New Pipeline Loop in PA: Speak Now or Forever Pipe Down
Published Date: 9/24/2026
Notice
Summary
Transcontinental Gas Pipe Line Company wants to build a new 3.38-mile pipeline loop and upgrade a compressor station in Pennsylvania to boost gas delivery by 183,100 dekatherms daily. The project will cost about $54.7 million and could change transportation rates. If you’re interested, you’ve got 90 days to speak up or get involved!
Analyzed Economic Effects
3 provisions identified: 1 benefits, 0 costs, 2 mixed.
New Capacity and Proposed Rate Change
Transcontinental proposes a project that will add 183,100 dekatherms per day of firm natural gas transportation capacity and is seeking authorization for an incremental recourse rate. The company estimates the Project cost at $54.7 million and has proposed an incremental recourse rate that could change transportation rates for shippers and customers.
Local Construction in Luzerne County, Pennsylvania
The Project would construct approximately 3.38 miles of 42-inch-diameter pipeline loop (the Diamond Loop), modify Compressor Station 515 (including pig launcher/receiver and tie-ins), and build a new mainline valve site, all located in Luzerne County, Pennsylvania. These specific construction activities and locations are identified in the application and may be of direct interest to landowners, residents, or recreationists in the area.
Public Comment and Intervention Rights
Anyone (individuals, organizations, businesses, municipalities) may file comments, protests, or a motion to intervene in Docket CP26-576-000 at no fee. The deadline to file a motion to intervene or submit comments or protests is 5:00 p.m. Eastern Time on October 13, 2026; timely intervenors gain party rights including the ability to request rehearing and challenge Commission orders.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-19575, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates and refunds from companies like National Fuel Gas and Columbia Gas. These filings include rate changes and special requests that could affect how much customers pay starting as soon as September 19, 2026. If you want to speak up or get involved, you need to act by September 30, 2026.
2026-19581, LED Enterprises, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Planned Yuma Pipeline Project, and Notice of Public Scoping Session
LED Enterprises plans to build the Yuma Pipeline in Arizona, and the government wants your thoughts on how it might affect the environment. If you live in Maricopa or Yuma Counties, this could impact your community, so now’s the time to speak up before October 21, 2026. Your input will help decide if the project moves forward and how it might change the area.
2026-19447, Cheniere Corpus Christi Pipeline, LP, Corpus Christi Liquefaction Stage IV, LLC, Corpus Christi Liquefaction, LLC; Notice of Availability of the Draft Environmental Impact Statement for the Proposed Corpus Christi Liquefaction Stage 4 Project and the CCPL Expansion Project
Cheniere and partners want to grow their Corpus Christi LNG terminal in Texas by building a new 26-mile natural gas pipeline, a compressor station, and other facilities. This project aims to boost LNG production to meet global energy needs. People can share their thoughts on the environmental report by November 9, 2026, as the government reviews the plan to keep things safe and green.
2026-19440, High Island Offshore System, L.L.C.; Notice of Application and Establishing Intervention Deadline
High Island Offshore System, L.L.C. wants to officially stop using about 287 miles of old offshore pipelines near Texas and Louisiana because they’re no longer needed for federal oversight. This change affects companies and communities relying on these pipelines and kicks off a 90-day review period where people can speak up. No big money changes yet, but the clock is ticking for anyone who wants to get involved!
2026-19244, Combined Notice of Filings
The Federal Energy Regulatory Commission got a new rate filing from Elba Express Company about natural gas pipeline charges, set to start October 1, 2026. If you want to speak up or join the discussion, you need to act by September 28, 2026. This could affect pipeline users and might change costs, so don’t miss the deadline to have your say!
2026-19280, Brown Bear II Hydro, Inc.; Notice of Reasonable Period of Time for Water Quality Certification Application
Brown Bear II Hydro, Inc. asked Maine’s environmental agency for permission to ensure their project keeps water clean. Maine has one year, until August 27, 2027, to approve or deny this request. If they don’t decide by then, their say is waived, speeding up the project’s progress without extra delays or costs.
Previous / Next Documents
Previous: 2026-19578, Health Center Program Performance Period Extensions
Health centers with current funding ending between December 2026 and February 2027 will get extra money and time to keep serving their communities without interruption. These 272 centers will get about $527 million total, extending their support through mid-2027 while they apply for new funding. This move ensures patients keep getting care smoothly while HRSA sorts out the next round of awards.
Next: 2026-19581, LED Enterprises, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Planned Yuma Pipeline Project, and Notice of Public Scoping Session
LED Enterprises plans to build the Yuma Pipeline in Arizona, and the government wants your thoughts on how it might affect the environment. If you live in Maricopa or Yuma Counties, this could impact your community, so now’s the time to speak up before October 21, 2026. Your input will help decide if the project moves forward and how it might change the area.