage Hub, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Vinton Dome Storage Hub Project
2026-18872, Commission Information Collection Activities (FERC-912); Comment Request; Extension
FERC is keeping the current rules for small power producers and cogeneration facilities the same and wants to extend the paperwork requirements for another three years. No changes mean no extra hassle or costs, but they’re asking for public comments by October 15, 2026. If you’re involved in small power production, this is your chance to speak up or stay informed!
2026-18871, Commission Information Collection Activities (FERC-556); Comment Request; Extension
In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is soliciting public comment on the currently approved information collection FERC-556 (OMB Control No. 1902-0075) Certification of Qualifying Facility (QF) Status for a Small Power Production or Cogeneration Facility. The comment period ended on September 8, 2026, with no comments received. There were no changes to the reporting requirements.