82 sections in this chapter.
ORS 543.010 Definitions for ORS 543.010 to 543.610. As used in ORS 543.010 to 543.610
1.2K chars
(1) “Actual original cost” includes the sum paid to the state at the time the application was made for a preliminary permit; the sum paid or secured to be paid to the state by the applicant for license at the time such application was made; such sums as may be paid to the United …
ORS 543.012 Applicability of chapter to reauthorization of existing hydroelectric project. (1) Except for the provisions of ORS 543.300, 543.310, 543.430, 543.440, 543.610, 543.650 to 543.685, 543.710, 543.720, 543.730 and 543.990, nothing in this chapter shall apply to the reauthorization of an existing project
0.4K chars
(2) All references in ORS 543.300, 543.310, 543.430, 543.440, 543.610, 543.650 to 543.685, 543.710, 543.720, 543.730 and 543.990 to a license or a license issued under ORS 543.010 to 543.610 also shall be considered a reference to a water right issued under ORS 468.065, 468B.040,…
ORS 543.013 Applicability of chapter and ORS chapter 543A to ocean renewable energy facility. The provisions of this chapter and ORS chapter 543A do not apply to an ocean renewable energy facility as defined in ORS 274.870 if
0.5K chars
(1) The facility is located within Oregon’s territorial sea, as defined in ORS 196.405; or (2) The facility is in an estuary, unless any part of the facility is not subject to a proprietary authorization issued by the Department of State Lands under ORS 274.873. [2015 c.386 §17] …
ORS 543.014 [2007 c.212 §2; 2009 c.405 §§1,2; repealed by 2015 c.386 §15]
0.0K chars
[Repealed or reserved.]
ORS 543.015 Policy. The Legislative Assembly declares that it is the policy of the State of Oregon
0.7K chars
(1) To protect the natural resources of this state from possible adverse impacts caused by the use of the waters of this state for the development of hydroelectric power. (2) To permit siting of hydroelectric projects subject to strict standards established to protect the natural…
ORS 543.017 Minimum standards for development of hydroelectric power; public interest considerations; rules. (1) In order to carry out the policy set forth in ORS 543.015, the following minimum standards shall apply to any action of the Water Resources Commission relating to the development of hydroelectric power in Oregon
4.5K chars
(a) The anadromous salmon and steelhead resources of Oregon shall be preserved. The commission shall not approve activity that may result in mortality or injury to anadromous salmon and steelhead resources or loss of natural habitat of any anadromous salmon and steelhead resource…
ORS 543.020 [Repealed by 1961 c.224 §20]
0.0K chars
[Repealed or reserved.]
ORS 543.030 [Repealed by 1961 c.224 §20]
0.0K chars
[Repealed or reserved.]
ORS 543.040 [Repealed by 1961 c.224 §20]
0.0K chars
[Repealed or reserved.]
ORS 543.050 Powers of Water Resources Commission as to permits, licenses, investigations, reports, forms and examination of records. The Water Resources Commission may
2.2K chars
(1) Issue preliminary permits, as provided in ORS 543.210 to 543.250, to any person qualified to become a licensee. (2) Issue licenses, as provided in ORS 543.260, to citizens of the United States, associations of citizens, or private corporations organized under the laws of the …
ORS 543.055 Hearings and witnesses. (1) The Water Resources Commission may hold hearings and take testimony orally, by deposition or in such other form as the commission considers satisfactory, either within or without this state. The Water Resources Commission may require, by subpoena, the attendance of witnesses and the production of documentary evidence
1.2K chars
(2) An administrative law judge assigned from the Office of Administrative Hearings established under ORS 183.605, shall conduct any contested case hearing that the commission is required or permitted by law to hold. The administrative law judge has the same powers with respect t…
ORS 543.060 Investigations; access to project, maps, books and other project data. The Water Resources Commission, the Water Resources Director or any employee of the Water Resources Department, at all reasonable times, shall have free access to any project, addition or betterment during or after construction or acquisition, and to all maps, plans, profiles, estimates, engineers’ reports, books, accounts, records and other data relating to the project. [1985 c.673 §142]
0.0K chars
[Repealed or reserved.]
