105 sections in this chapter.
ORS 279C.510 Demolition contracts to require material salvage; lawn and landscape maintenance contracts to require composting or mulching. (1) Every public improvement contract for demolition shall contain a condition requiring the contractor to salvage or recycle construction and demolition debris, if feasible and cost-effective
0.2K chars
(2) Every public improvement contract for lawn and landscape maintenance shall contain a condition requiring the contractor to compost or mulch yard waste material at an approved site, if feasible and cost-effective. [2003 c.794 §139]
ORS 279C.515 Conditions concerning payment of claims by public officers, payment to persons furnishing labor or materials and complaints. (1) Every public improvement contract must contain a clause or condition that, if the contractor fails, neglects or refuses to pay promptly a person’s claim for labor or services that the person provides to the contractor or a subcontractor in connection with the public improvement contract as the claim becomes due, the proper officer that represents the state or a county, school district, municipality or municipal corporation or a subdivision of the state, county, school district, municipality or municipal corporation may pay the amount of the claim to the person that provides the labor or services and charge the amount of the payment against funds due or to become due the contractor by reason of the contract
1.4K chars
(2) Every public improvement contract must contain a clause or condition that, if the contractor or a first-tier subcontractor fails, neglects or refuses to pay a person that provides labor or materials in connection with the public improvement contract within 30 days after recei…
ORS 279C.520 Condition concerning hours of labor; compliance with pay equity provisions; employee discussions of rate of pay or benefits. (1) Every public contract subject to this chapter must provide that
3.6K chars
(a) A contractor may not employ an employee for more than 10 hours in any one day, or 40 hours in any one week, except in cases of necessity, emergency or when the public policy absolutely requires otherwise, and in such cases, except in cases of contracts for personal services a…
ORS 279C.525 Provisions concerning environmental and natural resources laws; remedies. (1) Solicitation documents for a public improvement contract shall make specific reference to federal, state and local agencies that have enacted ordinances, rules or regulations dealing with the prevention of environmental pollution and the preservation of natural resources that affect the performance of the contract. If the successful bidder awarded the project is delayed or must undertake additional work by reason of existing ordinances, rules or regulations of agencies not cited in the public improvement contract or due to the enactment of new or the amendment of existing statutes, ordinances, rules or regulations relating to the prevention of environmental pollution and the preservation of natural resources occurring after the submission of the successful bid, the contracting agency may
4.4K chars
(a) Terminate the contract; (b) Complete the work itself; (c) Use nonagency forces already under contract with the contracting agency; (d) Require that the underlying property owner be responsible for cleanup; (e) Solicit bids for a new contractor to provide the necessary service…
ORS 279C.527 Inclusion of amount for green energy technology or woody biomass energy technology in public improvement contract; written determination of appropriateness; conditions, exemptions and limitations; rules. (1) As used in this section and ORS 279C.528
15.2K chars
(a)(A) “Green energy technology” means a system that employs: (i) Solar or geothermal energy directly for space or water heating or to generate electricity; (ii) Building design that uses solar energy passively to reduce energy use from other sources by at least 10 percent from a…
ORS 279C.528 State Department of Energy requirements and specifications; record keeping requirements; rules. (1) Each contracting agency, in soliciting, awarding and administering public improvement contracts that are subject to ORS 279C.527, is subject to rules the State Department of Energy adopts that include, but are not limited to, requirements, methods and specifications for
4.2K chars
(a) Using particular green energy technologies in public improvements; (b) Determining the cost-effectiveness of green energy technologies; (c) Determining the total solar resource fraction that applies to a public building or to a site on which a contracting agency will construc…
ORS 279C.530 Condition concerning payment for medical care and providing workers’ compensation. (1) Every public improvement contract shall contain a condition that the contractor shall promptly, as due, make payment to any person, copartnership, association or corporation furnishing medical, surgical and hospital care services or other needed care and attention, incident to sickness or injury, to the employees of the contractor, of all sums that the contractor agrees to pay for the services and all moneys and sums that the contractor collected or deducted from the wages of employees under any law, contract or agreement for the purpose of providing or paying for the services
0.3K chars
(2) Every public contract subject to this chapter shall contain a clause or condition that all subject employers working under the contract are either employers that will comply with ORS 656.017 or employers that are exempt under ORS 656.126. [2003 c.794 §143; 2005 c.103 §30]
ORS 279C.533 (1) As used in this section
11.6K chars
(a) “Apprentice” has the meaning given that term in ORS 660.010. (b) “Apprenticeable occupation” has the meaning given that term in ORS 660.010. (c) “Apprenticeship agreement” has the meaning given that term in ORS 660.010. (d) “Apprenticeship training program” means the total sy…
ORS 279C.534 Advisory committee for monitoring implementation of apprenticeship condition in public improvement contracts. (1) The Bureau of Labor and Industries shall establish and provide staffing for an advisory committee to monitor the implementation of, to advise state contracting agencies on compliance with, and to advise the Legislative Assembly on changes needed for better implementation of the requirements set forth in ORS 279C.533
2.2K chars
(2) The advisory committee consists of six members appointed by the Governor for a term of four years, with equal representation from construction contractors that have completed public improvement contracts for the state, or from an association of construction contractors, and f…
ORS 279C.535 Condition concerning steel material; rules. The Department of Transportation shall adopt rules to require that public improvement contracts entered into by the department include a price escalation and de-escalation clause relating to steel material. As used in this section, “steel material” includes structural and reinforcing steel, steel studs, sheet piling, guardrail, ductile iron pipe and other steel products used for the construction, reconstruction or major renovation of a road or highway. [2005 c.557 §6]
0.0K chars
[Repealed or reserved.]
