15.1.B.22-22-305 15 CAR § 22-305. Hearing officer
0.3K chars
15 CAR § 22-305. Hearing officer. The Director of the Arkansas Natural Resources Commission or his or her designee shall: (1) Preside at hearings on applications; and (2) Have the powers granted presiding officers by the Arkansas Administrative Procedure Act, Arkansas Code § 25-1…
15.1.B.22-22-401 15 CAR § 22-401. Procedures generally
0.5K chars
15 CAR § 22-401. Procedures generally. (a) The applicant shall: (1) Submit a master plan in the same form as applications for approval of other projects; and (2) Specify a time frame for constructing each phase of the proposed project. (b) The Arkansas Natural Resources Commissio…
15.1.B.22-22-402 15 CAR § 22-402. Effect of approval
0.5K chars
15 CAR § 22-402. Effect of approval. (a) If the Director of the Arkansas Natural Resources Commission approves the master plan, the applicant shall construct the project in the timeframe and manner approved in the master plan. (b) Upon notice to the applicant and opportunity for …
15.1.B.22-22-403 15 CAR § 22-403. Additional reporting requirements
0.4K chars
15 CAR § 22-403. Additional reporting requirements. (a) As each project listed in a master plan is developed for construction, the applicant shall notify the Arkansas Natural Resources Commission. (b) If the scope of work represents a significant departure from the master plan, t…
15.1.B.22-22-501 15 CAR § 22-501. Protection of service areas
0.5K chars
15 CAR § 22-501. Protection of service areas. It is unlawful for a person to provide water or wastewater services to an area where such services are being provided by a current provider that has pledged or uses revenue derived from services within the area to repay financial assi…
15.1.B.22-22-502 15 CAR § 22-502. Conditional approval based on partial payment to the commission
0.4K chars
15 CAR § 22-502. Conditional approval based on partial payment to the commission. (a) As a condition of its approval, the Arkansas Natural Resources Commission may require the payment of an equitable portion of the outstanding financial assistance provided. (b) Any payment made s…
15.1.B.22-22-503 15 CAR § 22-503. Approval process
1.7K chars
15 CAR § 22-503. Approval process. (a) Upon agreement of the providers exchanging territory, the providers shall submit a written proposal to the Director of the Arkansas Natural Resources Commission for consideration. (b) The proposal may be made part of an application for proje…
15.1.B.22-22-601 15 CAR § 22-601. Procedures generally
2.0K chars
15 CAR § 22-601. Procedures generally. (a)(1) Prior to acquiring rural water or wastewater service properties, facilities, and customers pursuant to Arkansas Code § 14-208-102, a municipality shall receive approval from the Arkansas Natural Resources Commission that the action co…
15.1.B.22-22-701 15 CAR § 22-701. Compliance criteria
0.4K chars
15 CAR § 22-701. Compliance criteria. The Director of the Arkansas Natural Resources Commission shall not approve any application unless he or she determines that the project: (1) Complies with and implements the goals and objectives of the Arkansas Water Plan; and (2) Adequately…
15.1.B.22-22-702 15 CAR § 22-702. Determination of compliance
0.4K chars
15 CAR § 22-702. Determination of compliance. (a) The Director of the Arkansas Natural Resources Commission may approve all or part of an application. (b) An applicant may refile at any time any application, or part thereof, that has been disapproved if the director determines th…
15.1.B.22-22-703 15 CAR § 22-703. Notice of decision
0.1K chars
15 CAR § 22-703. Notice of decision. A copy of the decision shall be provided to the applicant and to any aggrieved party so requesting.
15.1.B.22-22-704 15 CAR § 22-704. Incorporation into Arkansas Water Plan
0.3K chars
15 CAR § 22-704. Incorporation into Arkansas Water Plan. Upon approval of the application, the: (1) Project shall constitute an amendment of the Arkansas Water Plan; and (2) Arkansas Water Plan shall be deemed amended accordingly.
