Mountain Valley Pipeline Eyes 31-Mile Gas Boost: Speak Up!
Published Date: 2/24/2025
Notice
Summary
Mountain Valley Pipeline wants to build a new 31-mile natural gas pipeline and related facilities to boost energy delivery. This $524 million project will serve two big customers with guaranteed gas transport every day. If you want to speak up or get involved, you need to act before the set deadline!
Analyzed Economic Effects
4 provisions identified: 3 benefits, 0 costs, 1 mixed.
State Water Quality Certifications Required
The project requires a Clean Water Act section 401 water quality certification from the Virginia Department of Environmental Quality and the North Carolina Department of Environmental Quality. Mountain Valley must submit copies of each request and either the certifying agency's decision or evidence of waiver to the Commission.
Commenting and Intervention Deadline
You can file comments, protests, or a motion to intervene in the Mountain Valley Pipeline proceeding with no fee. The deadline to file a motion to intervene or submit comments or protests is 5:00 p.m. Eastern Time on March 11, 2025; filing comments alone does not make you a party, and only intervenors can seek rehearing or later challenge Commission orders.
Environmental Review Timing and Notices
Within 90 days of this notice, Commission staff will either complete the environmental review and place it in the public record or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule is issued, it will identify the anticipated date for the final environmental impact statement or environmental assessment, and federal authorizations must be completed within 90 days after issuance of the FEIS or EA.
Public Notice: Project Size and Firm Capacity
The Southgate Amendment Project is described as approximately 31.3 miles of 30-inch pipeline with ancillary facilities, and Mountain Valley estimates the total project cost at $524,137,766; the project is fully subscribed under two precedent agreements providing a total of 550,000 dekatherms per day of firm transportation capacity.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-22879, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies like ATCO, Emera, and Google Energy. These filings include requests for approvals, complaints, and updates on company statuses. If you’re involved or interested, note the comment deadlines in November—they could affect how energy businesses operate and possibly impact prices or services.
2026-22878, ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is investigating whether ConocoPhillips’ electricity rates are fair or not. If found unfair, refunds could be required starting from November 10, 2026. Anyone interested has 21 days to join the case and share their views.
2026-22877, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from natural gas companies about rate changes and reports. These updates could affect customers and businesses by changing pipeline rates or how penalties are handled, with some changes starting as soon as October 2026. If you want to speak up or get involved, you need to comment by specific deadlines in November or January.
2026-22803, Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Northern Illinois Hydropower, LLC asked for more time to start and finish building their Brandon Road Hydroelectric Project in Illinois. The project sits on federal land near Rockdale and needs approval from the Federal Energy Regulatory Commission (FERC). People have until December 4, 2026, to share their thoughts or objections, so this extension could affect the project’s timeline and future energy plans.
2026-22791, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates from Texas Eastern Transmission and Enable Gas Transmission. These filings propose changes to contracts and rates starting November 1 or 5, 2026, which could affect customers and companies using these pipelines. If you want to speak up or get involved, you need to act by November 16, 2026.
2026-22721, Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Expansion Project
Transcontinental Gas Pipe Line Company wants to build new pipeline facilities in Pennsylvania to move more natural gas from the Marcellus Shale area. The government is preparing an environmental review to make sure the project is safe and will finish it by March 26, 2027. If all goes well, final approvals should happen by June 24, 2027, affecting local communities and energy customers with potential new energy options.
Previous / Next Documents
Previous: 2025-03005, Pacific Gas and Electric Company; Notice of Reasonable Period of Time for Water Quality Certification Application
Pacific Gas and Electric Company asked California for permission to make sure their project won’t harm water quality. California has one year, until January 21, 2026, to approve or deny this request. If they don’t decide by then, the approval is automatically given, which could speed up the project and save time and money.
Next: 2025-03007, Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Natural Gas Pipeline Company of America, LLC Gulf Coast Storage Expansion Project
The Federal Energy Regulatory Commission is asking the public for comments on the environmental effects of a new natural gas storage expansion in Harrison County, Texas. This project could change how natural gas is stored and used in the Gulf Coast area, and your input will help shape the environmental review. Make sure to send your thoughts by March 20, 2025, so they count!