ORS 279C.537 Condition concerning use of diesel engines in motor vehicles used in performing certain public improvement contracts; rules. (1) As used in this section, “diesel engine,” “nonroad diesel engine” and “motor vehicle” have the meanings given those terms in ORS 468A.795
2.7K chars
(2) Except as provided in subsection (4) of this section, a public improvement contract must require at least 80 percent of the total fleet of motor vehicles that are motor vehicles powered by diesel engines and equipment powered by nonroad diesel engines used on site and in the …
ORS 279C.540 Maximum hours of labor on public contracts; holidays; exceptions; liability to workers; rules. (1) When labor is employed by the state or a county, school district, municipality, municipal corporation or subdivision thereof through a contractor, a person may not be required or permitted to labor more than 10 hours in any one day, or 40 hours in any one week, except in cases of necessity or emergency or when the public policy absolutely requires it, in which event, the person so employed for excessive hours shall receive at least time and a half pay
4.4K chars
(a)(A) For all overtime in excess of eight hours in any one day or 40 hours in any one week when the work week is five consecutive days, Monday through Friday; or (B) For all overtime in excess of 10 hours in any one day or 40 hours in any one week when the work week is four cons…
ORS 279C.545 Time limitation on claim for overtime; posting of circular by contractor. When labor is employed by the state or a county, school district, municipality, municipal corporation or subdivision thereof through another as a contractor, any worker employed by the contractor shall be foreclosed from the right to collect for any overtime provided in ORS 279C.540 unless a claim for payment is filed with the contractor within 90 days from the completion of the contract, providing the contractor has
0.5K chars
(1) Caused a circular clearly printed in boldfaced 12-point type and containing a copy of this section to be posted in a prominent place alongside the door of the timekeeper’s office or in a similar place that is readily available and freely visible to workers employed on the wor…
ORS 279C.550 “Retainage” defined. As used in ORS 279C.550 to 279C.570, “retainage” means the difference between the amount earned by a contractor on a public improvement contract and the amount paid on the contract by the contracting agency. [2003 c.794 §146; 2005 c.103 §32]
0.0K chars
[Repealed or reserved.]
ORS 279C.555 Withholding of retainage. The withholding of retainage by a contractor or subcontractor on public improvement contracts shall be in accordance with ORS 701.420. [2003 c.794 §147; 2013 c.410 §1]
0.0K chars
[Repealed or reserved.]
ORS 279C.560 Form of retainage; requirements for surety bonds; conditions for rejecting bonds, securities or other instruments; allocation of costs; procedures for holding and payment; requirement for contractor to accept bonds, securities or other instruments from subcontractors. (1)(a) A contractor may submit and a contracting agency shall accept from a contractor in lieu of withholding moneys for all or a portion of the retainage required under a public contract
7.2K chars
(A) Bonds, securities or other instruments of a character described in subsection (6) of this section that are deposited as provided in subsection (4) of this section; or (B) A surety bond deposited as provided in subsection (7) of this section. (b) A surety bond that a contracto…
ORS 279C.565 Limitation on retainage requirements. Unless otherwise specifically included by statute, the provisions of ORS 279C.560 or 279C.625 apply only as between the contracting agency or public body and the party with whom it contracts. [2003 c.794 §149]
0.0K chars
[Repealed or reserved.]