15.1.B.22-22-801 15 CAR § 22-801. Request for review by commission
1.0K chars
15 CAR § 22-801. Request for review by commission. (a) Any decision of the Director of the Arkansas Natural Resources Commission may be reviewed by the Arkansas Natural Resources Commission pursuant to the procedure set out in Subpart 5 of Rules of Organization and General Operat…
15.1.B.23-23-1001 15 CAR § 23-1001. Emergency action plans required
0.1K chars
15 CAR § 23-1001. Emergency action plans required. An emergency action plan must be prepared by the owner for all permitted high hazard dams.
15.1.B.23-23-1002 15 CAR § 23-1002. Approval of emergency action plans required
0.2K chars
15 CAR § 23-1002. Approval of emergency action plans required. Written approval of the Chief Engineer of the Arkansas Natural Resources Commission must be obtained for all EAPs.
15.1.B.23-23-1003 15 CAR § 23-1003. Contents of emergency action plans
0.2K chars
15 CAR § 23-1003. Contents of emergency action plans. (a) Site conditions will dictate exact contents of specific EAPs. (b) Guidelines for preparation of EAPs are available from the Arkansas Natural Resources Commission.
15.1.B.23-23-1004 15 CAR § 23-1004. Annual exercises and drills
0.4K chars
15 CAR § 23-1004. Annual exercises and drills. (a) Implementation of EAPs must include at least: (1) One (1) tabletop exercise per year; and (2) One (1) test drill every three (3) years. (b) The Chief Engineer of the Arkansas Natural Resources Commission must be notified at least…
15.1.B.23-23-101 15 CAR § 23-101. Purpose
0.4K chars
15 CAR § 23-101. Purpose. (a) Provide for the comprehensive regulation and supervision of dams for the protection of the health, safety, welfare, and property of the citizens of Arkansas. (b) Assure proper planning, design, construction, maintenance, monitoring, and supervision o…
15.1.B.23-23-102 15 CAR § 23-102. Definitions
3.5K chars
15 CAR § 23-102. Definitions. Unless clearly indicated by context, the following words and terms, when used in this part, shall have meanings as defined below: (1) “Billing volume” means normal storage designed to contain sediment accumulation over the life of the dam; (2) “Chief…
15.1.B.23-23-103 15 CAR § 23-103. Scope
0.3K chars
15 CAR § 23-103. Scope. All dams within the State of Arkansas, except those owned by the United States Government or those exempted by 15 CAR § 23-104, must have a valid construction and operation permit issued under the provisions of this part.
15.1.B.23-23-104 15 CAR § 23-104. Exemptions
0.4K chars
15 CAR § 23-104. Exemptions. Dams meeting any of the following criteria are not subject to rules contained in this part unless 15 CAR § 23-105 is successfully invoked: (1) Dams with height less than twenty-five feet (25’); (2) Dams with normal storage less than fifty acre-feet (5…
15.1.B.23-23-105 15 CAR § 23-105. Petition by affected persons
1.0K chars
15 CAR § 23-105. Petition by affected persons. (a) Persons who believe themselves or their property to be endangered by failure of a dam that is below the size requirements specified in 15 CAR § 23-104 may file a petition requesting that the Arkansas Natural Resources Commission …
15.1.B.23-23-106 15 CAR § 23-106. Duties, obligations, and liabilities of dam owners
0.3K chars
15 CAR § 23-106. Duties, obligations, and liabilities of dam owners. Nothing in this part shall be construed to relieve an owner or operator of a dam or reservoir of the legal duties, obligations, or liabilities incident to ownership or operation.
15.1.B.23-23-107 15 CAR § 23-107. No liability by commission, employees, or agents
0.8K chars
15 CAR § 23-107. No liability by commission, employees, or agents. No action shall be brought against the state or the Arkansas Natural Resources Commission or its employees or agents for the recovery of damages caused by the partial or total failure of any dam or reservoir or th…
15.1.B.23-23-108 15 CAR § 23-108. Exceptions
0.4K chars
15 CAR § 23-108. Exceptions. (a) The Arkansas Natural Resources Commission may grant exceptions to requirements contained within this part. (b) Any variance from this part must be supported by written approval of the Director of the Arkansas Natural Resources Commission setting f…
15.1.B.23-23-1101 15 CAR § 23-1101. Approval of plans required
0.2K chars
15 CAR § 23-1101. Approval of plans required. Prior to removal, a plan for removal and revegetation must be approved by the Chief Engineer of the Arkansas Natural Resources Commission.