ORS 543.070 [Repealed by 1975 c.581 §29]
0.0K chars
HYDROELECTRIC PROJECT FEES
ORS 543.075 Definitions for ORS 543.075 to 543.092. As used in ORS 543.075 to 543.092
1.6K chars
(1) “1998 dollar” means a dollar amount that when adjusted for inflation or deflation equals the value of a dollar in 1998. (2) “Holder” means a person authorized to operate a hydroelectric project under the authority of either a time-limited water right, a certificated water rig…
ORS 543.078 Annual fee for hydroelectric project. (1) On or before January 1 of each year, each holder shall pay to the State of Oregon an annual fee for each hydroelectric project that is subject to this section. The annual fee required by this section shall be based on the theoretical horsepower specified in the water right for each project
1.9K chars
(2) The amount of the annual fee required under subsection (1) of this section shall be determined in the following manner: (a) Subject to the adjustment required under this paragraph, for a project producing more than 123.5 theoretical horsepower each holder shall pay an amount …
ORS 543.080 Project specific fees; summary of project specific expenditures. (1) In addition to the annual fee set forth in ORS 543.078, a holder may be required to pay project specific fees
5.5K chars
(2) Project specific fees are fees that compensate a state agency for the agency’s reasonable and necessary oversight of a holder’s implementation of the protection, mitigation and enhancement measures included in a water right for the project, a certificate issued pursuant to OR…
ORS 543.082 Invoice for fees; overdue fee; interest on delinquent fees. (1) At least 45 days before the fees required under ORS 543.078 or 543.080 become due, the Water Resources Department shall issue invoices to the holder for each fee
1.6K chars
(2) If any holder fails to pay the fees required under ORS 543.078 or 543.080 within 15 days after the date specified in the invoice, the department shall notify the holder of the amount and nature of the overdue fee. Any such notice shall be sent to the holder by certified mail …
ORS 543.085 Periodic review of annual fee. (1) At least once every eight years the Water Resources Director shall appoint a review panel to review the amount of the annual fee established under ORS 543.078. The review panel shall consist of at least one representative from the following and others at the director’s discretion
1.6K chars
(a) The Department of Environmental Quality; (b) The State Department of Fish and Wildlife; (c) The Public Utility Commission; (d) The Water Resources Department; (e) Investor owned utilities; (f) Publicly owned utilities; (g) Municipalities; (h) Environmental organizations; (i) …
ORS 543.088 Payment of costs or fee for reauthorization or relicensing of project. (1) Notwithstanding ORS 543A.405 and 543A.410, during each year of the interim period established in subsection (2) of this section, any licensee or water right certificant seeking reauthorization of a state water right to operate a federally licensed hydroelectric project shall pay the greater of
3.0K chars
(a) The actual cost of the Hydroelectric Application Review Team’s reauthorization activities for the year in question as established pursuant to ORS 543A.405 and 543A.410; or (b) 12.5 cents per theoretical horsepower as specified in the water right for each project under conside…
ORS 543.090 Payment of expenses of Hydroelectric Application Review Team for project operating under federal license and state power claim or uncertificated claim. (1) Any project operating under a hydroelectric license issued by the Federal Energy Regulatory Commission and concurrently operating under the authority of a power claim or uncertificated claim shall pay all expenses related to the review and decision of a Hydroelectric Application Review Team established under ORS 543A.075 that
0.8K chars
(a) Are incurred by the team and any agency participating as part of the team in the federal relicensing process; and (b) Are not otherwise covered by a fee described in ORS 543.078. (2) Not later than six years before the expiration of a hydroelectric license issued by the Feder…
ORS 543.092 Amendment of hydroelectric water right or claim; rules; unilateral amendment of power claim or uncertificated claim to assess project specific fees. (1) Upon the request of the holder and the approval of the Water Resources Department, a hydroelectric water right or claim may be amended
0.6K chars
(2) The Water Resources Department shall develop rules governing the process by which a hydroelectric water right or claim may be amended. Any amendments under subsection (1) of this section shall: (a) Be consistent with the final unified state position for the project; (b) Be co…
ORS 543.095 Challenges to certain statutes related to hydroelectric projects. (1) As used in this section, “person” has the meaning given that term in ORS 174.100
1.4K chars
(2) No person shall be estopped or precluded from challenging the constitutionality or validity of any provision of chapter 449, Oregon Laws 1997, or the provisions of chapter 873, Oregon Laws 1999, as a result of having received or sought benefits under, complied with, paid fees…
ORS 543.110 Appropriation and use of water for power is governed by this chapter. After February 26, 1931, no right to appropriate or to use the waters of the lakes, rivers, streams or other bodies of water within this state, including water over which this state has concurrent jurisdiction, in connection with the development of any water power project for the generation of electricity, shall be initiated, perfected, acquired or held, except for and during the periods or extensions thereof stated in ORS 543.010 to 543.610, and pursuant to the provisions thereof
0.0K chars
[Repealed or reserved.]
