Louisiana LNG Terminal Eyes Big Export Capacity Jump
Published Date: 1/22/2026
Notice
Summary
Venture Global CP2 LNG wants to boost its LNG export terminal in Louisiana from 28 to 35 million tons per year. This means more natural gas can be shipped out, which could impact local jobs and energy markets. If you want to speak up or get involved, you’ve got 90 days to jump in before the deadline!
Analyzed Economic Effects
2 provisions identified: 1 benefits, 0 costs, 1 mixed.
LNG Export Capacity Increased to 35 MTPA
Venture Global CP2 LNG asked FERC to raise the plant's peak liquefaction capacity from 28.0 million metric tons per annum (MTPA) to 35.0 MTPA at the CP2 Export Terminal in Cameron Parish, Louisiana. The notice says this means more natural gas can be shipped out and could impact local jobs and energy markets.
You Can Comment or Intervene by Feb 6, 2026
Any person may file comments, protests, or a motion to intervene in Docket CP26-55-000 by 5:00 p.m. Eastern Time on February 6, 2026. The notice says there is no fee or cost to file comments or intervene, and it explains electronic and paper filing options.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-22879, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies like ATCO, Emera, and Google Energy. These filings include requests for approvals, complaints, and updates on company statuses. If you’re involved or interested, note the comment deadlines in November—they could affect how energy businesses operate and possibly impact prices or services.
2026-22878, ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is investigating whether ConocoPhillips’ electricity rates are fair or not. If found unfair, refunds could be required starting from November 10, 2026. Anyone interested has 21 days to join the case and share their views.
2026-22877, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from natural gas companies about rate changes and reports. These updates could affect customers and businesses by changing pipeline rates or how penalties are handled, with some changes starting as soon as October 2026. If you want to speak up or get involved, you need to comment by specific deadlines in November or January.
2026-22803, Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Northern Illinois Hydropower, LLC asked for more time to start and finish building their Brandon Road Hydroelectric Project in Illinois. The project sits on federal land near Rockdale and needs approval from the Federal Energy Regulatory Commission (FERC). People have until December 4, 2026, to share their thoughts or objections, so this extension could affect the project’s timeline and future energy plans.
2026-22791, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates from Texas Eastern Transmission and Enable Gas Transmission. These filings propose changes to contracts and rates starting November 1 or 5, 2026, which could affect customers and companies using these pipelines. If you want to speak up or get involved, you need to act by November 16, 2026.
2026-22721, Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Expansion Project
Transcontinental Gas Pipe Line Company wants to build new pipeline facilities in Pennsylvania to move more natural gas from the Marcellus Shale area. The government is preparing an environmental review to make sure the project is safe and will finish it by March 26, 2027. If all goes well, final approvals should happen by June 24, 2027, affecting local communities and energy customers with potential new energy options.
Previous / Next Documents
Previous: 2026-01146, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates from companies like Columbia Gas of Virginia and Northern Natural Gas. These filings could change how much customers pay starting as soon as January 16, 2026. If you want to speak up or get involved, you need to act by the listed deadlines in early February.
Next: 2026-01148, Sunshine Act Meetings
The U.S. International Development Finance Corporation canceled its closed meeting that was set for January 21, 2026. This change affects anyone tracking or involved in the meeting, with no new date or costs announced. If you wanted to attend or follow the meeting, now you know it’s off!