Argent LNG wants to build new energy facilities in Lafourche Parish, Louisiana, and the government is asking the public to share their thoughts on how this might affect the environment. People have until February 9, 2026, to send in comments about possible impacts and ideas to reduce harm. This feedback will help decide if the project is a good idea and how it should move forward.
Analyzed Economic Effects
5 provisions identified: 3 benefits, 2 costs, 0 mixed.
Project land footprint and property use
The planned terminal would be constructed on about 269.9 acres within an 885.5-acre leased property; marine facilities would impact 147.1 acres (127.4 acres within the leased site and 19.7 acres in the Belle Pass Channel). The project would include about 0.7 mile of new dual 16-inch natural gas interconnect pipelines and Argent LNG would maintain about 445 acres for permanent operations with the remaining acreage restored. Affected landowners (potential right-of-way grantors, owners whose property may be used temporarily, or owners of homes within certain distances of aboveground facilities) are included on the environmental mailing list.
New marine berths and navigation
The project would build marine facilities and two new berths capable of accommodating LNG carriers up to 260,000 cubic meters and would affect 19.7 acres in the Belle Pass Channel. FERC staff has identified marine transportation as a preliminary issue to study in the environmental review.
NEPA review will evaluate many impacts
FERC staff will prepare an environmental document (an Environmental Assessment or an Environmental Impact Statement if an application is filed) that will evaluate geology and soils; water resources and wetlands; vegetation and wildlife; threatened and endangered species; cultural resources; socioeconomics; land use; air quality and noise; and reliability and safety. Staff has already listed marine transportation, socioeconomic effects, and construction effects on water, wetlands, and marine species as issues to consider.
Public comment deadline and process
You can send written comments about the planned Argent LNG Project to FERC by 5:00 p.m. Eastern Time on February 9, 2026. Comments can be filed using FERC's eComment or eFiling systems or mailed referencing docket PF25-11-000; if you submitted comments before September 8, 2025 you must refile them in Docket No. PF25-11-000 to ensure they are considered.
Historic property and tribal consultation
FERC has initiated consultation under Section 106 of the National Historic Preservation Act with the applicable State Historic Preservation Office(s) and is soliciting views from Indian tribes, government agencies, and the public on potential effects to historic properties. The environmental document will summarize findings and the status of these consultations.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-22879, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies like ATCO, Emera, and Google Energy. These filings include requests for approvals, complaints, and updates on company statuses. If you’re involved or interested, note the comment deadlines in November—they could affect how energy businesses operate and possibly impact prices or services.
2026-22878, ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is investigating whether ConocoPhillips’ electricity rates are fair or not. If found unfair, refunds could be required starting from November 10, 2026. Anyone interested has 21 days to join the case and share their views.
2026-22877, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from natural gas companies about rate changes and reports. These updates could affect customers and businesses by changing pipeline rates or how penalties are handled, with some changes starting as soon as October 2026. If you want to speak up or get involved, you need to comment by specific deadlines in November or January.
2026-22803, Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Northern Illinois Hydropower, LLC asked for more time to start and finish building their Brandon Road Hydroelectric Project in Illinois. The project sits on federal land near Rockdale and needs approval from the Federal Energy Regulatory Commission (FERC). People have until December 4, 2026, to share their thoughts or objections, so this extension could affect the project’s timeline and future energy plans.
2026-22791, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates from Texas Eastern Transmission and Enable Gas Transmission. These filings propose changes to contracts and rates starting November 1 or 5, 2026, which could affect customers and companies using these pipelines. If you want to speak up or get involved, you need to act by November 16, 2026.
2026-22721, Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Expansion Project
Transcontinental Gas Pipe Line Company wants to build new pipeline facilities in Pennsylvania to move more natural gas from the Marcellus Shale area. The government is preparing an environmental review to make sure the project is safe and will finish it by March 26, 2027. If all goes well, final approvals should happen by June 24, 2027, affecting local communities and energy customers with potential new energy options.
Previous / Next Documents
Previous: 2026-00475, Notice of Final Adoption and Effective Date for Updates to the Submission Guidelines
The National Capital Planning Commission updated its Submission Guidelines, which agencies use to submit development plans for review. These changes take effect on February 12, 2026, and help make the process clearer and smoother—no extra costs involved. If you’re part of a government agency submitting projects, get ready to follow the new rules starting soon!
Next: 2026-00478, Appraisal Subcommittee Notice of Meeting
The Appraisal Subcommittee is holding a special closed meeting on January 20, 2026, to discuss important personnel matters. This meeting affects the people who work with the Subcommittee and could lead to changes in staff or leadership. It’s a virtual meeting, so no travel costs, but the decisions made might impact how the Subcommittee operates going forward.