Title 41 › Subtitle Subtitle III— Contract Disputes › Chapter 71— CONTRACT DISPUTES › § 7104
A contractor can challenge a contracting officer’s decision (the one in section 7103) by appealing to the agency board described in section 7105. The appeal must be filed within 90 days after the contractor gets the decision. Instead of that appeal, a contractor may file a lawsuit in the United States Court of Federal Claims, unless the defendant is the Tennessee Valley Authority; then the suit must be in a U.S. district court under 28 U.S.C. §1337. Any such lawsuit must be filed within 12 months of getting the contracting officer’s decision, and the court will hear the case anew under its normal rules.
Full Legal Text
Public Contracts — Source: USLM XML via OLRC
Legislative History
Reference
Citation
41 U.S.C. § 7104
Title 41 — Public Contracts