ORS 279C.570 Prompt payment policy; progress payments; retainage; interest; exception; settlement of compensation disputes. (1) The policy of the State of Oregon is that all payments due on a public improvement contract and owed by a contracting agency must be paid promptly. No contracting agency is exempt from the provisions of this section
5.9K chars
(2) Contracting agencies shall make progress payments on the contract monthly as work progresses on a public improvement contract. Payments shall be based upon estimates of work completed that are approved by the contracting agency. A progress payment is not considered acceptance…
ORS 279C.580 Contractor’s relations with subcontractors. (1) A contractor may not request payment from the contracting agency of any amount withheld or retained in accordance with subsection (5) of this section until the contractor has determined and certified to the contracting agency that the subcontractor has determined and certified to the contracting agency that the subcontractor is entitled to the payment
10.1K chars
(2) A dispute between a contractor and first-tier subcontractor relating to the amount or entitlement of a first-tier subcontractor to a payment or a late payment interest penalty under a clause included in the subcontract under subsection (3) or (4) of this section does not cons…
ORS 279C.585 Authority to substitute undisclosed first-tier subcontractor; circumstances; rules. A contractor whose bid is accepted may substitute a first-tier subcontractor that was not disclosed under ORS 279C.370 by submitting the name of the new subcontractor and the reason for the substitution in writing to the contracting agency. A contractor may substitute a first-tier subcontractor under this section in the following circumstances
1.9K chars
(1) When the subcontractor disclosed under ORS 279C.370 fails or refuses to execute a written contract after having had a reasonable opportunity to do so after the written contract, which must be reasonably based upon the general terms, conditions, plans and specifications for th…
ORS 279C.590 Complaint process for substitutions of subcontractors; civil penalties. (1)(a) A subcontractor disclosed under ORS 279C.370 may file a complaint based on the subcontractor disclosure requirements under ORS 279C.370 with the Construction Contractors Board about a contractor if the contractor has substituted another subcontractor for the complaining subcontractor
4.3K chars
(b) If more than one subcontractor files a complaint with the board under paragraph (a) of this subsection relating to a single subcontractor disclosure, the board shall consolidate the complaints into one proceeding. If the board imposes a civil penalty under this section agains…
ORS 279C.600 Right of action on payment bond or public works bond of contractor or subcontractor; notice of claim. (1) A person claiming to have supplied labor or materials for the performance of the work provided for in a public contract, including any person having a direct contractual relationship with the contractor furnishing the payment bond or a direct contractual relationship with any subcontractor, or an assignee of such person, or a person claiming moneys due the State Accident Insurance Fund Corporation, the Unemployment Compensation Trust Fund or the Department of Revenue in connection with the performance of the contract, has a right of action on the contractor’s payment bond as provided for in ORS 279C.380 and 279C.400 only if
1.8K chars
(a) The person or the assignee of the person has not been paid in full; and (b) The person gives written notice of claim, as prescribed in ORS 279C.605, to the contractor and the contracting agency. (2) When, upon investigation, the Commissioner of the Bureau of Labor and Industr…
ORS 279C.605 Notice of claim. (1) The notice of claim required by ORS 279C.600 must be sent by registered or certified mail or hand delivered no later than 180 days after the day the person last provided labor or furnished materials or 180 days after the worker listed in the notice of claim by the Commissioner of the Bureau of Labor and Industries last provided labor. The notice may be sent or delivered to the contractor or subcontractor at any place the contractor or subcontractor maintains an office or conducts business or at the residence of the contractor or subcontractor
2.0K chars
(2) Notwithstanding subsection (1) of this section, if the claim is for a required contribution to a fund of an employee benefit plan, the notice required by ORS 279C.600 must be sent or delivered within 200 days after the employee last provided labor or materials. (3) The notice…
ORS 279C.610 Action on contractor’s public works bond or payment bond; time limitation. (1) The Commissioner of the Bureau of Labor and Industries or a person who has a right of action on the public works bond or the payment bond under ORS 279C.600 and, where required, who has filed and served the notice or notices of claim, as required under ORS 279C.600 and 279C.605, or that person’s assignee, may institute an action on the contractor’s public works bond or payment bond in a circuit court of this state or the federal district court of the district
0.7K chars
(2) The action shall be on the relation of the commissioner, the claimant, or that person’s assignee, as the case may be, and shall be in the name of the contracting agency that let the contract or, when applicable, the public agency or agencies for whose benefit the contract was…
ORS 279C.615 Preference for labor and material liens. All labor and material liens have preference and are superior to all other liens and claims of any kind or nature created by ORS 279C.500 to 279C.530 and 279C.600 to 279C.625. [2003 c.794 §157]
0.0K chars
[Repealed or reserved.]