ORS 543.120 Water power projects to be in conformity with this chapter. After February 26, 1931, no water power project involving the use of the waters of lakes, rivers, streams or other bodies of water within this state, including waters over which this state has concurrent jurisdiction, for the generation of electricity, shall be begun or constructed except in conformity with the provisions of ORS 543.010 to 543.610
0.0K chars
[Repealed or reserved.]
ORS 543.130 [Repealed by 1961 c.224 §20]
0.0K chars
[Repealed or reserved.]
ORS 543.135 [1961 c.100 §§2,3; repealed by 1985 c.673 §185]
0.0K chars
[Repealed or reserved.]
ORS 543.140 Projects or developments constructed by federal government excepted from law. The provisions of ORS 543.010 to 543.610 shall not apply to any water power project or development constructed by the United States
0.0K chars
[Repealed or reserved.]
ORS 543.150 Municipal corporations and utility districts; applicability of laws; powers of commission respecting districts. The provisions of ORS 543.010, 543.050, 543.210, 543.220, 543.250, 543.260 and 543.290 to 543.610 shall not apply to cities, towns or other municipal corporations of this state, including utility districts organized under section 12, Article XI, Oregon Constitution, and legislation enacted thereunder; saving, however, to such cities, towns and other municipal corporations the rights and preferences specified in ORS 543.260, 543.270 and 543.610. The Water Resources Commission shall exercise the powers in relation to utility districts as may be conferred upon the commission by any legislation providing for the creation of such utility districts. [Amended by 1985 c.673 §144; 1991 c.869 §7]
0.0K chars
[Repealed or reserved.]
ORS 543.160 Hydroelectric facility on North Santiam River prohibited; exception. (1) No person shall construct or maintain, and no officer or agency of the state shall issue any permit for the construction or maintenance of any hydroelectric facility or structure on the North Santiam River between river mile 27 and Big Cliff Dam
0.6K chars
(2) Nothing in subsection (1) of this section applies to any hydroelectric facility or structure constructed on the North Santiam River prior to October 15, 1983, to the historic uses of such a hydroelectric facility or structure or to the repair or reconstruction of such a hydro…
ORS 543.165 Hydroelectric facility on part of Deschutes River prohibited. No person, state agency, local government, district or municipal corporation shall construct, and no officer or agency of the state shall issue any permit for the construction of any hydroelectric facility or structure on the Deschutes River between river mile 172 below Lava Island Falls and river mile 227 below but not including Wickiup Dam. [1985 c.560 §1]
0.2K chars
Note: 543.165 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 543 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.
ORS 543.170 Hydroelectric facility on Isqúulktpe Creek prohibited. No person, state agency, local government, district or municipal corporation shall construct or maintain, and no officer or agency of the state shall issue any permit for the construction or maintenance of any hydroelectric facility or structure on Isqúulktpe Creek. [1985 c.560 §2; 2019 c.13 §54]
0.2K chars
Note: 543.170 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 543 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.
ORS 543.175 Hydroelectric facility on Deschutes River within City of Bend prohibited; exception. (1) Except as provided in subsection (2) of this section, no person, state agency, local government, district or municipal corporation shall construct or maintain, and no officer or agency of the state shall issue any permit for the construction or maintenance of any hydroelectric facility or structure on that portion of the Upper Deschutes River situated within the city limits of the City of Bend except for a facility that meets all of the following criteria
1.3K chars
(a) The facility is located on an existing irrigation diversion facility or structure constructed by persons. (b) The operation of the facility would not require any water in addition to water appropriated for irrigation purposes. (c) Operation of the facility would be limited to…
ORS 543.210 Preliminary permits; application; contents; fee. (1) Any person who proposes to operate a hydroelectric project in Oregon shall apply for a state preliminary permit. Any person who applies to the Federal Energy Regulatory Commission for a preliminary permit to operate a hydroelectric project shall, at the same time, apply for a state preliminary permit. The Water Resources Commission may issue a preliminary permit to any person possessing the qualifications of a licensee as specified in ORS 543.010 to 543.610
1.0K chars
(2) The application for a preliminary permit shall set forth: (a) The name and post-office address of the applicant; (b) The approximate site of any proposed dam or diversion; (c) The amount of water in cubic feet per second; (d) The theoretical horsepower; and (e) Any other data…
ORS 543.220 (1) If an application is made for a preliminary permit, after said application has been referred to hearing the Water Resources Commission shall give written notice of the filing of the application to
0.9K chars
(a) Any municipality or other person or corporation that, in the judgment of the commission, is likely to be interested in or affected by the proposed project; and (b) The owner of any land that is: (A) Adjacent to any portion of the stream in which the quantity of water will be …
ORS 543.225 Hearing on application; notice; policy. (1) The Water Resources Commission shall conduct a public hearing on any application or amended application for a preliminary permit or for a license for a major project of more than 100 theoretical horsepower and an application for preliminary permit or license for a minor project of less than 100 theoretical horsepower if the commission concludes it is in the public interest to do so
2.5K chars
(2) The commission shall give proper notice of the public hearing on an application under subsection (1) of this section, to the applicant and to each protestant, if any. After the hearing, if the commission determines that the proposed project does not comply with the standards …
ORS 543.230 Hearings on application; rules; protest. (1) The Water Resources Commission shall, by order or rule, provide for the time and manner of hearings upon applications. However, upon request by any person made within 30 days after the Water Resources Director issues an order pertaining to cumulative impacts under ORS 543.255, the Water Resources Commission shall conduct a contested case hearing in accordance with the applicable provisions of ORS chapter 183 and any rules adopted by the commission
1.4K chars
(2) Every application for the appropriation of water for the generation of electricity subject to the terms of ORS 543.010 to 543.610 shall be subject to protest or remonstrance on behalf of the public, or any district organized for public purposes, or any interested private pers…
ORS 543.240 [Repealed by 1991 c.869 §15]
0.0K chars
[Repealed or reserved.]
