Transcontinental Gas Pipe Line Company wants to build a new 3.38-mile pipeline loop and upgrade a compressor station in Pennsylvania to boost gas delivery by 183,100 dekatherms daily. The project will cost about $54.7 million and could change transportation rates. If you’re interested, you’ve got 90 days to speak up or get involved!

Analyzed Economic Effects

3 provisions identified: 1 benefits, 0 costs, 2 mixed.

New Capacity and Proposed Rate Change

Transcontinental proposes a project that will add 183,100 dekatherms per day of firm natural gas transportation capacity and is seeking authorization for an incremental recourse rate. The company estimates the Project cost at $54.7 million and has proposed an incremental recourse rate that could change transportation rates for shippers and customers.

Local Construction in Luzerne County, Pennsylvania

The Project would construct approximately 3.38 miles of 42-inch-diameter pipeline loop (the Diamond Loop), modify Compressor Station 515 (including pig launcher/receiver and tie-ins), and build a new mainline valve site, all located in Luzerne County, Pennsylvania. These specific construction activities and locations are identified in the application and may be of direct interest to landowners, residents, or recreationists in the area.

Public Comment and Intervention Rights

Anyone (individuals, organizations, businesses, municipalities) may file comments, protests, or a motion to intervene in Docket CP26-576-000 at no fee. The deadline to file a motion to intervene or submit comments or protests is 5:00 p.m. Eastern Time on October 13, 2026; timely intervenors gain party rights including the ability to request rehearing and challenge Commission orders.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
Effective Date
9/24/2026
10/13/2026

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register