ORS 279C.620 Rights of person providing medical care to employees of contractor. A person providing medical, surgical or hospital care services or other needed care and attention, incident to sickness or injury, to the employees of a contractor or subcontractor on a public contract is deemed to have performed labor on the public contract for the purposes of ORS 279C.600 to 279C.625. [2003 c.794 §158]
0.0K chars
[Repealed or reserved.]
ORS 279C.625 Joint liability when payment bond not executed. If the public improvement contract is one for which a payment bond as provided for in ORS 279C.380 and 279C.400 is required and the contractor fails to pay for labor or materials or to pay claims due the Industrial Accident Fund, the Unemployment Compensation Trust Fund or the Department of Revenue and the officers of the public body that authorized the contract fail or neglect to require the person entering into the contract to execute the payment bond
0.8K chars
(1) The State of Oregon and the officers authorizing the contract shall be jointly liable for the labor and materials used in the performance of any work under the contract, and for claims due the Industrial Accident Fund, the Unemployment Compensation Trust Fund and the Departme…
ORS 279C.650 “Labor dispute” defined. As used in ORS 279C.650 to 279C.670, “labor dispute” has the meaning given that term in ORS 662.010. [2003 c.794 §160]
0.0K chars
[Repealed or reserved.]
ORS 279C.655 Extension and compensation when work suspended. If a public contract is not terminated but work under the contract is suspended by an order of a contracting agency for any reason considered to be in the public interest other than a labor dispute or any third-party judicial proceeding relating to the work other than a suit or action filed in regards to a labor dispute, the contractor is entitled to a reasonable extension of the contract time and reasonable compensation for all costs resulting from the suspension plus a reasonable allowance for overhead with respect to such costs. [2003 c.794 §161]
0.0K chars
[Repealed or reserved.]
ORS 279C.660 Compensation when contract terminated due to public interest. When a public contract is terminated by mutual agreement, provision shall be made for the payment of compensation to the contractor. In addition to a reasonable amount of compensation for preparatory work and for all costs and expenses arising out of termination, the amount to be paid to the contractor
0.3K chars
(1) Shall be determined on the basis of the contract price in the case of any fully completed separate item or portion of the work for which there is a separate or unit contract price; and (2) May, with respect to any other work, be a percent of the contract price equal to the pe…
ORS 279C.665 Contractual provisions for compensation when contract terminated due to public interest. A contracting agency may provide in a public improvement contract detailed provisions under which the contractor shall be entitled, as a matter of right, to compensation upon termination of the contract on account of any reason considered to be in the public interest. [2003 c.794 §163]
0.0K chars
[Repealed or reserved.]
ORS 279C.670 Application of ORS 279C.650 to 279C.670. ORS 279C.650 to 279C.670 do not apply to suspension of the work or termination of the contract that occurs as a result of the contractor’s violation of federal, state or local statutes, ordinances, rules or regulations in existence at the time the contract was executed or as a result of violations of the terms of the contract. [2003 c.794 §164]
0.0K chars
PREVAILING WAGE RATE
ORS 279C.800 Definitions for ORS 279C.800 to 279C.870. As used in ORS 279C.800 to 279C.870
6.6K chars
(1) “Fringe benefits” means: (a) Contributions that a contractor or subcontractor makes irrevocably to a trustee or to a third person under a plan, fund or program; and (b) Costs that a contractor or subcontractor may reasonably be anticipated to incur in providing the following …
ORS 279C.805 Policy. The Legislative Assembly declares that the purposes of the prevailing rate of wage law are
0.6K chars
(1) To ensure that contractors compete on the ability to perform work competently and efficiently while maintaining community-established compensation standards. (2) To recognize that local participation in publicly financed construction and family wage income and benefits are es…
ORS 279C.807 Workforce diversity for public works projects. (1) The Bureau of Labor and Industries shall develop and adopt a plan to increase diversity statewide among workers employed on projects subject to ORS 279C.800 to 279C.870. The bureau shall develop the plan after conducting a statewide public process to solicit proposals to increase diversity and shall adopt the plan after considering proposals submitted to the bureau
0.7K chars
(2) The bureau shall report each year to the Legislative Assembly or to the appropriate legislative interim committee concerning progress that results from the plan adopted under this section and may submit recommendations for legislation or other measures that will improve diver…
ORS 279C.808 Rules. In accordance with applicable provisions of ORS chapter 183, the Commissioner of the Bureau of Labor and Industries shall adopt rules necessary to administer ORS 279C.800 to 279C.870. [2007 c.764 §45]
0.0K chars
[Repealed or reserved.]