ORS 543.250 Permit; duration; transfer; cancellation; priority; terms and conditions; denial. A preliminary permit may be issued for a period not exceeding a total of three years. It shall not be transferable except upon written approval of the Water Resources Commission, and may be canceled by order of the commission at any time upon proof to the commission’s satisfaction, after hearing, that the holder is not in good faith complying with the provisions of the permit. The holder of a preliminary permit which has not been canceled shall have priority of right to make application for a license covering the project for which the preliminary permit was issued, within the term of the permit or any lawful extension thereof. Except as otherwise specified in ORS 543.010 to 543.610, the commission may fix the terms and conditions of any preliminary permit issued thereunder, and each preliminary permit issued shall set forth all the terms and conditions. The commission may decline to grant any application for a preliminary permit. [Amended by 1985 c.673 §149; 1993 c.63 §1]
0.0K chars
[Repealed or reserved.]
ORS 543.255 Determination of cumulative impacts of proposed hydroelectric power projects; consolidated review; applicability. (1) Whenever the Water Resources Department receives an application to appropriate water for a new hydroelectric project under ORS 537.140 to 537.320 or for a hydroelectric permit or license under ORS 543.010 to 543.610, the department shall determine whether the impacts of the project would be cumulative with
2.3K chars
(a) Impacts of other proposed hydroelectric projects for which an application is pending before the department; or (b) Existing hydroelectric projects in the same river basin. (2) If the department determines that there is no possibility that the hydroelectric projects proposed i…
ORS 543.257 [1985 c.569 §11; 1985 c.673 §194; repealed by 2007 c.354 §1]
0.0K chars
[Repealed or reserved.]
ORS 543.260 Licenses; duration; terms and conditions; termination; denial of application; preference of municipality or utility district. (1) A license may be issued by the Water Resources Commission to any qualified person for a period not exceeding 50 years. If the project is subject to regulation by the Federal Energy Regulatory Commission, the term shall be concurrent with and expire upon expiration of the federal license for the project. Each license shall be conditioned upon acceptance by the licensee of all the terms and conditions of ORS 543.010 to 543.610, and such further terms and conditions as the commission may prescribe, not inconsistent with those sections. All such terms and conditions, and their acceptance by the licensee, shall be expressed in the license. A license may be terminated for the reasons and in the manner provided in ORS 543.010 to 543.610. The form of license containing all the terms and conditions may be set forth in the preliminary permit
0.8K chars
(2) The commission may deny any application for a license if it appears that the applicant has failed to comply substantially with the terms and conditions of the preliminary permit or, notwithstanding the commission has issued a preliminary permit, if in the judgment of the comm…
ORS 543.265 Testing of fish protection measures as condition for hydroelectric project permit or license; scope and cost. The Water Resources Department shall impose as a condition to any water right permit to appropriate water for hydroelectric purposes granted under ORS 537.211 or any license granted under ORS 543.260 that the person operating the hydroelectric project shall, during the operational lifetime of the project, perform or allow the State Department of Fish and Wildlife to perform, any tests or studies required by the department to evaluate the effectiveness of measures for the protection of fish. The scope and cost of these studies will be negotiated between the State Department of Fish and Wildlife and the operator. [1985 c.674 §6; 1987 c.158 §116; 1995 c.416 §40]
0.2K chars
Note: 543.265 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 543 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.
