29.1-A1-1113 Project Planning: Policy - Planning. All capital improve-
0.9K chars
§1113. Project Planning: Policy - Planning. All capital improve- ment projects must be subjected to proper planning processes to assure that the following project requirements are fully and properly ad- dressed, evaluated and resolved: (a) Function and compatibility with an estab…
29.1-A1-1114 Same: Application. The provisions of §§1103 through 1124 3 GAR [this Section] shall apply to all capital improvement pro-
0.3K chars
§1114. Same: Application. The provisions of §§1103 through 1124 3 GAR [this Section] shall apply to all capital improvement pro- jects under the purview of the Department or more specifically, those projects assigned to any Engineering or Operations division of this Department.
29.1-A1-1115 Same: Project Planning Procedures . The following are procedures governing the planning of all projects. Planning shall be
0.8K chars
§1115. Same: Project Planning Procedures . The following are procedures governing the planning of all projects. Planning shall be defined as any activity which precedes the actual production of con- struction plans and specifications. Planning activities include but are not limit…
29.1-A1-1116 Same: Determination. (a) The Chief of Engineering shall determine whether planning, wholly or in part, can best be accom-
0.4K chars
§1116. Same: Determination. (a) The Chief of Engineering shall determine whether planning, wholly or in part, can best be accom- plished in-house, or whether the nature and magnitude of the project is such that consultant services are required. (b) Should planning by consultant b…
29.1-A1-1117 Same: Planning. Whether planning is done wholly, or in part in-house, or by consultant, the Project Manager must assure that
1.5K chars
§1117. Same: Planning. Whether planning is done wholly, or in part in-house, or by consultant, the Project Manager must assure that the following are accomplished: (a) The Using Agency parameters that contribute of the project program and design are established; (b) The project s…
29.1-A1-1118 Same: Public and Special Interest Group Participation
0.9K chars
§1118. Same: Public and Special Interest Group Participation in Project Planning Activities. The Principal Engineer shall determine if a project has sufficient impact on environment, the public, a commu- nity or a special interest group to warrant a public or special meeting. If …
29.1-A1-1119 Same: Same: Evaluation of Results. The Project Man- ager shall assure that all comments and suggestions made during the
0.3K chars
§1119. Same: Same: Evaluation of Results. The Project Man- ager shall assure that all comments and suggestions made during the meeting are thoroughly evaluated. The Project Manager shall incorpo- rate into the project all feasible and beneficial comments or suggestions before fin…
29.1-A1-1120 Same: Preparation of the Design Scope of Work. Based
0.2K chars
§1120. Same: Preparation of the Design Scope of Work. Based upon planning results, the Project Manager shall establish the project design concept and detailed design scope of work.
29.1-A1-1121 Same: Same: Required Provisions of the Design Scope of Work. The Project Manager (or Consultant when appropriate) shall
1.3K chars
§1121. Same: Same: Required Provisions of the Design Scope of Work. The Project Manager (or Consultant when appropriate) shall prepare a detailed design scope of work which must define and set forth the following provisions: (a) Intent of the Design Contract (b) Project Location …
29.1-A1-1122 Same: Same: Approval of the Scope of Work . The Project Manager shall assure that:
0.5K chars
§1122. Same: Same: Approval of the Scope of Work . The Project Manager shall assure that: (a) The Scope is satisfactory to the Director or authorized representative of the Using Agency and to a participating federal agency, if appropriate. (b) The Scope must then be submitted to …
29.1-A1-1123 Same: Identification of Preliminary Project Costs. The Project Manager shall prepare (on Schedule A as shown in Plate 7) a
0.8K chars
§1123. Same: Identification of Preliminary Project Costs. The Project Manager shall prepare (on Schedule A as shown in Plate 7) a Project Budget which must program the probable costs for the follow- ing: (a) Planning and Design (b) Contract Administration (c) Real Estate Acquisit…
29.1-A1-1124 Same: Filing of Project Management Documents. The
0.2K chars
§1124. Same: Filing of Project Management Documents. The Project Manager shall assure that all official actions related to project planning are documented and filed in accordance with §§1111 and 1112.