ORS 279C.810 Exemptions; rules. (1) As used in this section
5.1K chars
(a) “Funds of a public agency” does not include: (A) Funds provided in the form of a government grant to a nonprofit organization, unless the government grant is issued for the purpose of construction, reconstruction, major renovation or painting; (B) Building and development per…
ORS 279C.815 Determination of prevailing wage; sources of information; comparison of state and federal prevailing wage; other powers of commissioner. (1) As used in this section
3.6K chars
(a) “Electrical worker” means an electrician, inside wireman, cable splicer, electrical welder, electrical material handler, lighting maintenance worker or limited energy electrician. (b) “Person” means an employer, a labor organization or an official representative of an employe…
ORS 279C.817 Determination of applicability of prevailing wage rate; time limitation; hearing; rules. (1) The Commissioner of the Bureau of Labor and Industries shall, upon the request of a public agency or other interested person, make a determination about whether a project or proposed project is or would be a public works on which payment of the prevailing rate of wage is or would be required under ORS 279C.840
1.0K chars
(2) The requester shall provide the commissioner with information necessary to enable the commissioner to make the determination. (3) The commissioner shall make the determination within 60 days after receiving the request or 60 days after the requester has provided the commissio…
ORS 279C.820 Advisory committee to assist commissioner. (1) The Commissioner of the Bureau of Labor and Industries shall appoint an advisory committee to assist the commissioner in the administration of ORS 279C.800 to 279C.870
0.3K chars
(2) The advisory committee must include equal representation of members from management and labor in the building and construction industry who perform work on public works contracts and such other interested parties as the commissioner shall appoint. [2003 c.794 §179]
ORS 279C.825 Fees; rules. (1)(a) The Commissioner of the Bureau of Labor and Industries, by order, shall establish a fee to be paid by the public agency that awards a public works contract subject to ORS 279C.800 to 279C.870. The commissioner shall use the fee to pay the costs of
0.9K chars
(A) Surveys to determine the prevailing rates of wage; (B) Administering and providing investigations under and enforcement of ORS 279C.800 to 279C.870; and (C) Providing educational programs on public contracting law under the Public Contracting Code. (b) The commissioner shall …
ORS 279C.827 Division of public works project; applicability of prevailing wage rate to divided projects. (1)(a) A person or public agency may not divide a public works project into more than one contract for the purpose of avoiding compliance with ORS 279C.800 to 279C.870
2.5K chars
(b) If the Commissioner of the Bureau of Labor and Industries determines that a person or public agency has divided a public works project into more than one contract for the purpose of avoiding compliance with ORS 279C.800 to 279C.870, the commissioner shall issue an order compe…
ORS 279C.829 Agreement with other state to pay less than prevailing rate of wage. Notwithstanding any other provision of law, a contracting agency may not enter into an agreement with another state or a political subdivision or agency of another state in which the contracting agency agrees that a contractor or subcontractor may pay less than the prevailing rate of wage determined in accordance with ORS 279C.815 under the terms of a contract for public works to which the contracting agency is a party or of which the contracting agency is a beneficiary. [2009 c.322 §2]
0.0K chars
[Repealed or reserved.]
ORS 279C.830 Provisions concerning prevailing rate of wage in specifications, contracts and subcontracts; applicability of prevailing wage; bond. (1)(a) Except as provided in paragraph (e) of this subsection, the specifications for every contract for public works must state the existing state prevailing rate of wage and, if applicable, the federal prevailing rate of wage required under the Davis-Bacon Act (40 U.S.C. 3141 et seq.) that must be paid to workers in each trade or occupation that the contractor or subcontractor or other person who is a party to the contract uses in performing all or part of the contract. If the prevailing rates of wage are available electronically or are accessible on the Internet, the specifications may incorporate the rates by referring to the electronically accessible or Internet-accessible rates and by providing adequate information about how to access the rates
2.6K chars
(b) If a public agency under paragraph (a) of this subsection must state the state and federal prevailing rates of wage in the specifications, the public agency shall also require the contractor to pay the higher of the applicable state or federal prevailing rate of wage to all w…
ORS 279C.835 Notifying commissioner of public works contract subject to prevailing wage; payment of fee. Public agencies shall notify the Commissioner of the Bureau of Labor and Industries in writing, on a form prescribed by the commissioner, whenever a contract subject to the provisions of ORS 279C.800 to 279C.870 has been awarded. The notification shall be made within 30 days of the date that the contract is awarded. The notification shall include payment of the fee required under ORS 279C.825 and a copy of the disclosure of first-tier subcontractors that was submitted under ORS 279C.370. [2003 c.794 §175; 2009 c.161 §3]
0.0K chars
[Repealed or reserved.]
