Mine Proposes a New Route for Its Underground Return Air

Published Date: 11/17/2026

Notice

Summary

Ramaco Resources wants to change a safety rule about how air moves in their Tiller No. 1 mine in Virginia. They’re asking to let return air flow through a new path to the surface, promising it’s just as safe as current rules. Everyone can share their thoughts by December 17, 2026, and this could affect how ventilation works without extra costs.

Analyzed Economic Effects

5 provisions identified: 4 benefits, 1 costs, 0 mixed.

Allow return air via surface ventilation tube

Ramaco has asked MSHA to let the return air course enter a ventilation tube at the bottom of the existing slope and be carried to the surface instead of using a separate underground return entry. This request is for Tiller No. 1 Mine (MSHA ID 44-06804) and explicitly seeks a modification of 30 CFR 75.301.

Specified equipment and airflow requirements

The petitioner proposes a continuous ventilation tube with a minimum outside diameter of 42 inches made of MSHA‑approved materials, attached or secured underground, connected to an exhausting surface fan (a 929 RBB Centrifugal exhauster at up to 900 RPM producing up to 30 IN/WG vacuum). The petitioner anticipates 60,000 CFM through the exhaust tubing and 84,000 CFM or more supplied by the main blowing fan.

Shift and weekly examination requirements for tubing

The petitioner states the belt/neutral slope entry with the tubing will be examined each shift per 30 CFR 75.360, and weekly certified-examiner inspections will inspect the outside perimeter of the 1,030-foot tube and all connectors. The tubing will include at least three ports for Pitot‑tube airflow readings (within 50 feet of the tube start, near the 500-foot midpoint, and within 50 feet of the surface fan).

Temporary measure until new air shafts constructed

Ramaco intends the ventilation tube method to be temporary: new air shafts are planned once the mine reaches the Castle Seam, and the petitioner anticipates completing the new air shafts within 9 to 12 months after slope construction begins. At that time, the alternative return air course would no longer be needed.

Public comment deadline for the petition

MSHA is accepting public comments on Docket No. MSHA-2026-0991; comments must be received on or before December 17, 2026, via Regulations.gov or the contact channels listed in the notice.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
Comments Due
11/17/2026
12/17/2026

Department and Agencies

Department
Independent Agency
Agency
Labor Department
Mine Safety and Health Administration
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register