29.1-A1-1125 Procurement of Consultant Services: Policy . Only professionally qualified, experienced and reputable consultant firms
0.6K chars
§1125. Procurement of Consultant Services: Policy . Only professionally qualified, experienced and reputable consultant firms shall be engaged to provide project planning and/or design services. Negotiations shall be carried out, contracts executed and administered in accordance …
29.1-A1-1126 Same: Application. The provisions of §§1125 through 1144 apply to all activities involved with procurement of consultant
0.2K chars
§1126. Same: Application. The provisions of §§1125 through 1144 apply to all activities involved with procurement of consultant contracts for planning or engineering services.
29.1-A1-1127 Same: Professional Consultant Files. The Chief of
2.1K chars
§1127. Same: Professional Consultant Files. The Chief of Engineering shall be responsible for creating, maintaining and updating the files of all planning, surveying, architectural and engineering con- sultants who are qualified to provide the Government with professional service…
29.1-A1-1128 and 1137 will be repeated once again
0.6K chars
§§1128 and 1137 will be repeated once again. Ch. 1 - Director of Public Works Art. 1 - Policies, Procedures & Regulations - 1997 - p. 23 (g) If an agreement is reached, the Principal Engineer shall initiate a formal contract with the consultant using the standard departmental con…
29.1-A1-1129 Same: Same: Board of Review- Authority and Respon- sibilities. (a) Membership. The Board of Review is a committee con-
2.4K chars
§1129. Same: Same: Board of Review- Authority and Respon- sibilities. (a) Membership. The Board of Review is a committee con- vened and chaired by the Principal Engineer of the Implementing Division and consists of the following members: (1) Chief of Engineering (2) Principal Eng…
29.1-A1-1130 Same: Same: Slate Selection (or Pre-selection of Con- sultants). The Principal Engineer shall convene a Board of Review to
1.9K chars
§1130. Same: Same: Slate Selection (or Pre-selection of Con- sultants). The Principal Engineer shall convene a Board of Review to prepare and evaluate a slate of qualified consultants based upon the following criteria: (a) Specialized experience in the type of work required; (b) …
29.1-A1-1131 Same: Same: Final Selection of Consultants. The follow- ing shall govern the final selection of consultants:
1.1K chars
§1131. Same: Same: Final Selection of Consultants. The follow- ing shall govern the final selection of consultants: (a) The slate must be narrowed to three (3) firms in order of preference. (The standard selection work sheet with rating instruc- tions illustrated by Plate 8 shall…
29.1-A1-1132 Same: Procedures for Conduct of Negotiations. The following procedures shall govern the conduct of negotiations with
0.1K chars
§1132. Same: Procedures for Conduct of Negotiations. The following procedures shall govern the conduct of negotiations with selected consultants.
29.1-A1-1133 Same: Same: Negotiating Committee - Authority and Responsibilities. The negotiating committee is normally composed of
0.9K chars
§1133. Same: Same: Negotiating Committee - Authority and Responsibilities. The negotiating committee is normally composed of the Principal Engineer and the Project Manager. The size and specific membership of the committee may be in- creased should the Principal Engineer decide t…
29.1-A1-1134 Same: Same: Scope of Services. The design Scope of Work developed in accordance with §§1120 through 1122 of this
0.3K chars
§1134. Same: Same: Scope of Services. The design Scope of Work developed in accordance with §§1120 through 1122 of this Manual shall be used as the preliminary scope of services. During negotiations the contract scope of services shall be finalized between the consultant and the …
29.1-A1-1135 Same: Same: Independent Cost Estimate. Before the selected consultant is notified, the Project Manager shall prepare an
0.3K chars
§1135. Same: Same: Independent Cost Estimate. Before the selected consultant is notified, the Project Manager shall prepare an independent cost estimate of the work (see §1123 of this Subchapter [Manual]). This estimate will then be used as the basis of a mutually agreeable fee.