ORS 543.270 Preference in granting permit or license; municipal use. In issuing preliminary permits, and in issuing licenses where no preliminary permit is held by an applicant for a license, preference shall be given to the application which appears to the Water Resources Commission to be best adapted to conserve and utilize the water power involved. However, any application for the use of water made by any municipal corporation of this state under any law of the state, before a preliminary permit is issued, or before a license is issued when no preliminary permit upon the proposed project has been issued, shall always have preference. [Amended by 1985 c.673 §151]
0.0K chars
[Repealed or reserved.]
ORS 543.280 Fee payments by licensee. (1) Any person who applies to the Federal Energy Regulatory Commission for a preliminary permit to operate a hydroelectric project shall, at the same time, apply for a state preliminary permit. An applicant for a state preliminary permit for a new hydroelectric project shall submit to the Water Resources Commission a complete copy of any application for the project filed with the Federal Energy Regulatory Commission or other federal agency. For preliminary permits, if the copy of the federal application is filed with the commission at the same time it is filed with the federal agency, at the commission’s discretion, such copy may fulfill the requirements of ORS 543.210, except for the fee requirement in ORS 543.210 (4)
2.5K chars
(2) An applicant for a preliminary permit or license for a project or for a permit to appropriate water for power purposes shall pay to the state a project fee based on the capacity of the project to cover costs of recording, publishing notices, conducting the hearing required by…
ORS 543.290 Filing of maps, plans, estimates and other materials; incorporation as part of license; alteration; further statements and data. The applicant for a license shall submit to and file with the Water Resources Commission
0.8K chars
(1) All maps, plans, specifications and cost estimates as may be required by the commission for a full understanding of the proposed project. The maps, plans and specifications, when approved by the commission, shall become a part of the license, if one is issued upon the applica…
ORS 543.300 Conditions governing license; fees; waiver of conditions. Any license issued under ORS 543.010 to 543.610 shall take into consideration, and shall be on, the following conditions
3.5K chars
(1) That the proposed project shall be such as, in the judgment of the Water Resources Commission, is well adapted to the development and utilization of the water power involved. (2) That the licensee shall construct and build the project according to the maps, plans and specific…
ORS 543.310 Disposition of moneys collected. Except as provided in ORS 536.015, all moneys collected under the provisions of ORS 543.010 to 543.610 shall forthwith be paid to the State Treasurer and become a part of the General Fund. [Amended by 1985 c.674 §10; 1991 c.869 §10]
0.0K chars
[Repealed or reserved.]
ORS 543.320 Effect of amendment or repeal of law. The right to alter, amend or repeal ORS 543.010 to 543.610, or any part thereof, hereby is expressly reserved; but no such alteration, amendment or repeal shall affect any license theretofore issued under the provisions of ORS 543.010 to 543.610, or the rights of any licensee thereunder, unless expressly assented to by the licensee
0.1K chars
TIME FOR CONSTRUCTION; TERMINATION, REVOCATION OR TRANSFER OF LICENSE
ORS 543.410 Construction of project; time for commencement and completion; supply of service; extension of time; nonperformance; termination of license. (1) The licensee shall commence the construction of the project works within the time fixed in the license, which shall not be more than two years from the date thereof, shall thereafter in good faith and with due diligence prosecute such construction, and shall, within the time fixed in the license, complete and put into operation such part of the ultimate development as the Water Resources Commission considers necessary to supply the reasonable needs of the then available market, and shall, from time to time thereafter construct such portion of the balance of the development as the commission directs, so as to supply adequately the reasonable market demands until development is completed
0.7K chars
(2) The period for commencement of construction may be extended once but not longer than two additional years, and the period for the completion of construction carried on in good faith and with reasonable diligence may be extended by the commission when not incompatible with the…
ORS 543.420 Noncompletion of construction within prescribed time; judicial proceedings; sale of property; disposition of proceeds; rights of purchaser. If construction of a project under license has been begun but has not been completed within the time prescribed in the license or in any lawful extension thereof, then the Attorney General, upon request of the Water Resources Commission, shall institute proceedings in the circuit court for the county in which some part of the project is situated, for termination of the rights of the licensee under the license, the sale of the property embraced in the project, and for such other relief as the case may demand. Any judgment or decree entered in the proceeding shall provide for distribution of the proceeds of the sale to the parties equitably entitled thereto. The purchaser at any such sale shall take the property subject to all the terms and conditions of the license under which construction was begun, except insofar as they may be modified by the commission. [Amended by 1985 c.673 §156]
0.0K chars
[Repealed or reserved.]