2025-13870Notice

Alaska Hydro Plant Seeks Quick Capacity Upgrade Approval

Published Date: 7/23/2025

Notice

Summary

The Southeast Alaska Power Agency wants to increase the power capacity of its Tyee Lake Hydroelectric Project in Wrangell, Alaska. The Federal Energy Regulatory Commission has accepted this request and is skipping some early review steps to speed things up. People and groups affected have until August 19, 2025, to share their thoughts or get involved—this could impact local energy supply and future costs.

Analyzed Economic Effects

1 provisions identified: 1 benefits, 0 costs, 0 mixed.

Tyee Lake capacity rises to 33.75 MW

The Tyee Lake Hydroelectric Project would add a third 11.25-MW turbine, increasing the installed capacity from 22.50 MW to 33.75 MW. This change is meant to allow the licensee to meet current energy demand for Petersburg, Wrangell, and Ketchikan (Alaska) and to significantly reduce reliance on diesel generation.

Your PRIA Score

Score Hidden

Personalized for You

How does this regulation affect your finances?

Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.

Free to start

Key Dates

Published Date
7/23/2025

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML
Back to Federal Register

Take It Personal

Get Your Personalized Policy View

Start a Free Government Policy Watch to see how policy affects your household, then upgrade to PRIA Full Coverage for year-round monitoring.

Already have an account? Sign in