Clarksville Gas Seeks Pipeline to Kentucky with Rule Simplification
Published Date: 1/14/2026
Notice
Summary
Clarksville Natural Gas Utility wants to build a new pipeline crossing from Tennessee into Kentucky to boost gas service for current and future customers. They’re also asking for special treatment to simplify their rules and reporting. If you’re in the area or interested, you’ve got until the deadline to speak up or get involved!
Analyzed Economic Effects
2 provisions identified: 2 benefits, 0 costs, 0 mixed.
Pipeline to increase gas capacity
If you are a customer in Clarksville's Tennessee local distribution company service area or in the small Kentucky area served by Clarksville, the project is a single 12-inch-diameter pipeline that will connect to a city gate station about 25 feet over the Tennessee/Kentucky border in Todd County, Kentucky. The Project will allow Clarksville to increase its capacity to serve existing and future customers.
How to comment, protest, or intervene
You may file comments, protests, or a motion to intervene about the project at no fee; the deadline to file a motion to intervene is 5:00 p.m. Eastern Time on January 30, 2026. Only intervenors have the right to request rehearing of Commission orders in this proceeding and to later challenge Commission orders in the U.S. Circuit Courts of Appeal.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-20744, Combined Notice of Filings #2
The Federal Energy Regulatory Commission got a new filing from Iroquois Gas Transmission about changing their natural gas rates starting November 1, 2026. This affects customers and companies using their pipeline, who might see new negotiated prices. If you want to speak up or get involved, you have until October 19, 2026, to file your comments or protests.
2026-20580, Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Ventura to Farmington A-Line Abandonment and Capacity Replacement Project and Northern Lights 2027 Expansion Project
Northern Natural Gas Company plans to retire old pipeline sections in Iowa and Minnesota and build new ones to keep gas flowing smoothly and add extra capacity. This project will affect local communities and the environment but aims to do so responsibly, with a decision expected after public comments by November 2, 2026. The upgrades will help deliver more natural gas reliably, supporting energy needs without major environmental harm.
2026-20658, Shoshone Irrigation District; Notice of Existing Licensee's Failure To File a Timely Notice of Intent To File a New License Application, and Soliciting Notices of Intent To File a License Application and Pre-Application Documents
The Shoshone Irrigation District missed the deadline to say if they want to renew their license for the Garland Canal hydro project in Wyoming, which ends in 2031. Because of this, they’re treated as if they don’t plan to relicense, opening the door for others to step in and apply. If you’re interested, now’s the time to file your intent and get your paperwork ready!
2026-20659, Eastern Shore Natural Gas Company; Notice of Application and Establishing Intervention Deadline
Eastern Shore Natural Gas is planning a big upgrade to its pipelines in Pennsylvania, Delaware, and Maryland, including building new loops and replacing old pipes. This $75 million project will boost gas delivery for local utilities and customers, with new facilities and some old parts being removed. If you want to have a say, you need to act before the intervention deadline set by the Federal Energy Regulatory Commission.
2026-20582, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from several natural gas pipeline companies about rate changes and agreements that could affect how much customers pay starting this fall. If you want to speak up or get involved, you need to comment by mid-October or late October depending on the case. These updates impact pipeline rates and contracts, so keep an eye on deadlines to have your say!
2026-20642, Combined Notice of Filings
The Federal Energy Regulatory Commission got a new filing from Colorado Interstate Gas Company about changing a gas pipeline agreement that starts November 16, 2026. People who want to speak up or join the discussion must do so by October 14, 2026. This could affect gas rates and contracts, so keep an eye on the deadline if you’re involved!
Previous / Next Documents
Previous: 2026-00560, Tygart LLC; Notice of Availability of Environmental Assessment
Tygart LLC wants to update the design of their hydroelectric project at Tygart Dam in West Virginia by adding a fish exclusion net and changing turbine types, but the power output won’t change. The government reviewed the plan and says it won’t harm the environment if certain protections are followed. People affected can check the details and must send comments by February 9, 2026.
Next: 2026-00563, Agency Information Collection Activities; Revision of a Currently Approved Collection: Biographic Information (for Deferred Action)
USCIS is updating the form that collects basic info from people asking for Deferred Action, a special immigration status. They’re asking the public to comment on these changes by February 13, 2026. This update won’t cost extra money but helps keep the process smooth and clear for applicants.