ORS 279C.836 Public works bond; rules. (1) Except as provided in subsection (4), (7), (8) or (9) of this section, before starting work on a contract or subcontract for a public works project, a contractor or subcontractor shall file with the Construction Contractors Board a public works bond with a corporate surety authorized to do business in this state in the amount of $30,000. The bond must provide that the contractor or subcontractor will pay claims ordered by the Bureau of Labor and Industries to workers performing labor upon public works projects. The bond must be a continuing obligation, and the surety’s liability for the aggregate of claims that may be payable from the bond may not exceed the penal sum of the bond. The bond must remain in effect continuously until depleted by claims paid under this section, unless the surety sooner cancels the bond. The surety may cancel the bond by giving 30 days’ written notice to the contractor or subcontractor, to the board and to the Bureau of Labor and Industries. Canceling the bond relieves the surety of further liability for work performed on contracts entered into after the cancellation. The cancellation does not limit the surety’s liability for work performed on contracts entered into before the cancellation
4.3K chars
(2) Before permitting a subcontractor to start work on a public works project, the contractor shall verify that the subcontractor has filed a public works bond as required under this section, has elected not to file a public works bond under subsection (7) or (8) of this section …
ORS 279C.838 Applicability of state and federal rates of wage; determination of site of project; determination of applicability of wage to transportation workers; waiver. When a public works project is subject to the Davis-Bacon Act (40 U.S.C. 3141 et seq.)
1.6K chars
(1) If the state prevailing rate of wage is higher than the federal prevailing rate of wage, the contractor and every subcontractor on the project shall pay at least the state prevailing rate of wage as determined under ORS 279C.815; (2) The Commissioner of the Bureau of Labor an…
ORS 279C.840 Payment of prevailing rate of wage; posting of rates and fringe benefit plan provisions. (1) The hourly rate of wage that a contractor or subcontractor must pay to workers upon all public works may not be less than the prevailing rate of wage for an hour’s work in the same trade or occupation in the locality where the labor is performed. A contractor or subcontractor may discharge the obligation to pay the prevailing rate of wage by making the payments in cash, by making contributions of a type described in ORS 279C.800 (1)(a), or by assuming an enforceable commitment to bear the costs of fringe benefits of a type described in ORS 279C.800 (1)(b), or any combination of payments, contributions and assumption of costs, where the aggregate of any such payments, contributions and assumption of costs is not less than the prevailing rate of wage. The contractor or subcontractor shall pay all wages due and owing to the contractor’s or subcontractor’s workers upon public works on the regular payday established and maintained under ORS 652.120
3.2K chars
(2) After a contract for public works is executed with any contractor or work is commenced upon any public works, a contractor or subcontractor may not subject the amount of the prevailing rate of wage to attack in any legal proceeding in connection with that contract. (3) It is …
ORS 279C.845 Certified statements regarding payment of prevailing rates of wage; retainage. (1) The contractor or the contractor’s surety and every subcontractor or the subcontractor’s surety shall file certified statements with the public agency in writing, on a form prescribed by the Commissioner of the Bureau of Labor and Industries, certifying
3.4K chars
(a) The hourly rate of wage paid each worker whom the contractor or the subcontractor has employed upon the public works; and (b) That no worker employed upon the public works has been paid less than the prevailing rate of wage or less than the minimum hourly rate of wage specifi…
ORS 279C.850 Inspection to determine whether prevailing rate of wage being paid; civil action for failure to pay prevailing rate of wage or overtime. (1) At any reasonable time the Commissioner of the Bureau of Labor and Industries may enter the office or business establishment of any contractor or subcontractor performing public works and gather facts and information necessary to determine whether the prevailing rate of wage is actually being paid by such contractor or subcontractor to workers upon public works
1.3K chars
(2) Upon request by the commissioner, every contractor or subcontractor performing work on public works shall make available to the commissioner for inspection during normal business hours any payroll or other records in the possession or under the control of the contractor or su…