The law covers qualifying large data centers that begin operating on or after July 1, 2026. These centers withdraw at least 75 acre-feet yearly and meet the law’s facility, building-size, infrastructure, ownership, and land requirements. Before approving their land-use applications, local authorities must notify both state water divisions and the relevant water provider by mail or email. Operators must give the area’s water provider written notice 90 to 360 days before construction begins. They must also report location, estimated yearly withdrawals, discharge treatment and temperature, and water reuse or replacement plans to the Division of Water Rights.
The state must notify data center operators when required preconstruction or annual reports are missing or incomplete. Operators who still fail to file complete reports face fines of up to $100 per day. Each day may count as a separate violation. The state engineer can enforce these reporting duties and act against unlicensed well drilling, unlawful water use, dam-safety violations, and specified reporting or water-distribution violations. Enforcement does not cover direct rain capture that follows local laws, avoids existing water rights, and holds stormwater for absorption or release without beneficial use. Initial orders describe violations and potential penalties; they are exempt from the state Administrative Procedures Act. Enforcement rules must provide a hearing right and timely final orders after nonresponse or correction; outside parties cannot intervene. Final orders receive a fresh court review in Salt Lake County or the county of violation, with petitions due within 20 days. The engineer can seek court enforcement, and winning parties may recover court costs and reasonable attorney fees.
Beginning July 1, 2026, qualifying new data centers must file yearly reports after operations begin. Reports are due July 1 for the previous calendar year and cover actual withdrawals, water-saving efforts, applicable pollution protections, and rule-required information. This reporting requirement does not apply when the state engineer requires water-data reports under another law by rule. By September 1, the Division of Water Rights must publish each reported center’s water withdrawals for the previous year. Specified information stays protected when operators meet state records-law requirements; additional rule-required information is protected only when the rule allows it. The division must publish protected data in anonymous county totals and provide it to affected cities and counties. It must also share nonproprietary report information with the Division of Water Quality and the relevant water provider.
Jill Koford
Republican • House
John Arthur
Democratic • House
Jennifer Dailey-Provost
Democratic • House
James A. Dunnigan
Republican • House
Joseph Elison
Republican • House
Jake Fitisemanu
Democratic • House
Sahara Hayes
Democratic • House
Jason B. Kyle
Republican • House
Lee, T.
Affiliation unavailable
Clinton Okerlund
Republican • House
Stephanie Pitcher
Democratic • Senate
Scott D. Sandall
Republican • Senate
David Shallenberger
Republican • House
Jason E. Thompson
Republican • House
All Roll Calls
Yes: 198 • No: 22
Senate vote • 3/5/2026
Senate/ motion to reconsider
Yes: 0 • No: 0
Senate vote • 3/5/2026
Senate/ passed 2nd & 3rd readings/ suspension
Yes: 19 • No: 5
Senate vote • 3/5/2026
Senate/ uncircled
Yes: 0 • No: 0
House vote • 3/5/2026
House/ concurs with Senate amendment
Yes: 62 • No: 2
Senate vote • 3/5/2026
Senate/ failed
Yes: 13 • No: 15
Senate vote • 3/4/2026
Senate/ circled
Yes: 0 • No: 0
Senate vote • 3/3/2026
Senate Comm - Favorable Recommendation
Yes: 4 • No: 0
Senate vote • 3/3/2026
Senate Comm - Substitute Recommendation
Yes: 4 • No: 0
House vote • 1/29/2026
House/ passed 3rd reading
Yes: 72 • No: 0
House vote • 1/22/2026
House Comm - Amendment Recommendation
Yes: 8 • No: 0
House vote • 1/22/2026
House Comm - Favorable Recommendation
Yes: 8 • No: 0
House vote • 1/22/2026
House Comm - Substitute Recommendation
Yes: 8 • No: 0
Governor Signed
House/ to Governor
House/ received enrolled bill from Printing
House/ enrolled bill to Printing
Enrolled Bill Returned to House or Senate
Draft of Enrolled Bill Prepared
Bill Received from House for Enrolling
House/ signed by Speaker/ sent for enrolling
House/ received from Senate
Senate/ to House
Senate/ signed by President/ returned to House
Senate/ received from House
House/ to Senate
House/ concurs with Senate amendment
House/ placed on Concurrence Calendar
House/ received from Senate
Senate/ to House with amendments
Senate/ passed 2nd & 3rd readings/ suspension
Senate/ placed on 2nd Reading Calendar
Senate/ motion to reconsider
Senate/ to House
Senate/ failed
Senate/ uncircled
Senate/ circled
Senate/ 2nd & 3rd readings/ suspension
Enrolled
3/11/2026
Substitute #3
3/2/2026
Substitute #2
2/11/2026
Amended 1/23/2026 11:01:94
1/23/2026
Substitute #1
1/22/2026
Introduced
12/23/2025