Hydro Permit Application Filed for NY Canal Project
Published Date: 2/12/2025
Notice
Summary
NOW NE005 LLC wants to study building a new hydroelectric power project on the Champlain Canal and Hudson River in New York. This preliminary permit gives them first dibs to apply for a full license but doesn’t let them start construction yet. People have 60 days to share their thoughts or compete before the project moves forward, which could bring clean energy and new infrastructure to the area.
Analyzed Economic Effects
4 provisions identified: 4 benefits, 0 costs, 0 mixed.
Preliminary Permit Gives Filing Priority
NOW NE005 LLC filed for a preliminary permit (docket P-15384) on November 27, 2024. If issued, the preliminary permit gives the permit holder priority to file a full license application during the permit term, but it does not itself allow construction.
Permit Does Not Allow Construction or Trespass
A preliminary permit does not authorize the permit holder to perform land‑disturbing activities or to enter onto lands or waters owned by others without the owners' express permission. This means landowners in the project area cannot be entered or disturbed by the permit holder without giving permission.
New Hydropower Capacity and Infrastructure
The proposed Lock and Dam C1 Hydroelectric Project would add two new turbine‑generator units of 5,100 kilowatts each and is projected to generate 39.79 gigawatt‑hours annually. The proposal also includes a new 97-by-170-foot powerhouse, a 75-by-60-foot substation, and a new 34.5‑kilovolt, approximately 1.9‑mile transmission line in Saratoga and Rensselaer Counties, New York.
FERC Office Offers Public Participation Help
The Commission's Office of Public Participation (OPP) can help members of the public — including landowners, community organizations, and Tribal members — access information and navigate FERC filing and participation processes. The notice lists OPP contact options, including phone (202-502-6595) and an email address for assistance.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-20421, PJM Interconnection, L.L.C.; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is checking if PJM Interconnection’s new rules for buying backup power are fair and legal. This affects energy companies and customers in the PJM region, with possible changes to how costs are shared. If refunds are needed, they start from October 6, 2026, and anyone interested has 21 days to speak up.
2026-20453, Southern Star Central Gas Pipeline, Inc.; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Evergy McNew Power Plant Delivery Project
Southern Star Central Gas Pipeline wants to build new gas facilities to deliver power to the Evergy McNew Power Plant in Kansas. The government is asking the public to share their thoughts on how this might affect the environment before making a final decision. If you care about local air, water, or land, now’s the time to speak up by November 2, 2026!
2026-20450, Transcontinental Gas Pipe Line Company, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Leidy Access Expansion Project
Transcontinental Gas Pipe Line Company wants to expand its gas pipeline in Luzerne, Pennsylvania, and the government is asking the public to share their thoughts on how this might affect the environment. People have until November 2, 2026, to send in comments about possible impacts and better ways to do the project. This feedback will help decide if the project moves forward and how it’s done safely and responsibly.
2026-20420, Combined Notice of Filings
The Federal Energy Regulatory Commission got several filings from natural gas pipeline companies about rate changes and refunds. These updates affect customers and companies using pipelines, with new rates starting as soon as October 1, 2026. If you want to comment, deadlines are mostly mid-October, so act fast to have your say on possible price changes.
2026-20418, BIF III Holtwood LLC; Notice of Application for Non-Project Use of Project Land and Waters Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
BIF III Holtwood LLC wants to build docks on land and water near the Wallenpaupack Hydroelectric Project in Pennsylvania. The government is reviewing this request and asking the public to share their thoughts by October 30, 2026. This could change how the land and water are used but won’t affect electricity prices or timing.
2026-20416, Commission Information Collection Activities (FERC-603); Comment Request; Extension
FERC is renewing its info collection form called FERC-603, which helps protect important energy infrastructure details. No changes are planned, but folks who submit this info should know the deadline to comment is November 5, 2026. This keeps the process smooth without adding extra costs or paperwork.
Previous / Next Documents
Previous: 2025-02515, Notice of Filing; Western Area Power Administration
The Western Area Power Administration wants to update its power rates starting April 1, 2025. If you’re a customer or interested party, you can speak up or join the discussion by March 6, 2025. This change could affect how much you pay for power, so don’t miss your chance to weigh in!
Next: 2025-02517, Pacific Gas & Electric Company; Notice of Application for Temporary Flow Modification Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Pacific Gas & Electric wants to temporarily change how much water flows through its Drum-Spaulding Hydroelectric Project on rivers in Northern California. This affects local communities and the environment near Auburn, Colfax, Grass Valley, and Nevada City. People have until March 10, 2025, to share their thoughts or get involved before any changes happen.