15.1.B.23-23-1102 15 CAR § 23-1102. Notice to downstream landowners
0.2K chars
15 CAR § 23-1102. Notice to downstream landowners. Downstream landowners must be notified of the proposed action if any measure of flood protection would be lost due to the removal of the dam.
15.1.B.23-23-1103 15 CAR § 23-1103. Rights of other landowners
0.3K chars
15 CAR § 23-1103. Rights of other landowners. Downstream landowners and those adjacent to the reservoir have the right to notice of projected changes in streamflow patterns or reservoir levels but do not have the right to continued benefits at the dam owner’s expense, unless the …
15.1.B.23-23-1104 15 CAR § 23-1104. Procedure for breaching
0.2K chars
15 CAR § 23-1104. Procedure for breaching. The procedure for breaching must adequately guard against downstream: (1) Flooding; (2) Erosion; and (3) Sedimentation.
15.1.B.23-23-1105 15 CAR § 23-1105. Restoration of original stream channel
0.2K chars
15 CAR § 23-1105. Restoration of original stream channel. Dimensions of the final cut through the dam must be defined in the plan and must be of sufficient size to prevent impounding water when streamflow equals the one hundred-year flood.
15.1.B.23-23-1106 15 CAR § 23-1106. Erosion protection
0.2K chars
15 CAR § 23-1106. Erosion protection. The plan must provide for establishment of vegetation or other erosion protection measures sufficient to guard against deposition of excessive sediment off site.
15.1.B.23-23-201 15 CAR § 23-201. Construction permit
0.2K chars
15 CAR § 23-201. Construction permit. A permit issued by the Arkansas Natural Resources Commission is required prior to construction of any dam not exempted under 15 CAR § 23-103 or § 23-104.
15.1.B.23-23-202 15 CAR § 23-202. Operation permit
0.6K chars
15 CAR § 23-202. Operation permit. (a)(1) Before water is deliberately impounded by closing drain gates on a newly constructed dam, an operation permit must be issued by the Arkansas Natural Resources Commission. (2) An operation permit will be issued by the Chief Engineer of the…
15.1.B.23-23-203 15 CAR § 23-203. Transfer of permit
0.3K chars
15 CAR § 23-203. Transfer of permit. (a) Within six (6) months after change of ownership of a permitted dam, the new owner shall notify the Arkansas Natural Resources Commission. (b) The commission shall issue a dam permit in the name of the new owner.
15.1.B.23-23-204 15 CAR § 23-204. Water plan compliance
0.3K chars
15 CAR § 23-204. Water plan compliance. (a) Filing of an application to permit a proposed dam also serves as filing for Water Plan Compliance Certification as described in 15 CAR § 22-205. (b) The water plan compliance process may run concurrently with the dam permit review.…
15.1.B.23-23-205 15 CAR § 23-205. Application
0.2K chars
15 CAR § 23-205. Application. Applicants for dam permits must provide all applicable information requested on the form supplied by the Arkansas Natural Resources Commission.
