All Roll Calls
Yes: 230 • No: 30
Sponsored By: Linville
Failed
Personalized for You
Personalize government policy and PRIA will tell you what this bill means for your household, plus every other piece of legislation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
7 provisions identified: 5 benefits, 2 costs, 0 mixed.
Applicants for transmission lines of 200 kilovolts or more must give clear and convincing proof that allocated costs roughly match ratepayer benefits. This test covers costs assigned to West Virginia utilities serving customers, including otherwise unrecoverable costs charged to them. Applicants must fund needed connections serving West Virginia retail customers within a reasonable time after a valid, approved request. Applications must examine alternatives, including advanced transmission technology; applicants may use that technology when necessary and economical. The Public Service Commission may consider those options and their costs, but the law sets no household savings amount.
The Public Service Commission can enforce key siting conditions through applicable civil or criminal penalties, court orders, or injunctions. Before construction of a facility or major change is complete, it can also suspend or revoke the certificate. Any person can ask a circuit court to compel compliance with those conditions. Key conditions remain binding after the certificate or any ownership share in the generating facility is transferred. The original holder and new holder remain under the Commission's continuing authority.
The Public Service Commission must decide covered generating-facility siting applications, including major changes, within 270 days, down from 300. If it misses that deadline, it must issue the certificate as requested. Electric project applicants can also seek or obtain local and other government permits before getting their required state utility certificate. That state certificate is still required.
The Public Service Commission must decide covered utility certificate applications within 240 days of filing, down from 270. Water and sewer projects costing under $10 million have a 190-day deadline, down from 225. The longer review schedule now applies only above $100 million, rather than above $50 million. Those projects have a 360-day deadline, down from 400. After a hearing, covered decisions are due within 60 days of final submission, down from 90, unless another deadline applies.
Qualifying West Virginia local-government water or sewer providers are exempt from the utility certificate requirement and its related 30-day notice. Providers must have at least 4,500 customers and at least $3 million in annual combined gross revenue. The exemption does not specify a change to household bills or service eligibility.
The Public Service Commission can set fees by rule for siting applications and changes to existing certificates. The law sets no fee amount and specifies no direct household charge. Any fees collected go into the state treasury's fund for the Commission.
Utilities and other covered parties must get a state utility certificate before maintaining or repairing existing transmission facilities, conductors, or structures. The Public Service Commission can waive this requirement.
Linville
Affiliation unavailable
Ray Canterbury
Republican • House
Wayne Clark
Republican • House
Marty Gearheart
Republican • House
Michael Hornby
Republican • House
John Paul Hott
Republican • House
Tristan Leavitt
Republican • House
Phil Mallow
Republican • House
Mickey Petitto
Republican • House
Jimmy Willis
Republican • House
Mark Zatezalo
Republican • House
All Roll Calls
Yes: 230 • No: 30
House vote • 3/14/2026
Motion for previous question adopted (Roll No. 595)
Yes: 72 • No: 24
Senate vote • 3/13/2026
Effective from passage (Roll No. 526)
Yes: 33 • No: 0
Senate vote • 3/13/2026
Passed Senate with amended title (Roll No. 525)
Yes: 29 • No: 5
House vote • 2/11/2026
Passed House (Roll No. 72)
Yes: 96 • No: 1
House received Senate message
Motion for previous question adopted (Roll No. 595)
House refused to concur; requested Senate to recede (Voice)
Communicated to Senate
On 3rd reading with right to amend
Read 3rd time
Committee amendment withdrawn by unanimous consent
Floor amendment adopted (Voice vote)
Passed Senate with amended title (Roll No. 525)
Effective from passage (Roll No. 526)
Senate requests House to concur
Reported do pass, with amendment and title amendment
Immediate consideration
Read 2nd time
Without recommendation, but first rereferred to Energy, Industry, and Mining
Immediate consideration
Read 1st time
On 2nd reading, rereferred to Energy, Industry, and Mining
Introduced in Senate
To Energy, Industry, and Mining
To Energy, Industry, and Mining
On 3rd reading, Special Calendar
Read 3rd time
Passed House (Roll No. 72)
Title amendment adopted (Voice vote)
Committee Substitute
Engrossed
Introduced Version
HB 5694, Supplemental appropriation to Department of Education, fund 0313.
HB 5353, To bring virtual currency kiosks within the purview of money transmission licensure and create disclosure requirements and daily transaction limitations for new and existing customers.
HB 4452, To remove Mortmain restrictions on religious organizations
HB 4390, Relating to the temporary payment to a kinship parent of a subsidy equal to that of a foster parent
HB 4354, Relating to necessity allowance
HB 4191, Relating to providing child care generally