Coal-Mine Proximity Sensors Face Another Round of Federal Paperwork
Published Date: 11/17/2026
Notice
Summary
The Mine Safety and Health Administration wants to keep collecting info on safety systems that help prevent accidents with mining machines underground. This affects coal mine operators who use these machines and helps keep miners safe without adding extra paperwork hassle. Comments on this plan are open until January 19, 2027, so speak up if you have thoughts!
Analyzed Economic Effects
5 provisions identified: 0 benefits, 1 costs, 4 mixed.
Shift checks and certification for machines
If you operate continuous mining machines, a designated person must check machine-mounted proximity detection components either at the beginning of each shift when the machine is to be used, immediately before operation if it was not used at shift start, or within 1 hour of a shift change that occurs without an interruption in production (30 CFR 75.1732(c)(1)). A certified person must then certify the check by initials, date, and time, and record any defects and corrective actions before the end of the shift (30 CFR 75.1732(d)(1)).
Shift checks and records for wearable components
Operators must check miner-wearable proximity detection components at the beginning of each shift they will be used and correct defects before use (30 CFR 75.1732(c)(2)). The operator must make a record each shift of defects found, corrective actions taken, and dates of corrective actions (30 CFR 75.1732(d)(2)).
Training records for installation and maintenance
Operators must keep records of the persons trained in the installation and maintenance of proximity detection systems, as required under 30 CFR 75.1732(b)(6) and 75.1732(d)(3).
Secure recordkeeping and inspection access
Operators must maintain records in a secure book or electronically in a secure computer system not susceptible to alteration and retain those records for at least one year. Records must be made available for inspection by authorized representatives of the Secretary and representatives of miners (30 CFR 75.1732(d)(4)–(d)(5)).
ICR extension and paperwork burden estimates
MSHA proposes an extension without change of the information collection (OMB Control No. 1219-0148) for proximity detection systems. The notice reports 142 annual respondents, 229,744 annual responses, an annual time burden of 653 hours, annual recordkeeping costs of $0, and requests comments by January 19, 2027.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-15670, Roof Control Plan Approval Criteria
In response to a public request, the Mine Safety and Health Administration (MSHA) is reopening the rulemaking record and is scheduling a virtual public hearing on the Agency's proposed rule published on July 1, 2025, titled, "Roof Control Plan Approval Criteria."
2026-15717, Ventilation Plan Approval Criteria
In response to a public request, the Mine Safety and Health Administration (MSHA) is reopening the rulemaking record and is scheduling a virtual public hearing on the Agency's proposed rule published on July 1, 2025, titled, "Ventilation Plan Approval Criteria."
2026-10456, Department of Labor Federal Civil Penalties Inflation Adjustment Act Annual Adjustments for 2026
Good news for businesses and workers: the Department of Labor won’t raise any fines or penalties in 2026 because the usual inflation data wasn’t available. This means all civil penalties stay the same starting May 27, 2026. So, no surprise cost hikes this year—just steady rules and steady fees!
2025-12232, Ventilation Plan Approval Criteria
The Mine Safety and Health Administration (MSHA) wants to change how mine ventilation plans get approved. They’re removing the power of District Managers to add extra rules, making the process clearer and fairer. Mine operators should get ready to comment by July 31, 2025, but no big costs or delays are expected.
2026-23390, Respirable Crystalline Silica and Respiratory Protection
This update fixes a small mistake in the rules about protecting miners from harmful silica dust. It affects underground and surface coal mine operators by clarifying exposure limits to dangerous dust and gases. The correction takes effect November 17, 2026, helping keep miners safer without adding big costs.
2026-23307, Petition for Modification of Application of Existing Mandatory Safety Standards
Ramaco Resources wants to change a safety rule about how air moves in their Tiller No. 1 mine in Virginia. They’re asking to let return air flow through a new path to the surface, promising it’s just as safe as current rules. Everyone can share their thoughts by December 17, 2026, and this could affect how ventilation works without extra costs.
Previous / Next Documents
Previous: 2026-23311, Petition for Modification of Application of Existing Mandatory Safety Standards
Ramaco Resources wants to change a safety rule for their Tiller No. 1 mine in Virginia. They’re asking to stop weekly air checks at a certain point in the mine’s ventilation system, saying it’s just as safe. If approved, this could save time and money while keeping miners safe. Everyone has until December 17, 2026, to share their thoughts on this change.
Next: 2026-23313, Proposed Extension of Information Collection: Training Plans and Records of Training for Underground Miners and Miners Working at Surface Mines and Surface Areas of Underground Mines
The Mine Safety and Health Administration wants to keep collecting info on training plans and records for miners working underground and on surface mines. They’re asking for public feedback by January 19, 2027, to make sure the paperwork is clear and not too much work. This helps keep miners safe without wasting time or money on confusing forms.