29.1-A1-1136 Same: Same: Notification and Preparation for Negotia-
0.8K chars
§1136. Same: Same: Notification and Preparation for Negotia- tions. The Principal Engineer shall inform the consultant of the selec- tion in writing. He shall then arrange and conduct a conference with the consultant to explain the scope of services, departmental project man- age…
29.1-A1-1137 Same: Same: Proposal, Review and Conduct of Negoti-
1.8K chars
§1137. Same: Same: Proposal, Review and Conduct of Negoti- ations. (a) The Principal Engineer and his staff shall review the proposal to determine whether the scope of services was understood; the desired format followed; and if the fee as detailed is fair, reasonable and within …
29.1-A1-1138 Same: Contract Award and Notice to Proceed. (a) Low
1.8K chars
§1138. Same: Contract Award and Notice to Proceed. (a) Low Value Consultant Contract. If the negotiated contract fee is equal to or less than Ten Thousand Dollars ($10,000.00), the contract may be processed as a Low Value Contract - that is, the contract may be ap- proved by the …
29.1-A1-1139 Same: Amendments to Professional Consultant Con- tracts. Amendments may be made to professional consultant contracts
0.5K chars
§1139. Same: Amendments to Professional Consultant Con- tracts. Amendments may be made to professional consultant contracts for the following reasons: (a) Increase the scope of work and corresponding increase in contract amount. (b) Decrease the scope of work and corresponding de…
29.1-A1-1140 Same: Same: Format . Amendments shall be executed on the standard departmental format (CD-2)
0.1K chars
§1140. Same: Same: Format . Amendments shall be executed on the standard departmental format (CD-2).
29.1-A1-1141 Same: Same: Notification, Negotiation and Award
0.7K chars
§1141. Same: Same: Notification, Negotiation and Award. Notification, negotiation and award of amendments shall be generally in accord with procedures set forth in §§1131 to 1138 as modified to suit the purpose. The Director may approve amendments whose total value does not excee…
29.1-A1-1142 Same: Contract Provisions and Administration: Provi- sions of Contract. The formal contract shall be executed on the Stan-
0.4K chars
§1142. Same: Contract Provisions and Administration: Provi- sions of Contract. The formal contract shall be executed on the Stan- dard Departmental Contract Document CD-1 (Plate 10). The provisions of CD-1 are hereby adopted for official. There shall be no deviations from these p…
29.1-A1-1143 Same: Same: Administration. The Project Manager shall be responsible for assuring compliance with all contract provisions,
0.5K chars
§1143. Same: Same: Administration. The Project Manager shall be responsible for assuring compliance with all contract provisions, scope of work and schedule as set forth in CD-1 and §§1145 through 1153. The Project Manager shall immediately notify his Principal Ch. 1 - Director o…
29.1-A1-1144 Same: Same: References on Public Contract Practices
0.5K chars
§1144. Same: Same: References on Public Contract Practices. The Code of Federal Regulations, Subtitle A, Chapters 1 and 2 are hereby adopted as official references on contracting and contract administration practices. A copy of these regulations shall be retained by the Chief of …
29.1-A1-1145 Project Design: Policy. The design of capital improve- ment projects shall be undertaken only after proper planning has been
0.9K chars
§1145. Project Design: Policy. The design of capital improve- ment projects shall be undertaken only after proper planning has been accomplished as set forth in §1113 through 1124 of the Subchapter [Manual]. The design of capital improvement projects shall assure at all times tha…
29.1-A1-1146 Same: Application. The provisions of §§1145 through
0.3K chars
§1146. Same: Application. The provisions of §§1145 through 1153 shall apply to all capital improvement projects under the purview of the Department or, more specifically, those projects assigned to any Engineering or Operations divisions of this Department.