15.1.B.23-23-206 15 CAR § 23-206. Commission review
0.4K chars
15 CAR § 23-206. Commission review. (a) Upon receipt of application for dam permit, the Arkansas Natural Resources Commission staff will review data presented to determine compliance with: (1) State law; (2) Commission rules; and (3) Accepted engineering practices. (b) If necessa…
15.1.B.23-23-207 15 CAR § 23-207. Public notice
0.9K chars
15 CAR § 23-207. Public notice. (a) Upon completion of Arkansas Natural Resources Commission review, the Director of the Arkansas Natural Resources Commission will cause a public notice to be published two (2) times, one (1) week apart. (b) The public notice will be placed in a n…
15.1.B.23-23-208 15 CAR § 23-208. Public hearing
0.9K chars
15 CAR § 23-208. Public hearing. (a) If requested, the Director of the Arkansas Natural Resources Commission shall cause a public hearing to be conducted within the county in which the dam is/will be located. (b) Said hearing will be for the purpose of: (1) Describing the propose…
15.1.B.23-23-209 15 CAR § 23-209. Commission action
0.5K chars
15 CAR § 23-209. Commission action. (a) If no public hearing is requested as a result of the public notice, the Director of the Arkansas Natural Resources Commission will either approve or deny the permit request. (b) If a public hearing is requested as a result of the public not…
15.1.B.23-23-301 15 CAR § 23-301. Estimated application review fees
0.4K chars
15 CAR § 23-301. Estimated application review fees. Any application for permitting a proposed dam after March 24, 1993, shall be accompanied by a check for one percent (1%) of the estimated construction cost of the dam or one hundred dollars ($100), whichever is greater, except t…
15.1.B.23-23-302 15 CAR § 23-302. Final cost report
0.2K chars
15 CAR § 23-302. Final cost report. The owner shall provide to the Arkansas Natural Resources Commission a report of actual construction costs within forty-five (45) days after completion of construction.
15.1.B.23-23-303 15 CAR § 23-303. Final application review fees
0.4K chars
15 CAR § 23-303. Final application review fees. (a) If the estimated application review fee exceeds the fee based on actual construction cost, an amount equal to the difference will be refunded. (b) If the fee based on construction cost exceeds the estimated application review fe…
15.1.B.23-23-304 15 CAR § 23-304. Annual permit fee
1.1K chars
15 CAR § 23-304. Annual permit fee. (a) The annual permit fee shall be computed as specified in Arkansas Code § 15-22-219, as may be amended from time to time. (b) Excerpt from Arkansas Code § 15-22-219: “(b)(1) Any person obtaining a permit under the provisions of § 15-22-210, i…
15.1.B.23-23-401 15 CAR § 23-401. Notice of nonemergency deficiency
0.5K chars
15 CAR § 23-401. Notice of nonemergency deficiency. (a) Upon discovery of a deficiency that does not immediately threaten the dam’s safety, the Chief Engineer of the Arkansas Natural Resources Commission will issue a letter: (1) Specifying actions necessary to remedy the problem;…
15.1.B.23-23-402 15 CAR § 23-402. Public hearings
0.6K chars
15 CAR § 23-402. Public hearings. (a) In the event remedial measures for nonemergency deficiencies cannot be accomplished through the means of consent orders, the Director of the Arkansas Natural Resources Commission shall cause a public hearing to be conducted to: (1) Present th…
15.1.B.23-23-403 15 CAR § 23-403. Commission orders
0.2K chars
15 CAR § 23-403. Commission orders. After review of findings of the public hearing, the Arkansas Natural Resources Commission may issue orders compelling specified actions.
15.1.B.23-23-404 15 CAR § 23-404. Penalties
0.3K chars
15 CAR § 23-404. Penalties. (a) Noncompliance with Arkansas Natural Resources Commission rules or disregard of commission orders may result in fines up to ten thousand dollars ($10,000). (b) In general, penalties will be set by doubling the costs incurred by the commission.…
15.1.B.23-23-405 15 CAR § 23-405. Emergency remedial orders
0.4K chars
15 CAR § 23-405. Emergency remedial orders. (a) Upon discovery of a condition that renders a dam subject to rapid failure, the Director of the Arkansas Natural Resources Commission may issue an Emergency Remedial Order describing actions that must be taken to protect life and pro…
15.1.B.23-23-406 15 CAR § 23-406. Appeals
0.2K chars
15 CAR § 23-406. Appeals. Actions by the Arkansas Natural Resources Commission may be appealed as described in Subpart 5 of Organization and General Operation of the Arkansas Natural Resources Commission, 15 CAR pt. 1.