29.1-A1-1147 Same: Project Design Procedures . The following are
1.1K chars
§1147. Same: Project Design Procedures . The following are procedures governing the design of all projects. Design shall be defined as the actual development of complete construction plans, specifica- tions and detailed cost estimates in accordance with an approved scope of work.…
29.1-A1-1148 Same: Determination. (a) The Chief of Engineering shall determine whether design of a project, whole or in part can best be
0.5K chars
§1148. Same: Determination. (a) The Chief of Engineering shall determine whether design of a project, whole or in part can best be accomplished in-house, or whether the nature and magnitude of the project or current workload is such that consultant services are re- quired. (b) Sh…
29.1-A1-1149 Same: Design. Whether design is accomplished wholly, or
1.8K chars
§1149. Same: Design. Whether design is accomplished wholly, or in part, in house or by consultant, the Project Manager shall assure that the following are accomplished: (a) Design is in accordance with the approved design scope of work and in conformance with all applicable codes…
29.1-A1-1150 Same: Design Review and Submittal. All design work
0.7K chars
§1150. Same: Design Review and Submittal. All design work shall be reviewed by the Project Manager, his Chief Project Manager (or team leader) and the Principal Engineer, as a minimum. If design is by consultant, the Project Manager shall be responsible for the detail review of p…
29.1-A1-1151 Same: Same: Design Submittal. (a) Definition. A submittal is defined as the body of documents prearranged and desig-
2.4K chars
§1151. Same: Same: Design Submittal. (a) Definition. A submittal is defined as the body of documents prearranged and desig- nated by the approved design scope of work and/or contract for sub- mission to reviewing authorities and staff for the purpose of securing approval or concu…
29.1-A1-1152 Same: Same: Delineation of Review Responsibilities Within the Department of Public Works . The following defines and
2.4K chars
§1152. Same: Same: Delineation of Review Responsibilities Within the Department of Public Works . The following defines and delineates each DPW Division's (or Section if applicable) responsibility and authority for review of project plan and specifications: DIVISION/(OR SECTION) …
29.1-A1-1153 Same: Approval of Construction Plans, Specifications and Cost Estimates. The following procedures define the necessary
2.7K chars
§1153. Same: Approval of Construction Plans, Specifications and Cost Estimates. The following procedures define the necessary approvals which must be obtained for all project plans, specifications and cost estimates: (a) Acceptance by the Implementing Division. The Project Manage…
29.1-A1-1154 Project (Construction) Implementation Program Formulation, Review and Approval: Policy . Before any project
0.3K chars
§1154. Project (Construction) Implementation Program Formulation, Review and Approval: Policy . Before any project proceeds to the bid or negotiation phase, a construction permit must be acquired and within authorized funding constraints and to assure that funds are released and …
29.1-A1-1155 Same: Application. The provisions of §§1154 through
0.2K chars
§1155. Same: Application. The provisions of §§1154 through 1159 apply to all projects which have been authorized for construction either by legislation, or, if appropriate, directly by the Governor.
29.1-A1-1156 Same: Permits. All construction or renovation of govern- ment facilities must comply with the following permit procedures and
6.1K chars
§1156. Same: Permits. All construction or renovation of govern- ment facilities must comply with the following permit procedures and programs: (a) Building Permits: (1) Before a notice to proceed to construct is issued, the division who is responsible for administering the constr…
29.1-A1-1157 Same: Program Approval - Satisfactory Budget. After
0.2K chars
§1157. Same: Program Approval - Satisfactory Budget. After resolving the permit requirements, the Project Manager shall determine whether the project can be constructed within the available funds and, if so, proceed with the Bid Phase.
29.1-A1-1158 Same: Alternative Procedures - Unsatisfactory Budget
1.0K chars
§1158. Same: Alternative Procedures - Unsatisfactory Budget. If the project costs exceeds available funds, the Project Manager shall proceed with one of the following alternatives: (a) Program an incremental development of the project, such that the first increment can be constru…
29.1-A1-1159 Same: Documentation of Program Approval . All program alternative activities and policies shall be documented, pre-
0.2K chars
§1159. Same: Documentation of Program Approval . All program alternative activities and policies shall be documented, pre- pared for the Director's signature and routed to the Director via the Chief of Engineering.
29.1-A1-1160 Bid Phase - Procurement of Construction Contracts: Policy - Procurement of Construction Contracts. Except as otherwise
0.4K chars
§1160. Bid Phase - Procurement of Construction Contracts: Policy - Procurement of Construction Contracts. Except as otherwise Ch. 1 - Director of Public Works Art. 1 - Policies, Procedures & Regulations - 1997 - p. 35 provided in [Section 7] of this [Manual], construction of capi…
29.1-A1-1161 Same: Application. The provisions of §§1160 through
0.3K chars
§1161. Same: Application. The provisions of §§1160 through 1183 shall apply to all project under the purview of the Department of Public Works. The following procedures shall guide all Principal Engineers and Project Managers when preparing project plans and specifications for pu…
29.1-A1-1162 Same: Same: Preparation of Plans, Specifications and Cost Estimates for Bid. The Principal Engineer of the Implementing
0.3K chars
§1162. Same: Same: Preparation of Plans, Specifications and Cost Estimates for Bid. The Principal Engineer of the Implementing Division shall assure that project plans and specifications are finalized, accepted and approved in accord with §§1151 through 1153 of this Subchapter [M…